5400 N CARPENTER AVE #1-16 91607

Certificate Information: 5400 N CARPENTER AVE #1-16 91607

Application / Permit
19010-20000-04516
Plan Check / Job No.
B19VN17355
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
(N) 4-STORY TYPE V-A 16-UNIT (TOC TIER 3: 2-EXTREMELY LOW INCOME & 1-LOW INCOME UNITS) APARMENT BUILDING OVER 2 -LEVEL TYPE I-A BASEMENT PARKING (NFPA-13 FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 10/12/2022
Issuing Office
Valley
Current Status
CofO Issued on 1/31/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/9/2019 APPLICANT
Assigned to Plan Check Engineer 10/31/2019 NILOOFAR MEHRAIN
Green Plans Picked Up 11/6/2019 APPLICANT
Disabled Access Plans Picked Up 11/13/2019 APPLICANT
Corrections Issued 11/14/2019 NILOOFAR MEHRAIN
Quality Review Completed 11/14/2019 GUANG MIN TUNG
Building Plans Picked Up 11/15/2019 APPLICANT
Applicant returned to address corrections 9/23/2022 NILOOFAR MEHRAIN
Plan Check Approved 10/6/2022 NILOOFAR MEHRAIN
Issued 10/12/2022 APPLICANT
TCO Issued (Expire Date: 04-09-2025) 10/11/2024 RICKEY JACKSON
CofO in Progress 1/29/2025 JOHN KITCKO
Permit Finaled 1/31/2025 JEFFREY DURAN
CofO Issued 1/31/2025 JEFFREY DURAN
Permit Finaled 1/31/2025 JEFFREY DURAN

Permit Application Clearance Information

Address approval Cleared 11/19/2019 LEE GUILBEAUX
Encroachment in public way Cleared 11/19/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 11/19/2019 LEE GUILBEAUX
Sewer availability Cleared 11/19/2019 LEE GUILBEAUX
DAS Clearance Cleared 3/16/2021 NORLITO MEDRANO
Green Code Cleared 3/16/2021 MICHAEL AYERS
Building over 3-story or 36-ft Cleared 5/25/2021 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 5/25/2021 CALOSHA APPROVED
Disturb/Remove Protected Trees Cleared 6/4/2021 STEPHEN DUPREY
Hydrant and Access approval Cleared 9/2/2021 KURT CORRAL
Highway dedication Cleared 9/14/2021 LEE GUILBEAUX
Permit Cleared 9/14/2021 LEE GUILBEAUX
Trees in Parkway Cleared 10/21/2021 ADALBERTO VERA
Fire Marshall Fire Life Safety Cleared 1/19/2022 VIDAL GARCIA
Miscellaneous Cleared 4/11/2022 STEVEN WECHSLER
Miscellaneous Cleared 4/11/2022 STEVEN WECHSLER
Tract Map conditions Cleared 4/11/2022 STEVEN WECHSLER
ZI Cleared 4/11/2022 STEVEN WECHSLER
DCP conditions approval Cleared 4/20/2022 RICHARD TRUONG
Density Bonus 12.22.A.31 Cleared 4/20/2022 RICHARD TRUONG
Low Impact Development Cleared 5/5/2022 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 5/5/2022 JOHN LIN
Work Adjacent to Public Way Cleared 6/28/2022 JOSE RODRIGUEZ
"Q" conditions Cleared 8/29/2022 STEVEN WECHSLER
Opn space landscape/Water mgmt Cleared 8/29/2022 STEVEN WECHSLER
Specific Plan Cleared 8/29/2022 STEVEN WECHSLER

Contact Information

Contractor Alpa Construction Inc; Lic. No.: 708299-B PO BOX 2548      VAN NUYS, CA 91404
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065
Engineer Warling,, Jeffrey Paul; Lic. No.: C43743 2828 COCHRAN STREET 321      SIMI VALLEY, CA 93065

