1211 N KINGSLEY DR 90029
Certificate Information: 1211 N KINGSLEY DR 90029
- Application / Permit
- 19010-20000-04552
- Plan Check / Job No.
- B19VN17554
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SFD/ GAR
- Permit Issued
- Issued on 7/27/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/11/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2019 | CHON CHIO KUO |
| Corrections Issued | 10/28/2019 | CHON CHIO KUO |
| Quality Review Completed | 10/29/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 10/29/2019 | APPLICANT |
| Green Plans Picked Up | 10/29/2019 | APPLICANT |
| Applicant returned to address corrections | 8/17/2020 | CHON CHIO KUO |
| Applicant returned to address corrections | 2/25/2021 | CHON CHIO KUO |
| Applicant returned to address corrections | 3/31/2021 | CHON CHIO KUO |
| Plan Check Approved | 4/13/2021 | CHON CHIO KUO |
| Issued | 7/27/2023 | APPLICANT |
| CofO in Progress | 6/6/2025 | CRAIG VAUGHAN |
| Permit Finaled | 6/11/2025 | DEROLD HAUFF |
| CofO Issued | 6/11/2025 | DEROLD HAUFF |
| Permit Finaled | 6/11/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/29/2019 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 10/29/2019 | JEANIE LAM |
| Highway dedication | Cleared | 10/29/2019 | JEANIE LAM |
| Permit | Cleared | 10/29/2019 | JEANIE LAM |
| Sewer availability | Cleared | 10/29/2019 | JEANIE LAM |
| Green Code | Cleared | 3/25/2020 | MICHAEL AYERS |
| Frnt yard landscape/Water mgmt | Cleared | 7/2/2020 | DENZEL HENDERSON |
| Hydrant and Access approval | Cleared | 7/7/2020 | JOHN CONNEALLY |
| Roof/Waste drainage to street | Cleared | 7/17/2020 | CECILIO NAVARRO |
| Low Impact Development | Cleared | 12/14/2022 | JORGE MEJIA LEMUS |
Contact Information
| Contractor | C S W F Construction Inc; Lic. No.: 1021458-B | 15831 SAN JOSE AVE LA PUENTE, CA 91744 |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 2445 VIA SONOMA PALOS VERDES ESTATES, CA 90274 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/14/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Underground Mechanical | 8/14/2023 | Partial Approval | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 8/31/2023 | Approved | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 8/31/2023 | Approved | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2023 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2024 | No Access for Inspection | BRIAN SULLIVAN |
| Deputy Wood Construction | 1/9/2024 | Conditional Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2024 | Corrections Issued | BRIAN SULLIVAN |
| Wood Frame | 2/2/2024 | Partial Approval | STUART CHAPMAN |
| Interior/Exterior Lathing | 2/9/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 2/22/2024 | No Access for Inspection | ROY SPAULDING |
| Interior/Exterior Lathing | 2/22/2024 | No Access for Inspection | ROY SPAULDING |
| ELECTRICAL-Rough | 2/26/2024 | Not Ready for Inspection | ROY SPAULDING |
| Interior/Exterior Lathing | 2/26/2024 | Not Ready for Inspection | ROY SPAULDING |
| ELECTRICAL-Rough | 2/27/2024 | Not Ready for Inspection | ROY SPAULDING |
| HVAC-Rough | 2/27/2024 | Not Ready for Inspection | ROY SPAULDING |
| Interior/Exterior Lathing | 2/27/2024 | Not Ready for Inspection | ROY SPAULDING |
| HVAC-Rough | 4/8/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 4/8/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 4/9/2024 | Approved | ROY SPAULDING |
| HVAC-Rough | 4/9/2024 | Corrections Issued | ROY SPAULDING |
| Interior/Exterior Lathing | 4/9/2024 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 4/9/2024 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 4/11/2024 | Not Ready for Inspection | ROY SPAULDING |
| Green Building Rough | 4/11/2024 | Not Ready for Inspection | ROY SPAULDING |
| HVAC-Rough | 4/11/2024 | Not Ready for Inspection | ROY SPAULDING |
| Verify Sprinkler Sign Off | 4/11/2024 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 4/12/2024 | Partial Approval | ROY SPAULDING |
| HVAC-Final | 4/12/2024 | Approved | ROY SPAULDING |
| Insulation | 4/18/2024 | Approved | ROY SPAULDING |
| Drywall Nailing | 4/26/2024 | Approved | ROY SPAULDING |
| Green Building Rough | 4/26/2024 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 5/7/2024 | Not Ready for Inspection | ROY SPAULDING |
| Interior/Exterior Lathing | 5/30/2024 | Not Ready for Inspection | ROY SPAULDING |
| Interior/Exterior Lathing | 6/3/2024 | Approved | ROY SPAULDING |
| Shower Pan | 6/3/2024 | Approved | ROY SPAULDING |
| Sewer | 6/27/2024 | Approved | ROY SPAULDING |
| Underground Mechanical | 6/27/2024 | Approved | ROY SPAULDING |
| Underground Mechanical | 9/23/2024 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 5/2/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Final | 5/2/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 5/9/2025 | Approved | CRAIG VAUGHAN |
| Final | 5/9/2025 | Corrections Issued | CRAIG VAUGHAN |
| Gas Test | 5/9/2025 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 5/9/2025 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 5/9/2025 | SGSOV Approved | CRAIG VAUGHAN |
| Service/Power Release | 5/9/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Smoke Detectors | 5/9/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 5/15/2025 | Corrections Issued | CRAIG VAUGHAN |
| Service/Power Release | 5/15/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Smoke Detectors | 5/15/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 5/19/2025 | Corrections Issued | CRAIG VAUGHAN |
| Service/Power Release | 5/19/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Smoke Detectors | 5/19/2025 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 5/20/2025 | Approved | CRAIG VAUGHAN |
| Final | 5/20/2025 | Conditional Approval | CRAIG VAUGHAN |
| Gas Test | 5/20/2025 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 5/20/2025 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 5/20/2025 | Approved | CRAIG VAUGHAN |
| Service/Power Release | 5/20/2025 | Approved | CRAIG VAUGHAN |
| Final | 6/5/2025 | OK to Issue CofO | CRAIG VAUGHAN |