455 S CITRUS AVE 90036

Certificate Information: 455 S CITRUS AVE 90036

Application / Permit
19010-20000-04502
Plan Check / Job No.
B19VN17273
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW (78'-6"'x 32'-0") TWO- STORY SINGLE FAMILY DWELLING WITH BASEMENT NFPA-13D FIRE SPRINKLERED THROUGH-OUT. WORK PER ENGINEER.
Permit Issued
Issued on 2/28/2020
Issuing Office
Valley
Current Status
CofO Issued on 11/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/8/2019 APPLICANT
Assigned to Plan Check Engineer 10/31/2019 TROY DEGUZMAN
Corrections Issued 11/7/2019 TROY DEGUZMAN
Green Plans Picked Up 11/12/2019 APPLICANT
Quality Review Completed 11/14/2019 CHON CHIO KUO
Building Plans Picked Up 11/18/2019 APPLICANT
Applicant returned to address corrections 1/15/2020 TROY DEGUZMAN
Plan Check Approved 2/25/2020 TROY DEGUZMAN
Issued 2/28/2020 LADBS
CofO in Progress 10/27/2022 MICHAEL LEWIS
Permit Finaled 11/6/2022 DEROLD HAUFF
CofO Issued 11/6/2022 DEROLD HAUFF
Permit Finaled 11/6/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/12/2019 ADRIAN CASTRO
CPC Cleared 12/12/2019 ANNA VAN
Eng Process Fee Ord 176,300 Cleared 12/12/2019 ADRIAN CASTRO
Sewer availability Cleared 12/12/2019 ADRIAN CASTRO
ZI Cleared 12/12/2019 ANNA VAN
Green Code Cleared 12/26/2019 AARON COSTA
Hydrant and Access approval Cleared 1/6/2020 GILBERT URREA
Low Impact Development Cleared 1/14/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 1/14/2020 ERIK BEASLEY
Excavation more than 5-ft deep Cleared 2/24/2020 CALOSHA APPROVED

Contact Information

Contractor David Elliot Builders Inc; Lic. No.: 1021000-B 5967 W 3RD ST #360      LOS ANGELES, CA 90036
Engineer Tuchscher,, James Todd; Lic. No.: C77649 5503 E 2ND ST      LONG BEACH, CA 90803

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/4/2020 Partial Approval ARTHUR SARGSYAN
Deputy Methane Barrier 5/8/2020 Approved ARTHUR SARGSYAN
Underground Mechanical 5/8/2020 Approved ARTHUR SARGSYAN
Footing/Foundation/Slab 6/3/2020 Approved ARTHUR SARGSYAN
METHANE-Barrier 6/3/2020 Approved ARTHUR SARGSYAN
METHANE-Subgrade 6/3/2020 Approved ARTHUR SARGSYAN
Deputy Methane Barrier 6/4/2020 Approved ARTHUR SARGSYAN
Deputy Reinf. Concrete 6/5/2020 Approved ARTHUR SARGSYAN
Excavation/Setback/Form/Re-Bar 6/30/2020 Approved ARTHUR SARGSYAN
Deputy Methane Barrier 7/14/2020 Conditional Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 8/19/2020 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 9/4/2020 Approved ARTHUR SARGSYAN
Special/Order Compliance 9/4/2020 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 11/9/2020 Corrections Issued DONALD CRICHLOW
Floor/Roof Diaphrgm/Shear Wall 11/17/2020 Partial Approval DONALD CRICHLOW
Special/Order Compliance 11/17/2020 Corrections Issued DONALD CRICHLOW
Sewer 1/27/2021 Approved JOSEPH MCGARRY
Underground Mechanical 1/27/2021 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 5/7/2021 Not Ready for Inspection JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 5/7/2021 Partial Approval JOSEPH MCGARRY
METHANE-Rough 5/7/2021 Approved JOSEPH MCGARRY
PLUMBING-Rough 5/7/2021 Approved JOSEPH MCGARRY
Verify Sprinkler Sign Off 5/7/2021 Not Ready for Inspection JOSEPH MCGARRY
Wood Frame 5/7/2021 Not Ready for Inspection JOSEPH MCGARRY
ELECTRICAL-Rough 5/21/2021 Approved JOSEPH MCGARRY
HVAC-Rough 5/21/2021 Conditional Approval JOSEPH MCGARRY
Shower Pan 7/6/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 7/8/2021 Conditional Approval JOSEPH MCGARRY
Green Building Rough 7/8/2021 Approved JOSEPH MCGARRY
Shower Pan 7/8/2021 Approved JOSEPH MCGARRY
Verify Sprinkler Sign Off 7/8/2021 Approved JOSEPH MCGARRY
Insulation 8/2/2021 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 8/2/2021 Approved ARTHUR SARGSYAN
Drywall Nailing 8/12/2021 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 8/13/2021 Approved ARTHUR SARGSYAN
Grounding or Bonding 6/10/2022 Not Ready for Inspection RYAN SALAZAR
ELECTRICAL-Final 9/9/2022 Approved JEFFREY MEAD
Gas Test 9/9/2022 Approved JEFFREY MEAD
HVAC-Final 9/9/2022 Approved JEFFREY MEAD
PLUMBING-Final 9/9/2022 Approved JEFFREY MEAD
Service/Power Release 9/9/2022 Approved JEFFREY MEAD
Smoke Detectors 9/9/2022 Approved JEFFREY MEAD
Verify Rec and Parks Fee Memo 9/9/2022 Corrections Issued JEFFREY MEAD
BUILDING-Rough-Frame 9/21/2022 Approved JOSEPH MCGARRY
Final 9/21/2022 Corrections Issued JOSEPH MCGARRY
Green Building Final 9/21/2022 Approved JOSEPH MCGARRY
Reinforced Concrete Frame 9/21/2022 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 9/21/2022 SGSOV Approved JOSEPH MCGARRY
Final 10/26/2022 OK to Issue CofO MICHAEL LEWIS