Inspector Information

DEANDRE HOFFMAN, (818) 374-1182 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/15/2022 Partial Inspection JOHN KITCKO
Special/Order Compliance 12/15/2022 Approved BRIAN KELLY
Excavation/Setback/Form/Re-Bar 12/21/2022 Not Ready for Inspection JOHN KITCKO
Footing/Foundation/Slab 12/23/2022 Partial Inspection JOHN KITCKO
Deputy Reinf. Concrete 12/27/2022 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 12/27/2022 Not Ready for Inspection JOHN KITCKO
Pre-Inspection 12/28/2022 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 12/29/2022 Approved JOHN KITCKO
Footing/Foundation/Slab 12/29/2022 Partial Approval JOHN KITCKO
Excavation/Setback/Form/Re-Bar 1/10/2023 Corrections Issued JOHN KITCKO
Footing/Foundation/Slab 1/11/2023 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 1/12/2023 Approved JOHN KITCKO
Deputy Shotcrete 1/12/2023 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 1/17/2023 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 1/18/2023 Approved JOHN KITCKO
Deputy Shotcrete 1/18/2023 Approved JOHN KITCKO
Pre-Inspection 1/18/2023 Not Ready for Inspection JOHN KITCKO
Deputy Reinf. Concrete 1/19/2023 Approved JOHN KITCKO
Deputy Shotcrete 1/19/2023 Approved JOHN KITCKO
Footing/Foundation/Slab 1/19/2023 Partial Approval JOHN KITCKO
Special/Order Compliance 1/19/2023 Partial Approval STEVEN LEVITT
Pre-Inspection 1/20/2023 Not Ready for Inspection JOHN KITCKO
Special/Order Compliance 1/20/2023 Not Ready for Inspection STEVEN LEVITT
Excavation/Setback/Form/Re-Bar 1/25/2023 Conditional Approval JOHN KITCKO
Deputy Reinf. Concrete 1/26/2023 Approved JOHN KITCKO
Deputy Reinf. Concrete 1/27/2023 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 1/31/2023 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 2/6/2023 Approved JOHN KITCKO
Footing/Foundation/Slab 2/7/2023 Corrections Issued JOHN KITCKO
Excavation/Setback/Form/Re-Bar 2/8/2023 Partial Approval JOHN KITCKO
Deputy Shotcrete 2/14/2023 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 2/17/2023 Corrections Issued JOHN KITCKO
Excavation/Setback/Form/Re-Bar 2/20/2023 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 2/20/2023 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 2/21/2023 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 3/10/2023 Partial Inspection JOHN KITCKO
Deputy Reinf. Concrete 3/13/2023 Approved JOHN KITCKO
Pre-Inspection 3/14/2023 Not Ready for Inspection JOHN KITCKO
Deputy Reinf. Concrete 3/16/2023 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 3/16/2023 Conditional Approval JOHN KITCKO
Special/Order Compliance 3/16/2023 Partial Approval BRIAN KELLY
Special/Order Compliance 3/16/2023 Partial Approval STEVEN LEVITT
Special/Order Compliance 3/16/2023 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 3/17/2023 Approved JOHN KITCKO
Deputy Reinf. Concrete 3/20/2023 Approved JOHN KITCKO
Deputy Shotcrete 3/28/2023 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 3/29/2023 Not Ready for Inspection JOHN KITCKO
Deputy Shotcrete 3/30/2023 Approved JOHN KITCKO
Footing/Foundation/Slab 3/30/2023 Partial Approval JOHN KITCKO
Deputy Shotcrete 3/31/2023 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 4/26/2023 Partial Approval JOHN KITCKO
Special/Order Compliance 4/26/2023 Partial Approval STEVEN LEVITT
Deputy Reinf. Concrete 4/28/2023 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 5/1/2023 Not Ready for Inspection ANDREW DORSO
