2209-2211 N CAZADOR DR 90065

Certificate Information: 2209-2211 N CAZADOR DR 90065

Application / Permit
19010-20000-04434
Plan Check / Job No.
B19VN17048
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFD W/ ATTACHED 2-CAR GARAGE & ATTACHED 1-STORY ACCESSORY DWELLING UNIT @ REAR PER LAMC 12.22 A.33(c)(e) (NFPA-13D FIRE SPRINKLER THROUGHOUT)
Permit Issued
Issued on 6/13/2023
Issuing Office
Metro
Current Status
CofO Issued on 7/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/4/2019 APPLICANT
Assigned to Plan Check Engineer 10/24/2019 TROY DEGUZMAN
Corrections Issued 10/29/2019 TROY DEGUZMAN
Quality Review Completed 10/29/2019 CHON CHIO KUO
Building Plans Picked Up 11/5/2019 APPLICANT
Green Plans Picked Up 11/5/2019 APPLICANT
Applicant returned to address corrections 5/5/2022 TROY DEGUZMAN
Applicant returned to address corrections 1/26/2023 NILOOFAR MEHRAIN
Applicant returned to address corrections 2/14/2023 NILOOFAR MEHRAIN
Applicant returned to address corrections 3/9/2023 NILOOFAR MEHRAIN
Plan Check Approved 3/24/2023 NILOOFAR MEHRAIN
Issued 6/13/2023 APPLICANT
CofO in Progress 7/9/2025 NICHOLAS LOPEZ
CofO Issued 7/16/2025 DEROLD HAUFF
Permit Finaled 7/16/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/9/2020 CELINA MORENO
Permit Cleared 12/9/2020 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 12/11/2020 CELINA MORENO
Trees in Parkway Cleared 3/3/2021 JOHN KIM
Hydrant and Access approval Cleared 8/4/2021 MATTHEW CRAIG
Green Code Cleared 5/5/2022 AARON COSTA
Grading Pre-Inspection Cleared 6/2/2022 ROBERT HUGHES
Sewer availability Cleared 6/22/2022 JEANETTE VONG
Low Impact Development Cleared 8/4/2022 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 8/9/2022 JEANIE LAM
Specific Plan Cleared 12/13/2022 LOUIS ORTEGA
ZI Cleared 12/13/2022 LOUIS ORTEGA

Contact Information

Architect Lopez,, Craig Joseph; Lic. No.: C14263 155 GRANADA ST STE "L"      CAMARILLO, CA 93010
Contractor Molina Carlos Alberto Construction; Lic. No.: 973892-B 4348 LYND AVENUE      ARCADIA, CA 91006

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/23/2023 Partial Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 7/21/2023 Corrections Issued HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 7/26/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 7/26/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 7/28/2023 Partial Approval HAMIK HARTOUNIAN
Underground Mechanical 8/4/2023 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 8/9/2023 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 9/6/2023 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 9/12/2023 Partial Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 9/15/2023 Partial Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 10/12/2023 Corrections Issued BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 10/16/2023 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 8/8/2024 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 8/13/2024 Corrections Issued THOMAS LOGRASSO
HVAC-Rough 8/13/2024 Corrections Issued THOMAS LOGRASSO
PLUMBING-Rough 8/13/2024 Approved THOMAS LOGRASSO
Sewer 8/13/2024 Approved THOMAS LOGRASSO
ELECTRICAL-Rough 8/21/2024 Not Ready for Inspection THOMAS LOGRASSO
HVAC-Rough 8/21/2024 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Rough 10/2/2024 Approved THOMAS LOGRASSO
HVAC-Rough 10/2/2024 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 10/3/2024 Corrections Issued THOMAS LOGRASSO
Verify Sprinkler Sign Off 10/3/2024 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 10/11/2024 Not Ready for Inspection THOMAS LOGRASSO
HVAC-Rough 10/11/2024 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 10/17/2024 Approved THOMAS LOGRASSO
HVAC-Rough 10/17/2024 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 10/17/2024 Conditional Approval THOMAS LOGRASSO
Insulation 10/28/2024 Corrections Issued THOMAS LOGRASSO
Interior/Exterior Lathing 10/28/2024 Partial Approval THOMAS LOGRASSO
Insulation 10/30/2024 Approved THOMAS LOGRASSO
Drywall Nailing 11/6/2024 Not Ready for Inspection THOMAS LOGRASSO
Green Building Rough 11/6/2024 Approved THOMAS LOGRASSO
Drywall Nailing 11/8/2024 Approved ANTHONY RAMOS
HVAC-Final 3/5/2025 Corrections Issued NICHOLAS LOPEZ
PLUMBING-Final 3/5/2025 Corrections Issued NICHOLAS LOPEZ
Deputy Drilled-In Anchors 3/25/2025 Conditional Approval NICHOLAS LOPEZ
ELECTRICAL-Final 4/3/2025 Corrections Issued NICHOLAS LOPEZ
HVAC-Final 4/3/2025 Not Ready for Inspection NICHOLAS LOPEZ
PLUMBING-Final 4/3/2025 Corrections Issued NICHOLAS LOPEZ
ELECTRICAL-Final 4/24/2025 Corrections Issued NICHOLAS LOPEZ
Final 4/24/2025 Corrections Issued NICHOLAS LOPEZ
Footing/Foundation/Slab 4/24/2025 Approved NICHOLAS LOPEZ
Green Building Final 4/24/2025 Approved NICHOLAS LOPEZ
HVAC-Final 4/24/2025 Approved NICHOLAS LOPEZ
PLUMBING-Final 4/24/2025 Approved NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 4/24/2025 SGSOV No Gas NICHOLAS LOPEZ
Service/Power Release 4/24/2025 Not Ready for Inspection NICHOLAS LOPEZ
Smoke Detectors 4/24/2025 Approved NICHOLAS LOPEZ
ELECTRICAL-Final 7/3/2025 Approved NICHOLAS LOPEZ
Final 7/3/2025 Corrections Issued NICHOLAS LOPEZ
Service/Power Release 7/3/2025 Not Ready for Inspection NICHOLAS LOPEZ
ELECTRICAL-Final 7/8/2025 Approved NICHOLAS LOPEZ
Final 7/8/2025 OK to Issue CofO NICHOLAS LOPEZ
Service/Power Release 7/8/2025 Approved NICHOLAS LOPEZ