15313 W DE PAUW ST 90272

Certificate Information: 15313 W DE PAUW ST 90272

Application / Permit
19010-20000-04302
Plan Check / Job No.
B19VN16564
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 70'11" X 41'3" TWO STORY SFD WITH HABITABLE BASEMENT WITH ATTACHED TWO CAR ATTACHED GARAGE AND WITH 48' X 23'8"ROOFTOP DECK , NFPA-13D FIRE SPRINKLERS REQUIRED , ALL WORK PER ENGINEERING
Permit Issued
Issued on 11/30/2021
Issuing Office
Valley
Current Status
CofO Issued on 12/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/27/2019 APPLICANT
Green Plans Picked Up 10/8/2019 APPLICANT
Assigned to Plan Check Engineer 10/10/2019 RARES BODEA
Corrections Issued 10/12/2019 RARES BODEA
Quality Review Completed 10/23/2019 GUANG MIN TUNG
Building Plans Picked Up 10/23/2019 APPLICANT
Applicant returned to address corrections 1/22/2021 RARES BODEA
Applicant returned to address corrections 1/26/2021 RARES BODEA
Applicant returned to address corrections 5/19/2021 RARES BODEA
Applicant returned to address corrections 9/13/2021 RARES BODEA
Plan Check Approved 11/29/2021 RARES BODEA
Issued 11/30/2021 APPLICANT
CofO in Progress 11/1/2023 EVAN COOPER
CofO in Progress 11/29/2023 EVAN COOPER
Permit Finaled 12/11/2023 DANIEL ORRANTE
CofO Issued 12/11/2023 DANIEL ORRANTE
Permit Finaled 12/11/2023 DANIEL ORRANTE

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 10/29/2019 SAFA JAVANMARDI
BHO/Hillside ordinance Cleared 10/29/2019 SAFA JAVANMARDI
BHO/Hillside ordinance Cleared 10/29/2019 SAFA JAVANMARDI
BHO/Hillside ordinance Cleared 10/29/2019 SAFA JAVANMARDI
BHO/Hillside ordinance Cleared 10/29/2019 SAFA JAVANMARDI
Distance to fire station Cleared 10/29/2019 GEORGE SUCHAND
Eng Process Fee Ord 176,300 Cleared 10/29/2019 SAFA JAVANMARDI
Hydrant and Access approval Cleared 10/29/2019 GEORGE SUCHAND
Sewer availability Cleared 10/29/2019 SAFA JAVANMARDI
Low Impact Development Cleared 6/17/2021 MARCO SANCHEZ
Coastal Zone Cleared 8/3/2021 DENZEL HENDERSON
ZI Cleared 8/3/2021 DENZEL HENDERSON
Excavation more than 5-ft deep Cleared 8/20/2021 CALOSHA APPROVED
Roof/Waste drainage to street Cleared 8/24/2021 DINAH GARIN
GPI Written Notices Cleared 11/29/2021 RARES BODEA
Grading Pre-Inspection Cleared 11/29/2021 RARES BODEA

