14203 W BURTON ST 91402
Certificate Information: 14203 W BURTON ST 91402
- Application / Permit
- 19010-20000-04322
- Plan Check / Job No.
- B19VN16648
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW(14'-9"x 46'-0") 2-STORY DETACHED ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. WORK PER ENGINEER.
- Permit Issued
- Issued on 1/15/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/27/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2019 | TROY DEGUZMAN |
| Corrections Issued | 10/21/2019 | TROY DEGUZMAN |
| Quality Review Completed | 10/21/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 10/25/2019 | APPLICANT |
| Green Plans Picked Up | 10/28/2019 | APPLICANT |
| Plan Check Approved | 1/14/2020 | TROY DEGUZMAN |
| Issued | 1/15/2020 | LADBS |
| CofO in Progress | 1/29/2021 | GREGG CUMMINGS |
| CofO Issued | 4/27/2021 | MICHAEL SMITH |
| Permit Finaled | 4/27/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/5/2019 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/5/2019 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 12/5/2019 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 12/5/2019 | SARAH YOUSSEF |
| Sewer availability | Cleared | 12/5/2019 | ADRIAN CASTRO |
| Green Code | Cleared | 1/13/2020 | MICHAEL AYERS |
| Roof/Waste drainage to street | Cleared | 1/13/2020 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/10/2020 | Approved | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2020 | Partial Inspection | WILLIAM KUEHN |
| PLUMBING-Rough | 2/14/2020 | Partial Inspection | WILLIAM KUEHN |
| Sewer | 2/14/2020 | Approved | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2020 | Partial Inspection | WILLIAM KUEHN |
| Interior/Exterior Lathing | 5/7/2020 | Partial Inspection | WILLIAM KUEHN |
| Drywall Nailing | 5/20/2020 | Approved | WILLIAM KUEHN |
| Green Building Rough | 5/20/2020 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 5/20/2020 | Partial Inspection | WILLIAM KUEHN |
| Shower Pan | 7/2/2020 | Approved | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 12/1/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 12/1/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Final | 12/1/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 12/1/2020 | SGSOV Not Ready | GREGG CUMMINGS |
| Service/Power Release | 12/1/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 12/1/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 12/1/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 1/20/2021 | Approved | GREGG CUMMINGS |
| Final | 1/20/2021 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 1/20/2021 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 1/20/2021 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 1/20/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 1/20/2021 | Approved | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 1/20/2021 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 1/29/2021 | Approved | GREGG CUMMINGS |
| Final | 1/29/2021 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 1/29/2021 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 1/29/2021 | Approved | GREGG CUMMINGS |
| Service/Power Release | 1/29/2021 | Approved | GREGG CUMMINGS |