9124 N NILO LANE 91402

Certificate Information: 9124 N NILO LANE 91402

Application / Permit
19010-20000-04395
Plan Check / Job No.
B19VN16913
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
"SMALL LOT SUBDIVISION PURSUANT TO TENTATIVE TRACT MAP NO / PRELIMINARY PARCEL MAP NO. VTT-82584-SL. A CERTIFICATE OF OCCUPANCY (TEMPORARY OR FINAL ) SHALL NOT BE ISSUED UNTIL AFTER THE FINAL MAP HAS BEEN RECORDED." NEW 2 STORY 46' X 35' SFD WITH ATTACHED TWO CAR GARAGE , NFPA-13D FIRE SPRINKLERS THROUGH-OUT (PER VTT-82584-SL )
Permit Issued
Issued on 4/19/2021
Issuing Office
Current Status
CofO Issued on 11/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/4/2019 APPLICANT
Assigned to Plan Check Engineer 10/24/2019 RARES BODEA
Corrections Issued 11/1/2019 RARES BODEA
Quality Review Completed 11/5/2019 GUANG MIN TUNG
Building Plans Picked Up 11/8/2019 APPLICANT
Green Plans Picked Up 11/8/2019 APPLICANT
Applicant returned to address corrections 7/20/2020 RARES BODEA
Applicant returned to address corrections 8/19/2020 RARES BODEA
Applicant returned to address corrections 8/20/2020 RARES BODEA
Applicant returned to address corrections 8/21/2020 RARES BODEA
Applicant returned to address corrections 10/26/2020 RARES BODEA
Applicant returned to address corrections 10/27/2020 RARES BODEA
Plan Check Approved 12/16/2020 RARES BODEA
Issued 4/19/2021 APPLICANT
CofO in Progress 10/28/2023 SEAN WIRCH
CofO Issued 11/2/2023 JOHN JANSON
Permit Finaled 11/2/2023 JOHN JANSON

Permit Application Clearance Information

Miscellaneous Cleared 5/4/2020 BRANDON WILSON
Highway dedication Cleared 6/5/2020 ADRIAN CASTRO
Miscellaneous Cleared 6/5/2020 ADRIAN CASTRO
Permit Cleared 6/5/2020 ADRIAN CASTRO
Sewer availability Cleared 6/5/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 6/9/2020 ADRIAN CASTRO
Address approval Cleared 7/21/2020 HOWARD COOPER
Low Impact Development Cleared 7/30/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 8/4/2020 ADRIAN CASTRO
Trees in Parkway Cleared 8/20/2020 JOHN KIM
Hydrant and Access approval Cleared 9/22/2020 MATTHEW CRAIG
Green Code Cleared 9/30/2020 MICHAEL AYERS
"Q" conditions Cleared 10/15/2020 RUBEN VASQUEZ
"T" removal Cleared 10/15/2020 RUBEN VASQUEZ
APC Cleared 10/15/2020 RUBEN VASQUEZ
APC Cleared 10/15/2020 RUBEN VASQUEZ
Frnt yard landscape/Water mgmt Cleared 10/15/2020 RUBEN VASQUEZ
Miscellaneous Cleared 10/15/2020 RUBEN VASQUEZ
Miscellaneous Cleared 10/15/2020 RUBEN VASQUEZ
Miscellaneous Cleared 10/15/2020 RUBEN VASQUEZ
Tract Map conditions Cleared 10/15/2020 RUBEN VASQUEZ
Tract Map conditions Cleared 10/15/2020 RUBEN VASQUEZ
ZA Case Cleared 10/15/2020 RUBEN VASQUEZ
Disturb/Remove Protected Trees Cleared 10/30/2020 ADRIAN SANCHEZ
Miscellaneous Cleared 11/4/2020 RUBEN VASQUEZ

Contact Information

Contractor Alloy Construction And Restoration; Lic. No.: 1054043-B 948 S BERNAL AVE      LOS ANGELES, CA 90023
Engineer Naim,, Soleiman Israel; Lic. No.: S2454 403 21ST ST      SANTA MONICA, CA 90402
Engineer Vidal,, Juan Alonso; Lic. No.: GE861 7438 SHIRLEY AVE      RESEDA, CA 91335

Inspector Information

JOSEPH SAGEN, (818) 774-4353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/4/2021 Partial Approval JOSEPH SAGEN
Excavation/Setback/Form/Re-Bar 6/15/2021 Approved JOSEPH SAGEN
Footing/Foundation/Slab 6/15/2021 Approved JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 8/2/2021 Partial Approval JOSEPH SAGEN
ELECTRICAL-Rough 11/2/2021 Not Ready for Inspection JOSEPH SAGEN
Gas Test 11/2/2021 Not Ready for Inspection JOSEPH SAGEN
HVAC-Rough 11/2/2021 Not Ready for Inspection JOSEPH SAGEN
PLUMBING-Rough 11/2/2021 Partial Approval JOSEPH SAGEN
ELECTRICAL-Rough 11/19/2021 Not Ready for Inspection SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 11/19/2021 Partial Approval SEAN WIRCH
HVAC-Rough 11/19/2021 Not Ready for Inspection SEAN WIRCH
BUILDING-Rough-Frame 12/29/2021 Approved SEAN WIRCH
Green Building Rough 12/29/2021 Approved SEAN WIRCH
Rough-Elec/Plmb/HVAC 12/29/2021 Approved SEAN WIRCH
Verify Sprinkler Sign Off 12/29/2021 Approved SEAN WIRCH
Drywall Nailing 1/26/2022 Approved SEAN WIRCH
Interior/Exterior Lathing 1/26/2022 Approved SEAN WIRCH
Underground Mechanical 6/6/2022 Approved SEAN WIRCH
Service/Power Release 7/14/2023 Approved SEAN WIRCH
Gas Test 7/21/2023 Approved SEAN WIRCH
Final 10/25/2023 OK to Issue CofO SEAN WIRCH
Green Building Final 10/25/2023 Approved SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 10/25/2023 SGSOV Approved SEAN WIRCH
Smoke Detectors 10/25/2023 Approved SEAN WIRCH