6687 W COLGATE AVE 90048

Certificate Information: 6687 W COLGATE AVE 90048

Application / Permit
19010-20000-04529
Plan Check / Job No.
B19VN17483
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 35'-6" X 57'-1" (2) STORY SINGLE FAMILY DWELLING; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 12/23/2019
Issuing Office
Valley
Current Status
CofO Issued on 10/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/10/2019 APPLICANT
Green Plans Picked Up 10/23/2019 APPLICANT
Assigned to Plan Check Engineer 10/24/2019 SELLA BENYAMIN
Corrections Issued 10/29/2019 SELLA BENYAMIN
Quality Review Completed 10/29/2019 STEVEN KIM
Building Plans Picked Up 10/30/2019 APPLICANT
Applicant returned to address corrections 12/2/2019 SELLA BENYAMIN
Plan Check Approved 12/11/2019 SELLA BENYAMIN
Issued 12/23/2019 LADBS
CofO in Progress 10/15/2021 KENNETH NAGLE
Permit Finaled 10/15/2021 KENNETH NAGLE
CofO Issued 10/15/2021 KENNETH NAGLE
Permit Finaled 10/15/2021 KENNETH NAGLE

Permit Application Clearance Information

Address approval Cleared 11/5/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 11/5/2019 GUILLERMO PETRA
Permit Cleared 11/5/2019 GUILLERMO PETRA
Sewer availability Cleared 11/5/2019 GUILLERMO PETRA
Trees in Parkway Cleared 11/17/2019 ADRIAN SANCHEZ
Abandoned oil well Cleared 11/21/2019 GEORGE SUCHAND
Abandoned oil well approval Cleared 11/21/2019 GEORGE SUCHAND
Low Impact Development Cleared 11/26/2019 ANDRES COVARRUBIAS
Hydrant and Access approval Cleared 12/2/2019 GEORGE SUCHAND
Green Code Cleared 12/5/2019 MICHAEL AYERS
Roof/Waste drainage to street Cleared 12/5/2019 MARKOS PEREZ-BRAN
ZI Cleared 12/5/2019 DAISY BENICIA

Contact Information

Contractor Robin Jonathan; Lic. No.: 1053635-B 470 S BEDFORD DR #401      BEVERLY HILLS, CA 90212

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/29/2020 Not Ready for Inspection EVAN COOPER
METHANE-Barrier 1/29/2020 Not Ready for Inspection EVAN COOPER
METHANE-Subgrade 1/29/2020 Not Ready for Inspection EVAN COOPER
Footing/Foundation/Slab 2/13/2020 Corrections Issued EVAN COOPER
METHANE-Barrier 2/13/2020 Not Ready for Inspection EVAN COOPER
METHANE-Subgrade 2/13/2020 Not Ready for Inspection EVAN COOPER
Footing/Foundation/Slab 2/26/2020 Partial Approval EVAN COOPER
METHANE-Barrier 2/26/2020 Not Ready for Inspection EVAN COOPER
METHANE-Subgrade 2/26/2020 Partial Approval EVAN COOPER
PLUMBING-Rough 4/10/2020 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 4/17/2020 Partial Approval EVAN COOPER
Special/Order Compliance 4/17/2020 Corrections Issued EVAN COOPER
Deputy Methane Barrier 4/27/2020 Conditional Approval EVAN COOPER
Special/Order Compliance 5/4/2020 Approved EVAN COOPER
Excavation/Setback/Form/Re-Bar 5/5/2020 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 5/27/2020 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 7/24/2020 Conditional Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 7/31/2020 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 8/6/2020 Not Ready for Inspection EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 8/6/2020 Partial Approval EVAN COOPER
Green Building Rough 8/6/2020 Not Ready for Inspection EVAN COOPER
METHANE-Rough 8/6/2020 Not Ready for Inspection EVAN COOPER
Verify Sprinkler Sign Off 8/6/2020 Not Ready for Inspection EVAN COOPER
HVAC-Rough 9/4/2020 Approved EVAN COOPER
PLUMBING-Rough 9/9/2020 Approved EVAN COOPER
ELECTRICAL-Rough 10/22/2020 Approved EVAN COOPER
BUILDING-Rough-Frame 11/2/2020 Partial Approval EVAN COOPER
Green Building Rough 11/2/2020 Partial Approval EVAN COOPER
Insulation 11/16/2020 Corrections Issued EVAN COOPER
Insulation 11/24/2020 Approved EVAN COOPER
Interior/Exterior Lathing 11/24/2020 Approved EVAN COOPER
Drywall Nailing 12/1/2020 Approved EVAN COOPER
Gas Test 6/10/2021 Approved KEVIN SARGSYAN
HVAC-Final 7/27/2021 Corrections Issued KEVIN SARGSYAN
Gas Test 8/19/2021 Approved KEVIN SARGSYAN
PLUMBING-Final 8/19/2021 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Final 9/1/2021 Approved EVAN COOPER
HVAC-Final 9/1/2021 Approved EVAN COOPER
Service/Power Release 9/1/2021 Approved EVAN COOPER
BUILDING-Rough-Frame 9/15/2021 Approved EVAN COOPER
Deputy Methane Barrier 9/15/2021 Approved EVAN COOPER
Excavation/Setback/Form/Re-Bar 9/15/2021 Approved EVAN COOPER
Final 9/15/2021 Partial Inspection EVAN COOPER
Footing/Foundation/Slab 9/15/2021 Approved EVAN COOPER
Green Building Final 9/15/2021 Approved EVAN COOPER
Green Building Rough 9/15/2021 Approved EVAN COOPER
METHANE-Barrier 9/15/2021 Approved EVAN COOPER
METHANE-Final 9/15/2021 Approved EVAN COOPER
METHANE-Rough 9/15/2021 Approved EVAN COOPER
METHANE-Subgrade 9/15/2021 Approved EVAN COOPER
PLUMBING-Final 9/15/2021 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 9/15/2021 SGSOV Approved EVAN COOPER
Smoke Detectors 9/15/2021 Approved EVAN COOPER
Verify Sprinkler Sign Off 9/15/2021 Approved EVAN COOPER
Final 10/15/2021 OK to Issue CofO KENNETH NAGLE