9110 N NILO LANE 91402
Certificate Information: 9110 N NILO LANE 91402
- Application / Permit
- 19010-20000-04398
- Plan Check / Job No.
- B19VN16913
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- "SMALL LOT SUBDIVISION PURSUANT TO TENTATIVE TRACT MAP NO / PRELIMINARY PARCEL MAP NO. VTT-82584-SL. A CERTIFICATE OF OCCUPANCY (TEMPORARY OR FINAL ) SHALL NOT BE ISSUED UNTIL AFTER THE FINAL MAP HAS BEEN RECORDED." NEW 2 STORY 46' X 35' SFD WITH ATTACHED TWO CAR GARAGE , NFPA-13D FIRE SPRINKLERS THROUGH-OUT (PER VTT-82584-SL )
- Permit Issued
- Issued on 4/19/2021
- Issuing Office
- Current Status
- CofO Issued on 4/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/4/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2019 | RARES BODEA |
| Corrections Issued | 11/1/2019 | RARES BODEA |
| Quality Review Completed | 11/5/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 11/8/2019 | APPLICANT |
| Green Plans Picked Up | 11/8/2019 | APPLICANT |
| Applicant returned to address corrections | 7/20/2020 | RARES BODEA |
| Applicant returned to address corrections | 8/19/2020 | RARES BODEA |
| Applicant returned to address corrections | 8/20/2020 | RARES BODEA |
| Applicant returned to address corrections | 8/21/2020 | RARES BODEA |
| Applicant returned to address corrections | 10/26/2020 | RARES BODEA |
| Applicant returned to address corrections | 10/27/2020 | RARES BODEA |
| Plan Check Approved | 12/16/2020 | RARES BODEA |
| Issued | 4/19/2021 | APPLICANT |
| Permit Finaled | 4/22/2024 | JOHN JANSON |
| CofO Issued | 4/22/2024 | JOHN JANSON |
| Permit Finaled | 4/22/2024 | JOHN JANSON |
Permit Application Clearance Information
| Miscellaneous | Cleared | 5/4/2020 | BRANDON WILSON |
| Highway dedication | Cleared | 6/5/2020 | ADRIAN CASTRO |
| Miscellaneous | Cleared | 6/5/2020 | ADRIAN CASTRO |
| Permit | Cleared | 6/5/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 6/5/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 6/9/2020 | ADRIAN CASTRO |
| Address approval | Cleared | 7/21/2020 | HOWARD COOPER |
| Low Impact Development | Cleared | 7/30/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 8/4/2020 | ADRIAN CASTRO |
| Trees in Parkway | Cleared | 8/20/2020 | JOHN KIM |
| Hydrant and Access approval | Cleared | 9/22/2020 | MATTHEW CRAIG |
| Green Code | Cleared | 9/30/2020 | MICHAEL AYERS |
| "Q" conditions | Cleared | 10/15/2020 | RUBEN VASQUEZ |
| "T" removal | Cleared | 10/15/2020 | RUBEN VASQUEZ |
| APC | Cleared | 10/15/2020 | RUBEN VASQUEZ |
| APC | Cleared | 10/15/2020 | RUBEN VASQUEZ |
| Frnt yard landscape/Water mgmt | Cleared | 10/15/2020 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 10/15/2020 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 10/15/2020 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 10/15/2020 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 10/15/2020 | RUBEN VASQUEZ |
| Tract Map conditions | Cleared | 10/15/2020 | RUBEN VASQUEZ |
| Tract Map conditions | Cleared | 10/15/2020 | RUBEN VASQUEZ |
| ZA Case | Cleared | 10/15/2020 | RUBEN VASQUEZ |
| Disturb/Remove Protected Trees | Cleared | 10/30/2020 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Alloy Construction And Restoration; Lic. No.: 1054043-B | 948 S BERNAL AVE LOS ANGELES, CA 90023 |
| Engineer | Naim,, Soleiman Israel; Lic. No.: S2454 | 403 21ST ST SANTA MONICA, CA 90402 |
| Engineer | Vidal,, Juan Alonso; Lic. No.: GE861 | 7438 SHIRLEY AVE RESEDA, CA 91335 |
Inspector Information
| JOSEPH SAGEN, (818) 774-4353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/2/2021 | Partial Approval | JOSEPH SAGEN |
| Footing/Foundation/Slab | 7/14/2021 | Approved | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2021 | Partial Approval | JOSEPH SAGEN |
| Rough-Elec/Plmb/HVAC | 1/4/2022 | Approved | SEAN WIRCH |
| Interior/Exterior Lathing | 2/1/2022 | Partial Approval | SEAN WIRCH |
| Drywall Nailing | 3/9/2022 | Approved | SEAN WIRCH |
| Green Building Rough | 3/9/2022 | Approved | SEAN WIRCH |
| Underground Mechanical | 6/6/2022 | Approved | SEAN WIRCH |
| Interior/Exterior Lathing | 7/26/2022 | Approved | SEAN WIRCH |
| Shower Pan | 7/26/2022 | Approved | SEAN WIRCH |
| Service/Power Release | 7/14/2023 | Approved | SEAN WIRCH |
| Gas Test | 7/21/2023 | Approved | SEAN WIRCH |
| BUILDING-Rough-Frame | 10/25/2023 | Approved | SEAN WIRCH |
| Final | 10/25/2023 | Partial Approval | SEAN WIRCH |
| Green Building Final | 10/25/2023 | Approved | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 10/25/2023 | SGSOV Approved | SEAN WIRCH |
| Smoke Detectors | 10/25/2023 | Approved | SEAN WIRCH |
| Verify Sprinkler Sign Off | 10/25/2023 | Approved | SEAN WIRCH |