4565 N ENCINO AVE 91316

Certificate Information: 4565 N ENCINO AVE 91316

Application / Permit
19010-20000-04282
Plan Check / Job No.
B19VN16412
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE AND BASEMENT; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 1/24/2020
Issuing Office
Valley
Current Status
CofO Issued on 5/2/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/25/2019 APPLICANT
Assigned to Plan Check Engineer 10/10/2019 SELLA BENYAMIN
Green Plans Picked Up 10/10/2019 APPLICANT
Corrections Issued 10/16/2019 SELLA BENYAMIN
Quality Review Completed 10/21/2019 STEVEN KIM
Building Plans Picked Up 10/23/2019 APPLICANT
Plan Check Approved 1/22/2020 SELLA BENYAMIN
Issued 1/24/2020 LADBS
CofO in Progress 10/5/2021 RONALD COWAN
Permit Finaled 5/2/2022 RONALD MYRICK
CofO Issued 5/2/2022 RONALD MYRICK
Permit Finaled 5/2/2022 RONALD MYRICK

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 10/28/2019 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 10/28/2019 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 10/28/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 10/29/2019 ADRIAN CASTRO
Hydrant and Access approval Cleared 10/29/2019 GEORGE SUCHAND
Permit Cleared 10/29/2019 ADRIAN CASTRO
Sewer availability Cleared 10/29/2019 ADRIAN CASTRO
Construction near power lines Cleared 11/12/2019 WALTER RAMIREZ
Trees in Parkway Cleared 1/6/2020 JOHN KIM
Low Impact Development Cleared 1/13/2020 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 1/14/2020 GUILLERMO PETRA
Green Code Cleared 1/15/2020 MICHAEL AYERS

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 25531 PRADO DELAS BELLOTAS      CALABASAS, CA 91302

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 3/31/2020 Partial Approval RONALD COWAN
Deputy Reinf. Concrete 4/2/2020 Approved RONALD COWAN
Deputy Grading 4/3/2020 Approved RONALD COWAN
PLUMBING-Rough 5/12/2020 Not Ready for Inspection RONALD COWAN
Underground Mechanical 5/12/2020 Partial Approval RONALD COWAN
Footing/Foundation/Slab 5/13/2020 Partial Approval RONALD COWAN
Underground Mechanical 5/13/2020 Partial Approval RONALD COWAN
Deputy Shotcrete 5/15/2020 Approved RONALD COWAN
Footing/Foundation/Slab 5/29/2020 Partial Approval RONALD COWAN
Deputy Drilled-In Anchors 5/30/2020 Approved RONALD COWAN
Deputy Other (see comments) 6/12/2020 Approved RONALD COWAN
Footing/Foundation/Slab 6/12/2020 Approved RONALD COWAN
Deputy Reinf. Concrete 7/13/2020 Approved RONALD COWAN
BUILDING-Rough-Frame 7/20/2020 Partial Approval RONALD COWAN
SGSOV-Seismic Gas S/O Valve 7/20/2020 SGSOV Not Ready RONALD COWAN
Deputy Drilled-In Anchors 8/12/2020 Approved RONALD COWAN
Deputy Reinf. Concrete 8/18/2020 Approved RONALD COWAN
Footing/Foundation/Slab 8/18/2020 Partial Approval RONALD COWAN
Deputy Reinf. Concrete 9/1/2020 Approved RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 9/3/2020 Partial Approval RONALD COWAN
BUILDING-Rough-Frame 10/14/2020 Corrections Issued RONALD COWAN
Green Building Rough 10/14/2020 Not Ready for Inspection RONALD COWAN
Verify Sprinkler Sign Off 10/14/2020 Not Ready for Inspection RONALD COWAN
Deputy Wood Construction 10/26/2020 Approved RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 11/2/2020 Corrections Issued RONALD COWAN
Wood Frame 11/18/2020 Corrections Issued RONALD COWAN
BUILDING-Rough-Frame 11/24/2020 Partial Approval RONALD COWAN
Green Building Rough 11/24/2020 Approved RONALD COWAN
PLUMBING-Rough 11/24/2020 Corrections Issued RONALD COWAN
Sewer 11/24/2020 Corrections Issued RONALD COWAN
Verify Sprinkler Sign Off 11/24/2020 Not Ready for Inspection RONALD COWAN
ELECTRICAL-Rough 2/1/2021 Approved RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 2/1/2021 Approved RONALD COWAN
Gas Test 2/1/2021 Approved RONALD COWAN
HVAC-Rough 2/1/2021 Approved RONALD COWAN
Interior/Exterior Lathing 2/1/2021 Approved RONALD COWAN
PLUMBING-Rough 2/1/2021 Approved RONALD COWAN
Rough-Elec/Plmb/HVAC 2/1/2021 Approved RONALD COWAN
Sewer 2/1/2021 Approved RONALD COWAN
Shower Pan 2/1/2021 Approved RONALD COWAN
Insulation 2/11/2021 Partial Approval RONALD COWAN
Interior/Exterior Lathing 2/11/2021 Partial Approval RONALD COWAN
Drywall Nailing 2/17/2021 Corrections Issued RONALD COWAN
BUILDING-Rough-Frame 2/22/2021 Approved RONALD COWAN
ELECTRICAL-Rough 2/22/2021 Approved RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 2/22/2021 Approved RONALD COWAN
Footing/Foundation/Slab 2/22/2021 Approved RONALD COWAN
HVAC-Rough 2/22/2021 Approved RONALD COWAN
Insulation 2/22/2021 Approved RONALD COWAN
Interior/Exterior Lathing 2/22/2021 Partial Approval RONALD COWAN
PLUMBING-Rough 2/22/2021 Approved RONALD COWAN
Verify Sprinkler Sign Off 2/22/2021 Approved RONALD COWAN
ELECTRICAL-Final 9/2/2021 Approved RONALD COWAN
Final 9/2/2021 Corrections Issued RONALD COWAN
Green Building Final 9/2/2021 Approved RONALD COWAN
HVAC-Final 9/2/2021 Corrections Issued RONALD COWAN
PLUMBING-Final 9/2/2021 Not Ready for Inspection RONALD COWAN
SGSOV-Seismic Gas S/O Valve 9/2/2021 SGSOV Not Ready RONALD COWAN
Service/Power Release 9/2/2021 Corrections Issued RONALD COWAN
Smoke Detectors 9/2/2021 Approved RONALD COWAN
ELECTRICAL-Final 9/14/2021 Approved RONALD COWAN
Final 9/14/2021 Corrections Issued RONALD COWAN
HVAC-Final 9/14/2021 Approved RONALD COWAN
PLUMBING-Final 9/14/2021 Approved RONALD COWAN
SGSOV-Seismic Gas S/O Valve 9/14/2021 SGSOV Not Ready RONALD COWAN
Service/Power Release 9/14/2021 Approved RONALD COWAN
Final 9/29/2021 OK to Issue CofO RONALD COWAN
SGSOV-Seismic Gas S/O Valve 9/29/2021 SGSOV Approved RONALD COWAN