8539 N ENFIELD AVE 91325
Certificate Information: 8539 N ENFIELD AVE 91325
- Application / Permit
- 19010-20000-04493
- Plan Check / Job No.
- B19VN17226
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ACESSORY DWELLING UNIT (46'-9"X31'-0") PER AB 494 AND SB 229, ALL WORK PER WFPP
- Permit Issued
- Issued on 4/21/2021
- Issuing Office
- Current Status
- CofO Issued on 5/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/8/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2019 | MOHAMMAD ESMAILI |
| Green Plans Picked Up | 11/1/2019 | APPLICANT |
| Corrections Issued | 11/6/2019 | MOHAMMAD ESMAILI |
| Quality Review Completed | 11/8/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 11/14/2019 | APPLICANT |
| Plan Check Approved | 1/27/2021 | MOHAMMAD ESMAILI |
| Plan Check Approved | 2/1/2021 | MOHAMMAD ESMAILI |
| Issued | 4/21/2021 | APPLICANT |
| CofO in Progress | 5/17/2022 | RAUL OLAGI |
| CofO Issued | 5/25/2022 | MICHAEL SMITH |
| Permit Finaled | 5/25/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Low Impact Development | Cleared | 9/23/2020 | ANDRES COVARRUBIAS |
| Hydrant and Access approval | Cleared | 10/5/2020 | KURT CORRAL |
| Roof/Waste drainage to street | Cleared | 10/13/2020 | JOHN LIN |
| Green Code | Cleared | 10/16/2020 | MICHAEL AYERS |
| Address approval | Cleared | 10/20/2020 | HOWARD COOPER |
| Eng Process Fee Ord 176,300 | Cleared | 10/27/2020 | JOHN LIN |
| Sewer availability | Cleared | 10/27/2020 | JOHN LIN |
| ZI | Cleared | 11/24/2020 | STEVEN WECHSLER |
| Metro Rail approval | Cleared | 12/3/2020 | MOHAMMAD ESMAILI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/8/2021 | Corrections Issued | MARK JOHNSON |
| Excavation/Setback/Form/Re-Bar | 6/15/2021 | Approved | MARK JOHNSON |
| BUILDING-Rough-Frame | 6/18/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Green Building Rough | 6/18/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Verify Sprinkler Sign Off | 6/18/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 6/23/2021 | Partial Approval | MARK JOHNSON |
| Insulation | 6/23/2021 | Partial Approval | MARK JOHNSON |
| PLUMBING-Rough | 6/23/2021 | Approved | MARK JOHNSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2021 | Partial Approval | MARK JOHNSON |
| Wood Frame | 7/23/2021 | Partial Approval | MARK JOHNSON |
| BUILDING-Rough-Frame | 7/28/2021 | Corrections Issued | MARK JOHNSON |
| ELECTRICAL-Rough | 7/28/2021 | Approved | MARK JOHNSON |
| Green Building Rough | 7/28/2021 | Not Ready for Inspection | MARK JOHNSON |
| HVAC-Rough | 7/28/2021 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 7/28/2021 | Approved | MARK JOHNSON |
| Verify Sprinkler Sign Off | 7/28/2021 | Approved | MARK JOHNSON |
| BUILDING-Rough-Frame | 8/10/2021 | Approved | MARK JOHNSON |
| Green Building Rough | 8/10/2021 | Approved | MARK JOHNSON |
| Insulation | 8/10/2021 | Approved | MARK JOHNSON |
| Drywall Nailing | 8/19/2021 | Approved | ADAM ESCOTO |
| ELECTRICAL-Rough | 10/8/2021 | Partial Approval | MARK JOHNSON |
| Gas Test | 12/10/2021 | Approved | MARK JOHNSON |
| Sewer | 12/10/2021 | Approved | MARK JOHNSON |
| Underground Mechanical | 12/10/2021 | Approved | MARK JOHNSON |
| ELECTRICAL-Final | 3/8/2022 | Corrections Issued | RAUL OLAGI |
| Final | 3/8/2022 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 3/8/2022 | Approved | RAUL OLAGI |
| Green Building Final | 3/8/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Final | 3/8/2022 | Corrections Issued | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 3/8/2022 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 3/8/2022 | Approved | RAUL OLAGI |
| Special/Order Compliance | 3/8/2022 | Partial Inspection | ALAN MORELOS |
| Final | 3/25/2022 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 3/25/2022 | Corrections Issued | RAUL OLAGI |
| Service/Power Release | 3/25/2022 | Not Ready for Inspection | RAUL OLAGI |
| Final | 4/13/2022 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 4/13/2022 | Approved | RAUL OLAGI |
| Service/Power Release | 4/13/2022 | Not Ready for Inspection | RAUL OLAGI |
| Final | 5/17/2022 | OK to Issue CofO | RAUL OLAGI |
| Service/Power Release | 5/17/2022 | Approved | RAUL OLAGI |