Contact Information

Contractor Emma Corporation; Lic. No.: 458263-B 1318 BROADWAY SUITE 100      SANTA MONICA, CA 90404
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403
Engineer Amoroso,, Gregory Michael; Lic. No.: L8771 24269 PALO VERDE DR      VALENCIA, CA 91354
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/6/2021 Approved ANDREW NAVE
Piling/Pier/Caisson 12/20/2021 Not Ready for Inspection ANDREW NAVE
Footing/Foundation/Slab 2/1/2022 Partial Approval ANDREW NAVE
Deputy Reinf. Concrete 2/3/2022 Conditional Approval ANDREW NAVE
Deputy Shotcrete 2/15/2022 Conditional Approval ANDREW NAVE
Excavation/Setback/Form/Re-Bar 2/15/2022 Partial Approval ANDREW NAVE
Deputy Shotcrete 2/17/2022 Conditional Approval ANDREW NAVE
PLUMBING-Rough 2/25/2022 Approved ANDREW NAVE
Footing/Foundation/Slab 3/31/2022 Partial Approval ANDREW NAVE
Excavation/Setback/Form/Re-Bar 4/20/2022 Partial Approval ANDREW NAVE
Deputy Reinf. Concrete 4/22/2022 Conditional Approval ANDREW NAVE
Deputy Reinf. Concrete 5/12/2022 Conditional Approval ANDREW NAVE
Footing/Foundation/Slab 5/13/2022 Partial Approval OGANES TARAKHCHYAN
Deputy Reinf. Concrete 5/17/2022 Conditional Approval ANDREW NAVE
Deputy Reinf. Masonry 5/23/2022 Conditional Approval ANDREW NAVE
ELECTRICAL-Rough 5/25/2022 Partial Approval ANDREW NAVE
Gas Test 5/25/2022 Approved ANDREW NAVE
PLUMBING-Rough 5/25/2022 Partial Approval ANDREW NAVE
Underground Mechanical 5/25/2022 Partial Approval ANDREW NAVE
Deputy Steel/Welding 5/31/2022 Conditional Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 6/16/2022 Partial Approval ANDREW NAVE
Deputy Other (see comments) 6/28/2022 Approved MICHAEL PELHAM
Deputy Wood Construction 7/28/2022 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 7/28/2022 Corrections Issued BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 8/9/2022 Corrections Issued BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 8/15/2022 Partial Approval BRENDAN LOONEY
Deputy Wood Construction 8/16/2022 Corrections Issued BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 8/19/2022 Corrections Issued BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 9/20/2022 Partial Approval ANDREW NAVE
PLUMBING-Rough 10/6/2022 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Rough 10/7/2022 Approved BRENDAN LOONEY
HVAC-Rough 10/7/2022 Corrections Issued BRENDAN LOONEY
HVAC-Rough 10/12/2022 Approved JUAN VALENZUELA
PLUMBING-Rough 10/17/2022 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 10/19/2022 Approved ANDREW NAVE
Wood Frame 10/19/2022 Not Ready for Inspection ANDREW NAVE
Interior/Exterior Lathing 10/27/2022 Partial Approval ANDREW NAVE
Interior/Exterior Lathing 10/31/2022 Partial Approval CLAYTON GRAHAM
BUILDING-Rough-Frame 11/2/2022 Partial Approval BRENDAN LOONEY
Green Building Rough 11/2/2022 Approved BRENDAN LOONEY
Deputy Steel/Welding 11/9/2022 Conditional Approval BRENDAN LOONEY
Insulation 11/9/2022 Conditional Approval BRENDAN LOONEY
Drywall Nailing 12/6/2022 Conditional Approval BRENDAN LOONEY
Shower Pan 1/18/2023 Approved BRENDAN LOONEY
Interior/Exterior Lathing 1/24/2023 Corrections Issued BRENDAN LOONEY
Interior/Exterior Lathing 1/30/2023 Partial Approval BRENDAN LOONEY
Interior/Exterior Lathing 2/22/2023 Partial Approval STEPHANIE SWANSON
Sewer 6/8/2023 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 6/26/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 6/29/2023 Partial Approval OGANES TARAKHCHYAN
Service/Power Release 7/24/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Pre-Inspection 8/17/2023 Approved EVAN COOPER
Service/Power Release 8/17/2023 Not Ready for Inspection EVAN COOPER
BUILDING-Rough-Frame 8/28/2023 Approved EVAN COOPER
Drywall Nailing 8/28/2023 Approved EVAN COOPER
Final 8/28/2023 Not Ready for Inspection EVAN COOPER
Footing/Foundation/Slab 8/28/2023 Approved EVAN COOPER
Green Building Final 8/28/2023 Not Ready for Inspection EVAN COOPER
PLUMBING-Final 8/28/2023 Not Ready for Inspection EVAN COOPER
SGSOV-Seismic Gas S/O Valve 8/28/2023 SGSOV Approved EVAN COOPER
Service/Power Release 8/28/2023 Not Ready for Inspection EVAN COOPER
Smoke Detectors 8/28/2023 Not Ready for Inspection EVAN COOPER
Verify Sprinkler Sign Off 8/28/2023 Approved EVAN COOPER
HVAC-Final 9/13/2023 Approved EVAN COOPER
Gas Test 9/18/2023 Approved EVAN COOPER
PLUMBING-Final 9/18/2023 Approved EVAN COOPER
ELECTRICAL-Final 9/20/2023 Corrections Issued EVAN COOPER
ELECTRICAL-Final 9/25/2023 Approved OGANES TARAKHCHYAN
Final 10/3/2023 Not Ready for Inspection EVAN COOPER
Green Building Final 10/3/2023 Approved EVAN COOPER
Service/Power Release 10/3/2023 Not Ready for Inspection EVAN COOPER
Smoke Detectors 10/3/2023 Approved EVAN COOPER
Service/Power Release 10/5/2023 Approved KENNETH NAGLE
Final 10/11/2023 Corrections Issued EVAN COOPER
Final 11/1/2023 OK to Issue CofO EVAN COOPER
Final 11/29/2023 OK to Issue CofO EVAN COOPER