12815 W KAMLOOPS ST 91331
Certificate Information: 12815 W KAMLOOPS ST 91331
- Application / Permit
- 19010-20000-04233
- Plan Check / Job No.
- B19VN16225
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 20'-6" x 24'-6", TWO-STORY ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
- Permit Issued
- Issued on 2/18/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/2/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2019 | ANGELICA DAVE |
| Corrections Issued | 10/7/2019 | ANGELICA DAVE |
| Quality Review Completed | 10/7/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 10/28/2019 | APPLICANT |
| Green Plans Picked Up | 10/28/2019 | APPLICANT |
| Applicant returned to address corrections | 12/2/2019 | ANGELICA DAVE |
| Plan Check Approved | 2/18/2020 | ANGELICA MARTINEZ |
| Issued | 2/18/2020 | LADBS |
| CofO in Progress | 12/24/2020 | MICHEL ABAJAN |
| Permit Finaled | 10/2/2021 | MICHAEL SMITH |
| CofO Issued | 10/2/2021 | MICHAEL SMITH |
| Permit Finaled | 10/2/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/5/2019 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 12/5/2019 | JOHN LIN |
| Sewer availability | Cleared | 12/5/2019 | JOHN LIN |
| Hydrant and Access approval | Cleared | 12/13/2019 | GEORGE SUCHAND |
| Green Code | Cleared | 12/26/2019 | AARON COSTA |
| Low Impact Development | Cleared | 2/13/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 2/18/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mejia,, Fernando Finuliar; Lic. No.: C54382 | 8305 DUCOR AVE WEST HILLS, CA 91304 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/28/2020 | Corrections Issued | MICHEL ABAJAN |
| Footing/Foundation/Slab | 3/12/2020 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 3/12/2020 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 3/12/2020 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 3/31/2020 | Partial Approval | MICHEL ABAJAN |
| Wood Frame | 3/31/2020 | Partial Approval | MICHEL ABAJAN |
| Insulation | 4/2/2020 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 5/26/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 5/26/2020 | Approved | MICHEL ABAJAN |
| Green Building Rough | 5/26/2020 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 5/26/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 5/26/2020 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 5/26/2020 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 6/8/2020 | Approved | MATTHEW NUCKOLLS |
| Insulation | 6/8/2020 | Approved | MATTHEW NUCKOLLS |
| Wood Frame | 6/8/2020 | Approved | MATTHEW NUCKOLLS |
| Drywall Nailing | 6/17/2020 | Approved | MICHEL ABAJAN |
| Shower Pan | 7/21/2020 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 8/6/2020 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 8/26/2020 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 11/16/2020 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 11/16/2020 | Approved | MICHEL ABAJAN |
| Final | 11/16/2020 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 11/16/2020 | Approved | MICHEL ABAJAN |
| HVAC-Final | 11/16/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 11/16/2020 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 11/16/2020 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 11/16/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 11/16/2020 | Approved | MICHEL ABAJAN |
| Final | 12/4/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| Service/Power Release | 12/4/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 12/8/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| Service/Power Release | 12/8/2020 | Approved | MICHEL ABAJAN |
| Final | 12/24/2020 | OK to Issue CofO | MICHEL ABAJAN |