15523 W COBALT ST LOT #3 91342

Certificate Information: 15523 W COBALT ST LOT #3 91342

Application / Permit
19010-20000-04420
Plan Check / Job No.
B19VN17030
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFD W/ ATTACHED GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT) [Small lot subdivision pursuant to Tract Map No. 82021. A certificate of occupancy (temporary or final) shall not be issued until after the final map has recorded]
Permit Issued
Issued on 1/27/2020
Issuing Office
Valley
Current Status
CofO Issued on 12/11/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/4/2019 APPLICANT
Green Plans Picked Up 10/16/2019 APPLICANT
Assigned to Plan Check Engineer 10/17/2019 NILOOFAR MEHRAIN
Corrections Issued 10/21/2019 NILOOFAR MEHRAIN
Quality Review Completed 10/23/2019 GUANG MIN TUNG
Building Plans Picked Up 10/23/2019 APPLICANT
Applicant returned to address corrections 11/14/2019 NILOOFAR MEHRAIN
Applicant returned to address corrections 12/12/2019 NILOOFAR MEHRAIN
Plan Check Approved 1/27/2020 NILOOFAR MEHRAIN
Issued 1/27/2020 LADBS
CofO in Progress 12/10/2020 JOSEPH SAGEN
Permit Finaled 12/11/2020 DONALD SUNSERI
CofO Issued 12/11/2020 DONALD SUNSERI
Permit Finaled 12/11/2020 DONALD SUNSERI

Permit Application Clearance Information

GPI Written Notices Cleared 11/14/2019 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 11/14/2019 NILOOFAR MEHRAIN
Address approval Cleared 11/26/2019 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 11/26/2019 APEKSHYA BAJRACHARYA
Highway dedication Cleared 11/26/2019 APEKSHYA BAJRACHARYA
Hydrant and Access approval Cleared 11/26/2019 JEREMY CARTER
Miscellaneous Cleared 11/26/2019 APEKSHYA BAJRACHARYA
Permit Cleared 11/26/2019 APEKSHYA BAJRACHARYA
Roof/Waste drainage to street Cleared 11/26/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 11/26/2019 APEKSHYA BAJRACHARYA
Tract Map conditions Cleared 12/2/2019 SOPHIE GABEL-SCHEINBAU
Green Code Cleared 12/3/2019 MICHAEL AYERS
Trees in Parkway Cleared 12/6/2019 JOHN KIM
Disturb/Remove Protected Trees Cleared 12/20/2019 STEPHEN DUPREY
Low Impact Development Cleared 1/10/2020 SARAH YOUSSEF

Contact Information

Contractor Williams Homes Inc; Lic. No.: 734097-B 21080 CENTRE POINTE PARKWAY   #101    SANTA CLARITA, CA 91350
Engineer Deihimi,, Amir Hossein; Lic. No.: C78194 23172 PLAZA POINTE DR STE 145      LAGUNA HILLS, CA 92653

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/5/2020 Approved SEAN WIRCH
Deputy Pre-Stress Concrete 2/20/2020 Approved SEAN WIRCH
Footing/Foundation/Slab 2/21/2020 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 3/6/2020 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 4/2/2020 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 4/24/2020 Partial Approval JOSEPH SAGEN
BUILDING-Rough-Frame 5/4/2020 Approved JOSEPH SAGEN
ELECTRICAL-Rough 5/4/2020 Approved JOSEPH SAGEN
Green Building Rough 5/4/2020 Approved JOSEPH SAGEN
HVAC-Rough 5/4/2020 Approved JOSEPH SAGEN
PLUMBING-Rough 5/4/2020 Approved JOSEPH SAGEN
Verify Sprinkler Sign Off 5/4/2020 Approved JOSEPH SAGEN
Insulation 5/5/2020 Approved JOSEPH SAGEN
Drywall Nailing 5/12/2020 Approved JOSEPH SAGEN
Interior/Exterior Lathing 5/12/2020 Partial Approval JOSEPH SAGEN
Gas Test 6/25/2020 Approved JOSEPH SAGEN
Service/Power Release 8/11/2020 Approved JOSEPH SAGEN
Sewer 8/13/2020 Approved SEAN WIRCH
Underground Mechanical 9/25/2020 Not Ready for Inspection SEAN WIRCH
Underground Mechanical 9/29/2020 Partial Approval JOSEPH SAGEN
PLUMBING-Final 10/20/2020 Not Ready for Inspection JOSEPH SAGEN
SGSOV-Seismic Gas S/O Valve 10/21/2020 SGSOV Approved SEAN WIRCH
PLUMBING-Final 11/6/2020 Approved SEAN WIRCH
HVAC-Final 11/13/2020 Approved JOSEPH SAGEN
ELECTRICAL-Final 11/20/2020 Approved JOSEPH SAGEN
Final 11/25/2020 Not Ready for Inspection JOSEPH SAGEN
Green Building Final 11/25/2020 Not Ready for Inspection JOSEPH SAGEN
Smoke Detectors 11/25/2020 Approved JOSEPH SAGEN
Final 12/9/2020 OK to Issue CofO JOSEPH SAGEN
Green Building Final 12/9/2020 Approved JOSEPH SAGEN