6606 N MATILIJA AVE 91405
Certificate Information: 6606 N MATILIJA AVE 91405
- Application / Permit
- 19010-20000-04523
- Plan Check / Job No.
- B19VN17431
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- NEW 24' X 20' DETACHED GARAGE PER WEPP.
- Permit Issued
- Issued on 9/2/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/20/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/10/2019 | PINANK PATEL |
| Plan Check Approved | 10/10/2019 | PINANK PATEL |
| Issued | 9/2/2020 | APPLICANT |
| CofO in Progress | 9/2/2021 | JENNIFER RABUCHIN |
| Permit Finaled | 9/20/2021 | MICHAEL SMITH |
| CofO Issued | 9/20/2021 | MICHAEL SMITH |
| Permit Finaled | 9/20/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/10/2019 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 10/10/2019 | SAFA JAVANMARDI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/15/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Footing/Foundation/Slab | 10/15/2020 | Approved | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2020 | Partial Inspection | WILLIAM KUEHN |
| Green Building Rough | 11/6/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 11/16/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| ELECTRICAL-Rough | 11/16/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2020 | Partial Inspection | WILLIAM KUEHN |
| Green Building Rough | 11/16/2020 | No Access for Inspection | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 12/8/2020 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 12/8/2020 | Approved | MICHEL ABAJAN |
| Green Building Rough | 12/8/2020 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 12/15/2020 | Partial Approval | BEAU COLLINS |
| Drywall Nailing | 12/30/2020 | Approved | MISAEL ESPARZA |
| Final | 4/21/2021 | Not Ready for Inspection | JOHN HAYES |
| Green Building Final | 4/21/2021 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 4/21/2021 | SGSOV Not Ready | JOHN HAYES |
| Service/Power Release | 4/21/2021 | Not Ready for Inspection | JOHN HAYES |
| Smoke Detectors | 4/21/2021 | Not Ready for Inspection | JOHN HAYES |
| Final | 5/27/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 5/27/2021 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 5/27/2021 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Service/Power Release | 5/27/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Smoke Detectors | 5/27/2021 | Approved | JENNIFER RABUCHIN |
| Final | 8/24/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 8/24/2021 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 8/24/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Final | 9/2/2021 | OK to Issue CofO | JENNIFER RABUCHIN |
| Service/Power Release | 9/2/2021 | Approved | JENNIFER RABUCHIN |