3609 S GREENWOOD AVE 90066

Certificate Information: 3609 S GREENWOOD AVE 90066

Application / Permit
19010-20000-04190
Plan Check / Job No.
B19VN16109
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
NEW (11"-0 x 19'-0") DETACHED PATIO COVER CABANA. WORK PER ENGINEER.
Permit Issued
Issued on 11/22/2019
Issuing Office
Valley
Current Status
CofO Issued on 8/11/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/20/2019 APPLICANT
Assigned to Plan Check Engineer 10/3/2019 TROY DEGUZMAN
Corrections Issued 10/6/2019 TROY DEGUZMAN
Quality Review Completed 10/10/2019 CHON CHIO KUO
Building Plans Picked Up 10/17/2019 APPLICANT
Green Plans Picked Up 10/17/2019 APPLICANT
Applicant returned to address corrections 11/12/2019 TROY DEGUZMAN
Plan Check Approved 11/18/2019 TROY DEGUZMAN
Issued 11/22/2019 LADBS
CofO in Progress 8/11/2020 JOHNNY MIRANDA
CofO Issued 8/11/2020 VINCENT COTTON
Permit Finaled 8/11/2020 VINCENT COTTON

Permit Application Clearance Information

Specific Plan Cleared 10/29/2019 RINA LARA
ZI Cleared 10/29/2019 RINA LARA
Eng Process Fee Ord 176,300 Cleared 11/5/2019 LEE GUILBEAUX
Sewer availability Cleared 11/5/2019 LEE GUILBEAUX
Grading Pre-Inspection Cleared 11/12/2019 TROY DEGUZMAN
Roof/Waste drainage to street Cleared 11/12/2019 GUILLERMO PETRA
Green Code Cleared 11/18/2019 DAVID MATSON

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 25531 PRADO DELAS BELLOTAS      CALABASAS, CA 91302

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/16/2020 Approved JOHNNY MIRANDA
Underground Mechanical 1/16/2020 Approved JOHNNY MIRANDA
Footing/Foundation/Slab 1/21/2020 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 2/6/2020 Partial Approval MICHAEL TEMPLE
ELECTRICAL-Rough 2/18/2020 Approved JOHNNY MIRANDA
PLUMBING-Rough 2/18/2020 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 2/19/2020 Partial Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 2/25/2020 Conditional Approval JUAN VALENZUELA
Green Building Rough 2/25/2020 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 7/6/2020 Approved JOHNNY MIRANDA
Drywall Nailing 7/6/2020 Approved JOHNNY MIRANDA
ELECTRICAL-Final 7/6/2020 Approved JOHNNY MIRANDA
Final 7/6/2020 Partial Inspection JOHNNY MIRANDA
Green Building Final 7/6/2020 Approved JOHNNY MIRANDA
PLUMBING-Final 7/6/2020 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 7/6/2020 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 7/6/2020 Approved JOHNNY MIRANDA
Verify Sprinkler Sign Off 7/6/2020 Approved JOHNNY MIRANDA
Final 7/14/2020 Not Ready for Inspection JOHNNY MIRANDA
Final 7/28/2020 Not Ready for Inspection JOHNNY MIRANDA
Service/Power Release 7/28/2020 Not Ready for Inspection JOHNNY MIRANDA
Final 8/3/2020 Partial Approval JOHNNY MIRANDA
Service/Power Release 8/3/2020 Not Required JOHNNY MIRANDA