3253 S MOUNTAIN VIEW AVE 90066

Certificate Information: 3253 S MOUNTAIN VIEW AVE 90066

Application / Permit
19010-20000-04501
Plan Check / Job No.
B19VN17269
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 39' X 64' TWO STORY SINGLE FAMILLY DWELLING WITH ATTACHED TWO CAR GARAGE W/ ROOF DECK. WORK PER ENGINEERING. PROVIDE FIRE SPRINKLER NFPA 13D.
Permit Issued
Issued on 2/14/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/14/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/9/2019 APPLICANT
Assigned to Plan Check Engineer 10/31/2019 PARISA ZAHABI
Corrections Issued 11/8/2019 PARISA ZAHABI
Quality Review Completed 11/12/2019 OMID HEDAYAT
Building Plans Picked Up 11/19/2019 APPLICANT
Green Plans Picked Up 12/5/2019 APPLICANT
Applicant returned to address corrections 1/6/2020 PARISA ZAHABI
Applicant returned to address corrections 1/22/2020 PARISA ZAHABI
Plan Check Approved 2/7/2020 PARISA ZAHABI
Issued 2/14/2020 LADBS
CofO in Progress 7/14/2021 KENNETH NAGLE
Permit Finaled 7/14/2021 KENNETH NAGLE
CofO Issued 7/14/2021 KENNETH NAGLE
Permit Finaled 7/14/2021 KENNETH NAGLE

Permit Application Clearance Information

Drainage to Storm Drain Cleared 11/26/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 11/26/2019 LEE GUILBEAUX
Hydrant and Access approval Cleared 11/26/2019 GEORGE SUCHAND
Sewer availability Cleared 11/26/2019 LEE GUILBEAUX
Green Code Cleared 1/30/2020 DAVID MATSON
Low Impact Development Cleared 2/6/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 2/6/2020 APEKSHYA BAJRACHARYA

Contact Information

Architect Carawan,, Diane Parker; Lic. No.: C25411 1516 BRODIEA AVE      VENTURA, CA 93001
Contractor Owner-Builder       ,
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Structural Steel Frame 4/13/2020 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 4/29/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 4/29/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Underground Mechanical 4/29/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 5/5/2020 Approved EVAN COOPER
BUILDING-Rough-Frame 6/30/2020 Not Ready for Inspection JUSTIN CURTIS
Floor/Roof Diaphrgm/Shear Wall 6/30/2020 Partial Approval JUSTIN CURTIS
Green Building Rough 6/30/2020 Not Ready for Inspection JUSTIN CURTIS
Verify Sprinkler Sign Off 6/30/2020 Not Ready for Inspection JUSTIN CURTIS
PLUMBING-Rough 8/20/2020 Approved EVAN COOPER
ELECTRICAL-Rough 9/29/2020 Not Ready for Inspection KENNETH NAGLE
HVAC-Rough 9/29/2020 Corrections Issued KENNETH NAGLE
BUILDING-Rough-Frame 10/9/2020 Corrections Issued EVAN COOPER
ELECTRICAL-Rough 10/9/2020 Not Ready for Inspection EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 10/9/2020 Not Ready for Inspection EVAN COOPER
Green Building Rough 10/9/2020 Not Ready for Inspection EVAN COOPER
HVAC-Rough 10/9/2020 Approved EVAN COOPER
Verify Sprinkler Sign Off 10/9/2020 Approved EVAN COOPER
Deputy Drilled-In Anchors 10/14/2020 Partial Approval MATT KELLERMAN
ELECTRICAL-Rough 10/15/2020 Not Ready for Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 10/15/2020 Partial Inspection KENNETH NAGLE
BUILDING-Rough-Frame 11/4/2020 Approved PIERRE VEGA
ELECTRICAL-Rough 11/4/2020 Approved PIERRE VEGA
Green Building Rough 11/4/2020 Approved PIERRE VEGA
Shower Pan 11/4/2020 Not Ready for Inspection PIERRE VEGA
Interior/Exterior Lathing 11/23/2020 Not Ready for Inspection RICHARD ROBLES
Shower Pan 11/23/2020 Approved RICHARD ROBLES
Interior/Exterior Lathing 12/10/2020 Approved RICHARD ROBLES
Insulation 12/15/2020 Approved RICHARD ROBLES
Drywall Nailing 12/28/2020 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 1/4/2021 No Access for Inspection KENNETH NAGLE
Interior/Exterior Lathing 1/7/2021 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 4/28/2021 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Final 4/28/2021 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Final 5/3/2021 Approved EVAN COOPER
Gas Test 5/3/2021 Approved EVAN COOPER
PLUMBING-Final 5/3/2021 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 5/3/2021 SGSOV Not Ready EVAN COOPER
Smoke Detectors 5/3/2021 Approved EVAN COOPER
HVAC-Final 5/17/2021 Conditional Approval EVAN COOPER
Final 6/9/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 6/9/2021 Not Ready for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 6/9/2021 SGSOV Approved OGANES TARAKHCHYAN
Service/Power Release 6/9/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Final 6/25/2021 Partial Inspection OGANES TARAKHCHYAN
Green Building Final 6/25/2021 Approved OGANES TARAKHCHYAN
Service/Power Release 6/25/2021 Approved OGANES TARAKHCHYAN
Final 7/7/2021 No Access for Inspection DONALD GALLAGHER
Final 7/8/2021 OK to Issue CofO OGANES TARAKHCHYAN