18083 W BORIS DR 91316
Certificate Information: 18083 W BORIS DR 91316
- Application / Permit
- 19010-20000-04275
- Plan Check / Job No.
- B19VN16397
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW (36'-0"x 13'-0") DETACHED ACCESSORY DWELLING UNIT PER AB 494 & SB 229.
- Permit Issued
- Issued on 1/3/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/24/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/25/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2019 | TROY DEGUZMAN |
| Corrections Issued | 10/22/2019 | TROY DEGUZMAN |
| Quality Review Completed | 10/22/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 10/24/2019 | APPLICANT |
| Green Plans Picked Up | 12/2/2019 | APPLICANT |
| Plan Check Approved | 12/17/2019 | TROY DEGUZMAN |
| Issued | 1/3/2020 | LADBS |
| CofO in Progress | 3/23/2021 | DAVID SANDOVAL |
| CofO Issued | 3/24/2021 | MICHAEL SMITH |
| Permit Finaled | 3/24/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 11/5/2019 | ADRIAN CASTRO |
| BHO/Hillside ordinance | Cleared | 11/5/2019 | ADRIAN CASTRO |
| BHO/Hillside ordinance | Cleared | 11/5/2019 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 11/5/2019 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 11/5/2019 | ADRIAN CASTRO |
| Sewer availability | Cleared | 11/5/2019 | ADRIAN CASTRO |
| BHO/Hillside ordinance | Cleared | 12/12/2019 | ADRIAN CASTRO |
| Green Code | Cleared | 12/13/2019 | MICHAEL AYERS |
| Grading Pre-Inspection | Cleared | 12/17/2019 | TROY DEGUZMAN |
Contact Information
| Architect | Salcedo,, Glen Charles; Lic. No.: C33143 | P O BOX 14202 VAN NUYS, CA 91409 |
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/10/2020 | Approved | DAVID SANDOVAL |
| Pre-Inspection | 2/25/2020 | Approved | DAVID SANDOVAL |
| Footing/Foundation/Slab | 3/3/2020 | Corrections Issued | DAVID SANDOVAL |
| PLUMBING-Rough | 3/3/2020 | Not Ready for Inspection | DAVID SANDOVAL |
| Footing/Foundation/Slab | 3/5/2020 | Approved | DAVID SANDOVAL |
| Deputy Reinf. Concrete | 3/9/2020 | Approved | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2020 | Partial Approval | MICHAEL TEMPLE |
| PLUMBING-Rough | 6/29/2020 | Partial Approval | MICHAEL TEMPLE |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2020 | Partial Approval | DAVID SCANTLIN |
| Insulation | 7/1/2020 | Partial Approval | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2020 | Partial Approval | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2020 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 8/17/2020 | Approved | DAVID SANDOVAL |
| Green Building Rough | 8/17/2020 | Approved | DAVID SANDOVAL |
| HVAC-Rough | 8/17/2020 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 8/17/2020 | Not Ready for Inspection | DAVID SANDOVAL |
| Rough-Elec/Plmb/HVAC | 8/17/2020 | Corrections Issued | DAVID SANDOVAL |
| Verify Sprinkler Sign Off | 8/17/2020 | Approved | DAVID SANDOVAL |
| Insulation | 8/21/2020 | Not Ready for Inspection | DONALD SUNSERI |
| BUILDING-Rough-Frame | 8/24/2020 | Approved | DAVID SANDOVAL |
| Insulation | 8/24/2020 | Approved | DAVID SANDOVAL |
| Rough-Elec/Plmb/HVAC | 8/24/2020 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 9/4/2020 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 9/4/2020 | Approved | DAVID SANDOVAL |
| Final | 1/5/2021 | Corrections Issued | DAVID SANDOVAL |
| Green Building Final | 1/5/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 1/5/2021 | SGSOV Not Ready | DAVID SANDOVAL |
| Service/Power Release | 1/5/2021 | Approved | DAVID SANDOVAL |
| Smoke Detectors | 1/5/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Final | 3/18/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Green Building Final | 3/18/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 3/18/2021 | SGSOV Approved | DAVID SANDOVAL |
| Smoke Detectors | 3/18/2021 | Approved | DAVID SANDOVAL |
| Final | 3/23/2021 | OK to Issue CofO | DAVID SANDOVAL |
| Green Building Final | 3/23/2021 | Approved | DAVID SANDOVAL |