Deputy Reinf. Concrete 5/2/2023 Approved JOHN KITCKO
Footing/Foundation/Slab 5/2/2023 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 5/3/2023 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 5/22/2023 Partial Approval JOHN KITCKO
Deputy Wood Construction 5/23/2023 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 6/7/2023 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 6/15/2023 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 7/6/2023 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 7/17/2023 Not Ready for Inspection JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 7/19/2023 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 7/25/2023 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 7/28/2023 Partial Approval JOHN KITCKO
Drywall Nailing 8/2/2023 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 8/15/2023 Partial Approval JOHN KITCKO
Insulation 9/7/2023 Partial Approval JOHN KITCKO
Insulation 9/11/2023 Partial Approval JOHN KITCKO
Insulation 9/12/2023 Partial Approval JOHN KITCKO
Insulation 9/14/2023 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 9/19/2023 Partial Approval JOHN KITCKO
Pre-Inspection 9/22/2023 Partial Inspection JOHN KITCKO
Drywall Nailing 10/10/2023 Partial Approval JOHN KITCKO
Insulation 10/10/2023 Partial Approval JOHN KITCKO
Insulation 10/11/2023 Partial Inspection JOHN KITCKO
Wood Frame 10/12/2023 Partial Inspection JOHN KITCKO
Interior/Exterior Lathing 11/8/2023 Partial Inspection DEANDRE HOFFMAN
Insulation 11/13/2023 Partial Approval JOHN KITCKO
Green Building Rough 11/17/2023 Not Ready for Inspection ANDREW DORSO
Insulation 11/17/2023 Partial Inspection ANDREW DORSO
Verify Sprinkler Sign Off 11/17/2023 Not Ready for Inspection ANDREW DORSO
Wood Frame 11/17/2023 Partial Inspection ANDREW DORSO
Green Building Rough 11/21/2023 Approved JOHN KITCKO
Insulation 11/21/2023 Partial Approval JOHN KITCKO
Verify Sprinkler Sign Off 11/21/2023 Approved JOHN KITCKO
Wood Frame 11/21/2023 Partial Approval JOHN KITCKO
Drywall Nailing 11/27/2023 Partial Inspection ANDREW DORSO
Drywall Nailing 12/1/2023 Partial Approval JOHN KITCKO
Drywall Nailing 12/8/2023 Partial Inspection ANDREW DORSO
Interior/Exterior Lathing 12/8/2023 Partial Inspection ANDREW DORSO
Drywall Nailing 12/14/2023 Not Ready for Inspection JOHN KITCKO
Drywall Nailing 12/18/2023 Partial Approval JOHN KITCKO
Wood Frame 1/29/2024 Partial Approval JOHN KITCKO
Interior/Exterior Lathing 2/12/2024 Partial Approval JOHN KITCKO
Wood Frame 3/15/2024 Partial Approval JOHN KITCKO
Light Gage Steel Frame 4/19/2024 Partial Approval JOHN KITCKO
Drywall Nailing 5/1/2024 Partial Approval JOHN KITCKO
Special/Order Compliance 5/15/2024 Partial Approval JOHN KITCKO
Special/Order Compliance 5/20/2024 Partial Approval JOHN KITCKO
Special/Order Compliance 6/24/2024 Partial Inspection JOHN KITCKO
Final 9/19/2024 Not Ready for Inspection JOHN KITCKO
Footing/Foundation/Slab 9/19/2024 Approved JOHN KITCKO
Green Building Final 9/19/2024 Approved JOHN KITCKO
Reinforced Concrete Frame 9/19/2024 Approved JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 9/19/2024 SGSOV Approved JOHN KITCKO
Smoke Detectors 9/19/2024 Approved JOHN KITCKO
Wood Frame 9/19/2024 Approved JOHN KITCKO
Special/Order Compliance 9/27/2024 Partial Inspection JOHN KITCKO
Final 10/9/2024 OK for TCO JOHN KITCKO
Final 1/29/2025 OK to Issue CofO JOHN KITCKO