3533 S CHESAPEAKE AVE 1-28 90016
Certificate Information: 3533 S CHESAPEAKE AVE 1-28 90016
- Application / Permit
- 19010-20000-04227
- Plan Check / Job No.
- B19VN16199
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 114' X 68'6-1/2" FIVE STORY 28 UNIT APARTMENT FULLY SPRINKLERED NFPA-13 (TYPE VA CONSTRUCTION ) WITH ATTACHED 1ST FLOOR GARAGE (TYPE IA ) ( TOC, TIER 3 INCLUDING 3 EXTREME LOW INCOME UNITS PER LAMC 12.22A31 [PER DIR-2019-6653-TOC], ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 5/18/2022
- Issuing Office
- Current Status
- CofO Issued on 10/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2019 | RARES BODEA |
| Disabled Access Plans Picked Up | 10/21/2019 | APPLICANT |
| Green Plans Picked Up | 10/21/2019 | APPLICANT |
| Corrections Issued | 10/24/2019 | RARES BODEA |
| Quality Review Completed | 10/29/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 10/30/2019 | APPLICANT |
| Applicant returned to address corrections | 1/6/2021 | RARES BODEA |
| Applicant returned to address corrections | 8/9/2021 | RARES BODEA |
| Applicant returned to address corrections | 12/16/2021 | RARES BODEA |
| Applicant returned to address corrections | 5/9/2022 | RARES BODEA |
| Plan Check Approved | 5/11/2022 | RARES BODEA |
| Issued | 5/18/2022 | APPLICANT |
| CofO in Progress | 10/4/2024 | EDWIN GREGORYONA |
| CofO Issued | 10/4/2024 | ERNESTO CORRAL |
| Permit Finaled | 10/4/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 4/8/2020 | GEORGE SUCHAND |
| DAS Clearance | Cleared | 5/19/2020 | RARES BODEA |
| Green Code | Cleared | 5/20/2020 | MICHAEL AYERS |
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2020 | PAMELA TENEZA |
| Highway dedication | Cleared | 6/3/2020 | ELAINE LEI |
| Sewer availability | Cleared | 6/3/2020 | ELAINE LEI |
| Trees in Parkway | Cleared | 6/11/2020 | JOHN KIM |
| Low Impact Development | Cleared | 10/23/2020 | ANDRES COVARRUBIAS |
| Address approval | Cleared | 10/30/2020 | ELAINE LEI |
| Permit | Cleared | 10/30/2020 | ELAINE LEI |
| Roof/Waste drainage to street | Cleared | 10/30/2020 | ELAINE LEI |
| Building over 3-story or 36-ft | Cleared | 12/22/2020 | CALOSHA APPROVED |
| Fire Marshall Fire Life Safety | Cleared | 1/15/2021 | VIDAL GARCIA |
| DCP conditions approval | Cleared | 9/21/2021 | LOUIE MILLER |
| Density Bonus 12.22.A.31 | Cleared | 9/21/2021 | LOUIE MILLER |
| Frnt yard landscape/Water mgmt | Cleared | 4/6/2022 | KENTON TRINH |
| Miscellaneous | Cleared | 4/6/2022 | KENTON TRINH |
| Miscellaneous | Cleared | 4/6/2022 | KENTON TRINH |
| Miscellaneous | Cleared | 4/6/2022 | KENTON TRINH |
| Miscellaneous | Cleared | 4/6/2022 | KENTON TRINH |
| Opn space landscape/Water mgmt | Cleared | 4/6/2022 | KENTON TRINH |
Contact Information
| Architect | Stockton,, Kenneth; Lic. No.: C19870 | 26500 W AGOURA RD. PMB # 844 CALABASAS, CA 91302 |
| Contractor | Schaffel Development Company Inc; Lic. No.: 411849-B | 15235 BURBANK BLVD #C VAN NUYS, CA 91411 |
| Engineer | Freitas,, Richard Gomes; Lic. No.: C49072 | 240 COPA DE ORO DR BREA, CA 92823 |
Inspector Information
| MARTIN TAVITIAN, (213) 482-7357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/2/2022 | Partial Approval | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 8/2/2022 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 8/3/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Reinf. Concrete | 8/4/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Reinf. Concrete | 8/5/2022 | Partial Approval | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 8/5/2022 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 8/8/2022 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Masonry | 8/10/2022 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 8/11/2022 | Partial Approval | EDWIN GREGORYONA |
| Green Building Rough | 8/11/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| Masonry Wall/Backfill | 8/11/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| Reinforced Concrete Frame | 8/11/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| Verify Sprinkler Sign Off | 8/11/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 8/12/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Reinf. Masonry | 8/12/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Reinf. Concrete | 8/15/2022 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 8/15/2022 | Partial Approval | JAMES POWERS |
| Green Building Rough | 8/15/2022 | Not Ready for Inspection | JAMES POWERS |
| Reinforced Masonry Frame | 8/15/2022 | Partial Approval | JAMES POWERS |
| Verify Sprinkler Sign Off | 8/15/2022 | Not Ready for Inspection | JAMES POWERS |
| Deputy Reinf. Masonry | 8/16/2022 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Masonry | 8/17/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Reinf. Masonry | 8/18/2022 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Masonry | 8/19/2022 | Partial Approval | EDWIN GREGORYONA |
