10983 W ELINDA PL 91352

Certificate Information: 10983 W ELINDA PL 91352

Application / Permit
19010-20000-04367
Plan Check / Job No.
B19VN16814
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSE 21'-10"X58'-6" ACCESSORY DWELLING UNIT PER AB 494 AND SB 229_BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT NFPA 13D [SEE COMMENTS]
Permit Issued
Issued on 3/16/2020
Issuing Office
Valley
Current Status
CofO Issued on 10/14/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/1/2019 APPLICANT
Assigned to Plan Check Engineer 10/10/2019 DAWN MC NULTY
Corrections Issued 10/15/2019 DAWN MC NULTY
Quality Review Completed 10/15/2019 CHON CHIO KUO
Building Plans Picked Up 10/17/2019 APPLICANT
Green Plans Picked Up 10/17/2019 APPLICANT
Plan Check Approved 3/13/2020 DAWN MC NULTY
Issued 3/16/2020 LADBS
CofO in Progress 10/10/2020 DANIEL ORRANTE
Permit Finaled 10/14/2020 DANIEL ORRANTE
CofO Issued 10/14/2020 DANIEL ORRANTE
Permit Finaled 10/14/2020 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/24/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 10/24/2019 GUILLERMO PETRA
Permit Cleared 10/24/2019 GUILLERMO PETRA
Specific Plan Cleared 2/26/2020 PEGGY MALONE-BROWN
Green Code Cleared 3/11/2020 AARON COSTA
Hydrant and Access approval Cleared 3/12/2020 GEORGE SUCHAND
Low Impact Development Cleared 3/12/2020 MITESH PATEL
GPI Written Notices Cleared 3/13/2020 DAWN MC NULTY
Grading Pre-Inspection Cleared 3/13/2020 DAWN MC NULTY
Roof/Waste drainage to street Cleared 3/13/2020 LEE GUILBEAUX
Sewer availability Cleared 3/13/2020 LEE GUILBEAUX
Private sewage disp. approval Cleared 3/16/2020 DAN RYAN EVANGELISTA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/1/2020 Approved BEAU COLLINS
METHANE-Barrier 4/1/2020 Approved BEAU COLLINS
METHANE-Subgrade 4/1/2020 Approved BEAU COLLINS
PLUMBING-Rough 4/15/2020 Partial Approval BEAU COLLINS
Wood Frame 4/15/2020 Partial Approval BEAU COLLINS
Floor/Roof Diaphrgm/Shear Wall 5/7/2020 Approved BEAU COLLINS
Special/Order Compliance 5/7/2020 Approved GREGG CUMMINGS
ELECTRICAL-Rough 5/15/2020 Approved BEAU COLLINS
HVAC-Rough 5/15/2020 Not Ready for Inspection BEAU COLLINS
PLUMBING-Rough 5/15/2020 Approved BEAU COLLINS
Wood Frame 5/15/2020 Not Ready for Inspection BEAU COLLINS
HVAC-Rough 5/19/2020 Approved BEAU COLLINS
Wood Frame 5/19/2020 Not Ready for Inspection BEAU COLLINS
BUILDING-Rough-Frame 6/10/2020 Approved BEAU COLLINS
Green Building Rough 6/10/2020 Approved BEAU COLLINS
METHANE-Rough 6/10/2020 Approved BEAU COLLINS
Verify Sprinkler Sign Off 6/10/2020 Approved BEAU COLLINS
Insulation 6/12/2020 Approved BEAU COLLINS
Drywall Nailing 6/17/2020 Approved BEAU COLLINS
Interior/Exterior Lathing 7/2/2020 Approved BEAU COLLINS
ELECTRICAL-Final 8/27/2020 Approved BEAU COLLINS
HVAC-Final 8/27/2020 Approved BEAU COLLINS
PLUMBING-Final 8/27/2020 Approved BEAU COLLINS
Final 10/9/2020 OK to Issue CofO DANIEL ORRANTE
Green Building Final 10/9/2020 Approved DANIEL ORRANTE
SGSOV-Seismic Gas S/O Valve 10/9/2020 SGSOV Approved DANIEL ORRANTE
Service/Power Release 10/9/2020 Approved DANIEL ORRANTE
Smoke Detectors 10/9/2020 Approved DANIEL ORRANTE