14606 W COHASSET ST 91405

Certificate Information: 14606 W COHASSET ST 91405

Application / Permit
19010-20000-04284
Plan Check / Job No.
B19VN16423
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 54'9" X 23'4" ACCESSORY DWELLING UNIT PER AB 494 AND SB 220 ALL WORK PER ENGINEERING
Permit Issued
Issued on 4/9/2020
Issuing Office
Valley
Current Status
CofO Issued on 8/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/25/2019 APPLICANT
Assigned to Plan Check Engineer 10/17/2019 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 10/23/2019 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 10/29/2019 OMID HEDAYAT
Building Plans Picked Up 11/4/2019 APPLICANT
Applicant returned to address corrections 2/14/2020 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 4/2/2020 SEWADA ZADOORAN MILAGARDI
Issued 4/9/2020 LADBS
CofO in Progress 7/21/2022 GREGG CUMMINGS
CofO Issued 8/16/2022 MICHAEL SMITH
Permit Finaled 8/16/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/10/2019 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 12/10/2019 ADRIAN CASTRO
Sewer availability Cleared 12/10/2019 ADRIAN CASTRO
Construction near power lines Cleared 2/4/2020 RIDWAN HARDY
Green Code Cleared 2/4/2020 DAVID MATSON
Hydrant and Access approval Cleared 2/19/2020 JOHN CONNEALLY
Low Impact Development Cleared 2/19/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 2/19/2020 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Motavvef,, Nasser; Lic. No.: C40977 15335 MORRISON ST 370      SHERMAN OAKS, CA 91403

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/13/2020 Approved WILLIAM KUEHN
Excavation/Setback/Form/Re-Bar 5/5/2020 Approved WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 5/18/2020 Partial Inspection WILLIAM KUEHN
PLUMBING-Rough 5/18/2020 Partial Inspection WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 6/23/2020 Partial Inspection WILLIAM KUEHN
Wood Frame 6/23/2020 Not Ready for Inspection WILLIAM KUEHN
BUILDING-Rough-Frame 8/10/2020 Not Ready for Inspection PIERRE VEGA
ELECTRICAL-Rough 8/10/2020 Approved PIERRE VEGA
Green Building Rough 8/10/2020 Not Ready for Inspection PIERRE VEGA
HVAC-Rough 8/10/2020 Not Ready for Inspection PIERRE VEGA
PLUMBING-Rough 8/10/2020 Approved PIERRE VEGA
Verify Sprinkler Sign Off 8/10/2020 Not Ready for Inspection PIERRE VEGA
Wood Frame 8/10/2020 Corrections Issued PIERRE VEGA
BUILDING-Rough-Frame 8/14/2020 Approved GREGG CUMMINGS
Green Building Rough 8/14/2020 Approved GREGG CUMMINGS
HVAC-Rough 8/14/2020 Partial Approval GREGG CUMMINGS
Shower Pan 8/14/2020 Approved GREGG CUMMINGS
Verify Sprinkler Sign Off 8/14/2020 Approved GREGG CUMMINGS
Wood Frame 8/14/2020 Approved GREGG CUMMINGS
Interior/Exterior Lathing 9/8/2020 Corrections Issued GREGG CUMMINGS
Insulation 9/25/2020 Approved GREGG CUMMINGS
Green Building Rough 9/30/2020 Approved GREGG CUMMINGS
Drywall Nailing 10/21/2020 Approved GREGG CUMMINGS
Interior/Exterior Lathing 10/21/2020 Partial Approval GREGG CUMMINGS
Interior/Exterior Lathing 11/6/2020 Approved GREGG CUMMINGS
Grading Pre-Inspection 3/25/2021 No Access for Inspection GREGG CUMMINGS
PLUMBING-Final 3/25/2021 No Access for Inspection GREGG CUMMINGS
Underground Mechanical 5/10/2021 Approved GREGG CUMMINGS
ELECTRICAL-Final 5/19/2021 Corrections Issued GREGG CUMMINGS
PLUMBING-Final 5/19/2021 Not Ready for Inspection GREGG CUMMINGS
Sewer 5/19/2021 Approved GREGG CUMMINGS
ELECTRICAL-Final 2/2/2022 Not Ready for Inspection GREGG CUMMINGS
Final 2/2/2022 Corrections Issued GREGG CUMMINGS
Footing/Foundation/Slab 2/2/2022 Not Ready for Inspection GREGG CUMMINGS
Green Building Final 2/2/2022 Not Ready for Inspection GREGG CUMMINGS
HVAC-Final 2/2/2022 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Final 2/2/2022 Not Ready for Inspection GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 2/2/2022 SGSOV Not Ready GREGG CUMMINGS
Service/Power Release 2/2/2022 Not Ready for Inspection GREGG CUMMINGS
Smoke Detectors 2/2/2022 Not Ready for Inspection GREGG CUMMINGS
Final 6/28/2022 No Access for Inspection GREGG CUMMINGS
Footing/Foundation/Slab 6/28/2022 No Access for Inspection GREGG CUMMINGS
Green Building Final 6/28/2022 No Access for Inspection GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 6/28/2022 SGSOV Not Ready GREGG CUMMINGS
Service/Power Release 6/28/2022 No Access for Inspection GREGG CUMMINGS
Smoke Detectors 6/28/2022 No Access for Inspection GREGG CUMMINGS
Final 7/7/2022 Corrections Issued GREGG CUMMINGS
Footing/Foundation/Slab 7/7/2022 Approved GREGG CUMMINGS
Green Building Final 7/7/2022 Approved GREGG CUMMINGS
HVAC-Final 7/7/2022 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 7/7/2022 SGSOV Approved GREGG CUMMINGS
Service/Power Release 7/7/2022 Not Ready for Inspection GREGG CUMMINGS
Smoke Detectors 7/7/2022 Approved GREGG CUMMINGS
Final 7/14/2022 Corrections Issued GREGG CUMMINGS
Service/Power Release 7/14/2022 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Final 7/20/2022 Approved GREGG CUMMINGS
Final 7/20/2022 OK to Issue CofO GREGG CUMMINGS
PLUMBING-Final 7/20/2022 Approved GREGG CUMMINGS
Service/Power Release 7/20/2022 Approved GREGG CUMMINGS