4545 N LEMP AVE 91602

Certificate Information: 4545 N LEMP AVE 91602

Application / Permit
19010-20000-04403
Plan Check / Job No.
B19VN16944
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New Two-Story irregular 45'x46'7" Single Family Dwelling with attached 18'x18'1" Garage and 4'9"x10'6" covered porch, 10'6" x 23'6" and 10'6" x 9' rooftop decks over the first story.
Permit Issued
Issued on 2/6/2020
Issuing Office
Valley
Current Status
CofO Issued on 2/27/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/3/2019 APPLICANT
Green Plans Picked Up 10/16/2019 APPLICANT
Assigned to Plan Check Engineer 10/17/2019 LUIS RINCON
Corrections Issued 10/19/2019 LUIS RINCON
Quality Review Completed 10/31/2019 CHON CHIO KUO
Building Plans Picked Up 11/1/2019 APPLICANT
Plan Check Approved 2/6/2020 LUIS RINCON
Issued 2/6/2020 LADBS
CofO in Progress 2/12/2021 THOMAS FINNILA
CofO Issued 2/27/2021 MICHAEL SMITH
Permit Finaled 2/27/2021 MICHAEL SMITH

Permit Application Clearance Information

Green Code Cleared 12/2/2019 DAVID MATSON
Eng Process Fee Ord 176,300 Cleared 1/2/2020 MARKOS PEREZ-BRAN
Permit Cleared 1/2/2020 MARKOS PEREZ-BRAN
Sewer availability Cleared 1/2/2020 MARKOS PEREZ-BRAN
ZI Cleared 1/2/2020 HERMINIGILDO AGUSTIN
Low Impact Development Cleared 1/3/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 1/3/2020 ELAINE LEI
Hydrant and Access approval Cleared 1/24/2020 GEORGE SUCHAND

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia, Zelada, Eddy Alexander; Lic. No.: S6159 17958 LULL ST      RESEDA, CA 91335

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 2/28/2020 Not Ready for Inspection JEFFREY PARD
Excavation/Setback/Form/Re-Bar 4/8/2020 Not Ready for Inspection JEFFREY PARD
Underground Mechanical 4/8/2020 Corrections Issued JEFFREY PARD
Footing/Foundation/Slab 4/14/2020 Partial Approval JEFFREY PARD
Underground Mechanical 4/14/2020 Approved JEFFREY PARD
Excavation/Setback/Form/Re-Bar 4/20/2020 Approved JEFFREY PARD
Footing/Foundation/Slab 4/20/2020 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 5/8/2020 Partial Approval JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 5/26/2020 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 7/7/2020 Approved DANIEL ORRANTE
PLUMBING-Rough 7/7/2020 Approved DANIEL ORRANTE
ELECTRICAL-Rough 7/10/2020 Corrections Issued THOMAS FINNILA
HVAC-Rough 7/10/2020 Not Ready for Inspection THOMAS FINNILA
Interior/Exterior Lathing 7/10/2020 Corrections Issued THOMAS FINNILA
BUILDING-Rough-Frame 7/13/2020 Not Ready for Inspection THOMAS FINNILA
Green Building Rough 7/13/2020 Not Ready for Inspection THOMAS FINNILA
MERV13>=Rough 7/13/2020 Not Ready for Inspection THOMAS FINNILA
Verify Sprinkler Sign Off 7/13/2020 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 7/14/2020 Approved THOMAS FINNILA
HVAC-Rough 7/14/2020 Conditional Approval THOMAS FINNILA
BUILDING-Rough-Frame 7/15/2020 Approved THOMAS FINNILA
Green Building Rough 7/15/2020 Approved THOMAS FINNILA
Interior/Exterior Lathing 7/15/2020 Approved THOMAS FINNILA
MERV13>=Rough 7/15/2020 Approved THOMAS FINNILA
Verify Sprinkler Sign Off 7/15/2020 Approved THOMAS FINNILA
Insulation 7/20/2020 Approved THOMAS FINNILA
Shower Pan 7/20/2020 Approved THOMAS FINNILA
Drywall Nailing 7/31/2020 Approved THOMAS FINNILA
Interior/Exterior Lathing 7/31/2020 Approved THOMAS FINNILA
Final 1/27/2021 Corrections Issued THOMAS FINNILA
Green Building Final 1/27/2021 Not Ready for Inspection THOMAS FINNILA
MERV13>=Final 1/27/2021 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 1/27/2021 SGSOV Not Ready THOMAS FINNILA
Service/Power Release 1/27/2021 Not Ready for Inspection THOMAS FINNILA
Smoke Detectors 1/27/2021 Not Ready for Inspection THOMAS FINNILA
Final 2/1/2021 Not Ready for Inspection THOMAS FINNILA
Green Building Final 2/1/2021 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 2/1/2021 SGSOV Approved THOMAS FINNILA
Service/Power Release 2/1/2021 Not Ready for Inspection THOMAS FINNILA
Smoke Detectors 2/1/2021 Approved THOMAS FINNILA
Final 2/10/2021 Not Ready for Inspection THOMAS FINNILA
Service/Power Release 2/10/2021 Not Ready for Inspection THOMAS FINNILA
Final 2/12/2021 OK to Issue CofO THOMAS FINNILA
Service/Power Release 2/12/2021 Approved THOMAS FINNILA