| Green Building Rough | 8/19/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| Masonry Wall/Backfill | 8/19/2022 | Partial Approval | EDWIN GREGORYONA |
| Pre-Inspection | 8/19/2022 | Approved | EDWIN GREGORYONA |
| Reinforced Masonry Frame | 8/19/2022 | Partial Approval | EDWIN GREGORYONA |
| Verify Sprinkler Sign Off | 8/19/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| Deputy Reinf. Masonry | 8/23/2022 | Conditional Approval | WINSTON DUNNING |
| Deputy Reinf. Masonry | 8/25/2022 | Partial Approval | EDWIN GREGORYONA |
| Green Building Rough | 8/25/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| Masonry Wall/Backfill | 8/25/2022 | Partial Approval | EDWIN GREGORYONA |
| Reinforced Masonry Frame | 8/25/2022 | Partial Approval | EDWIN GREGORYONA |
| Verify Sprinkler Sign Off | 8/25/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| Deputy Reinf. Masonry | 8/26/2022 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Masonry | 8/30/2022 | Partial Approval | EDWIN GREGORYONA |
| Green Building Rough | 8/30/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| Reinforced Masonry Frame | 8/30/2022 | Partial Approval | EDWIN GREGORYONA |
| Verify Sprinkler Sign Off | 8/30/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 10/3/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Wall Anchors | 10/4/2022 | Partial Approval | GREGORY POMISH |
| Deputy Reinf. Concrete | 10/5/2022 | Partial Approval | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 10/5/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| Wall Anchors | 10/5/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 10/13/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Wood Construction | 10/28/2022 | Partial Approval | EDWIN GREGORYONA |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2022 | Partial Approval | EDWIN GREGORYONA |
| Deputy Wood Construction | 11/15/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2022 | Partial Approval | EDWIN GREGORYONA |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2022 | Partial Approval | EDWIN GREGORYONA |
| Deputy Wood Construction | 12/7/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2022 | Partial Approval | EDWIN GREGORYONA |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2023 | Partial Approval | EDWIN GREGORYONA |
| Green Building Rough | 3/6/2023 | Not Ready for Inspection | EDWIN GREGORYONA |
| Verify Sprinkler Sign Off | 3/6/2023 | Not Ready for Inspection | EDWIN GREGORYONA |
| Wood Frame | 3/6/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Wood Construction | 3/7/2023 | Partial Approval | EDWIN GREGORYONA |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2023 | Partial Approval | EDWIN GREGORYONA |
| Special/Order Compliance | 4/17/2023 | Approved | EDWIN GREGORYONA |
| Green Building Rough | 4/25/2023 | Not Ready for Inspection | EDWIN GREGORYONA |
| Insulation | 4/25/2023 | Partial Approval | EDWIN GREGORYONA |
| Verify Sprinkler Sign Off | 4/25/2023 | Approved | EDWIN GREGORYONA |
| Wood Frame | 4/25/2023 | Not Ready for Inspection | EDWIN GREGORYONA |
| Green Building Rough | 5/11/2023 | Approved | EDWIN GREGORYONA |
| Wood Frame | 5/11/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Drilled-In Anchors | 5/12/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Insulation | 6/8/2023 | Partial Inspection | EDWIN GREGORYONA |
| Drywall Nailing | 6/29/2023 | Partial Approval | EDWIN GREGORYONA |
| Drywall Nailing | 7/25/2023 | Partial Approval | EDWIN GREGORYONA |
| Drywall Nailing | 8/4/2023 | Partial Approval | EDWIN GREGORYONA |
| Interior/Exterior Lathing | 8/25/2023 | Partial Approval | EDWIN GREGORYONA |
| Light Gage Steel Frame | 9/20/2023 | Partial Approval | EDWIN GREGORYONA |
| Light Gage Steel Frame | 10/2/2023 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 1/9/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Drilled-In Anchors | 2/15/2024 | Partial Approval | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 2/15/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 2/27/2024 | Partial Approval | EDWIN GREGORYONA |
| Masonry Wall/Backfill | 2/27/2024 | Partial Approval | EDWIN GREGORYONA |
| Drywall Nailing | 5/6/2024 | Partial Approval | EDWIN GREGORYONA |
| Drywall Nailing | 8/13/2024 | Approved | EDWIN GREGORYONA |
| Final | 8/13/2024 | OK to Issue CofO | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 8/13/2024 | Approved | EDWIN GREGORYONA |
| Green Building Final | 8/13/2024 | Approved | EDWIN GREGORYONA |
| Reinforced Concrete Frame | 8/13/2024 | Approved | EDWIN GREGORYONA |
| Reinforced Masonry Frame | 8/13/2024 | Approved | EDWIN GREGORYONA |
| SGSOV-Seismic Gas S/O Valve | 8/13/2024 | SGSOV Approved | EDWIN GREGORYONA |
| Smoke Detectors | 8/13/2024 | Approved | EDWIN GREGORYONA |
| Structural Steel Frame | 8/13/2024 | Approved | EDWIN GREGORYONA |
| T-Bar Ceiling | 8/13/2024 | Approved | EDWIN GREGORYONA |
| Verify Rec and Parks Fee Memo | 8/13/2024 | Approved | EDWIN GREGORYONA |
| Wood Frame | 8/13/2024 | Approved | EDWIN GREGORYONA |