1262 N HYPERION AVE BLDG C 90029
Certificate Information: 1262 N HYPERION AVE BLDG C 90029
- Application / Permit
- 19010-20000-04194
- Plan Check / Job No.
- B19VN16113
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 48'-11" x 27'-7" Fully Sprinkelred Single family Dwelling with attached garage per Small lot subdivision pursuant to Tentative Tract Map No./Preliminary Parcel Map No. AA-2018-1866-PMLA-SL. A certificate of occupancy (temporary or final) shall not be issued until after the final map has been recorded. Fire sprinklers required throughout. All work per engineering.
- Permit Issued
- Issued on 5/10/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2019 | ABDUL CHEGENI |
| Green Plans Picked Up | 10/18/2019 | APPLICANT |
| Corrections Issued | 11/7/2019 | ABDUL CHEGENI |
| Quality Review Completed | 11/7/2019 | STEVEN KIM |
| Building Plans Picked Up | 11/7/2019 | APPLICANT |
| Applicant returned to address corrections | 10/29/2020 | COLIN LOREDO |
| Applicant returned to address corrections | 11/23/2020 | COLIN LOREDO |
| Applicant returned to address corrections | 5/27/2021 | COLIN LOREDO |
| Applicant returned to address corrections | 6/3/2021 | COLIN LOREDO |
| Plan Check Approved | 7/13/2021 | COLIN LOREDO |
| Issued | 5/10/2022 | APPLICANT |
| CofO in Progress | 2/6/2024 | BRENDAN MORELLI |
| Permit Finaled | 2/7/2024 | DEROLD HAUFF |
| CofO Issued | 2/7/2024 | DEROLD HAUFF |
| Permit Finaled | 2/7/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/31/2020 | JEANETTE VONG |
| Permit | Cleared | 1/31/2020 | JEANETTE VONG |
| Green Code | Cleared | 7/20/2020 | MICHAEL AYERS |
| Hydrant and Access approval | Cleared | 9/22/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 10/27/2020 | MARTIN FRAGOSO |
| Highway dedication | Cleared | 10/29/2020 | LINDA MARGARET |
| Roof/Waste drainage to street | Cleared | 10/29/2020 | LINDA MARGARET |
| Eng Process Fee Ord 176,300 | Cleared | 11/6/2020 | JEANIE LAM |
| Sewer availability | Cleared | 11/13/2020 | JEANIE LAM |
| Building over 3-story or 36-ft | Cleared | 11/23/2020 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 11/23/2020 | ABDUL CHEGENI |
| Grading Pre-Inspection | Cleared | 11/23/2020 | ABDUL CHEGENI |
| Frnt yard landscape/Water mgmt | Cleared | 1/5/2021 | LAUREN PADICK |
| ZA Case | Cleared | 1/5/2021 | LAUREN PADICK |
| Miscellaneous | Cleared | 7/13/2021 | ABDUL CHEGENI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rahmanishamsi,, Esmaeel; Lic. No.: C88618 | 8070 E OAK RIDGE CIRCLE ANAHEIM, CA 92808 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/29/2022 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 8/29/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 9/7/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 9/7/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 11/10/2022 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 11/10/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 11/16/2022 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 12/12/2022 | Partial Inspection | SCOTT FINNILA |
| Underground Mechanical | 12/12/2022 | Partial Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 12/29/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 12/29/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Green Building Rough | 2/6/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 2/6/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Deputy Wood Construction | 2/7/2023 | Conditional Approval | ALIZAH MAYAGOITIA |
| Drywall Nailing | 2/8/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Deputy Wood Construction | 2/14/2023 | Conditional Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Drywall Nailing | 3/3/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 3/13/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Drywall Nailing | 3/31/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Rough | 3/31/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Drywall Nailing | 5/1/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 5/23/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Deputy Wood Construction | 5/24/2023 | Conditional Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Rough-Elec/Plmb/HVAC | 6/20/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 6/22/2023 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Rough | 6/26/2023 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 6/29/2023 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 6/30/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 7/7/2023 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 7/7/2023 | Approved | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 7/7/2023 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 7/14/2023 | Approved | SCOTT FINNILA |
| Shower Pan | 7/14/2023 | Approved | SCOTT FINNILA |
| Drywall Nailing | 7/24/2023 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 7/24/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 8/2/2023 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 1/2/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Service/Power Release | 1/2/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 1/9/2024 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 1/9/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 1/17/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 1/29/2024 | Corrections Issued | BRENDAN MORELLI |
| Footing/Foundation/Slab | 1/29/2024 | Approved | BRENDAN MORELLI |
| Gas Test | 1/29/2024 | Approved | BRENDAN MORELLI |
| Green Building Final | 1/29/2024 | Approved | BRENDAN MORELLI |
| HVAC-Final | 1/29/2024 | Approved | BRENDAN MORELLI |
| PLUMBING-Final | 1/29/2024 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 1/29/2024 | SGSOV Approved | BRENDAN MORELLI |
| Service/Power Release | 1/29/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| Smoke Detectors | 1/29/2024 | Approved | BRENDAN MORELLI |
| Final | 1/31/2024 | OK to Issue CofO | BRENDAN MORELLI |
| Service/Power Release | 1/31/2024 | Approved | BRENDAN MORELLI |