17143 W ADLON ROAD 91436

Certificate Information: 17143 W ADLON ROAD 91436

Application / Permit
19010-20000-04177
Plan Check / Job No.
B19VN16034
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW 12'X 18' REC. ROOM WITH 10' X 18' ATTACHED TRELLIS
Permit Issued
Issued on 5/27/2020
Issuing Office
Metro
Current Status
CofO Issued on 8/7/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/19/2019 APPLICANT
Green Plans Picked Up 10/1/2019 APPLICANT
Assigned to Plan Check Engineer 10/3/2019 SELLA BENYAMIN
Corrections Issued 10/7/2019 SELLA BENYAMIN
Quality Review Completed 10/9/2019 STEVEN KIM
Plan Check Approved 5/5/2020 SELLA BENYAMIN
Issued 5/27/2020 LADBS
Building Plans Picked Up 5/28/2020 APPLICANT
CofO in Progress 7/28/2021 MICHAEL PELHAM
CofO Issued 8/7/2021 MICHAEL SMITH
Permit Finaled 8/7/2021 MICHAEL SMITH

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 12/10/2019 ADRIAN CASTRO
BHO/Hillside ordinance Cleared 12/10/2019 ADRIAN CASTRO
BHO/Hillside ordinance Cleared 12/10/2019 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 12/10/2019 ADRIAN CASTRO
Low Impact Development Cleared 2/11/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 2/26/2020 JOHN TRIANTAFYLLOS
Green Code Cleared 4/16/2020 DAVID MATSON
GPI Written Notices Cleared 5/5/2020 SELLA BENYAMIN
Grading Pre-Inspection Cleared 5/5/2020 SELLA BENYAMIN

Contact Information

Contractor Giant First Construction Inc; Lic. No.: 853860-B 40 SABRA AVE      OAK PARK, CA 91377
Engineer Wang,, Hongyu; Lic. No.: C72679 6270 MCLEOD DR STE 140      LAS VEGAS, NV 89120

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/18/2020 Partial Approval RONALD COWAN
Footing/Foundation/Slab 8/18/2020 Partial Approval RONALD COWAN
PLUMBING-Rough 8/18/2020 Partial Approval RONALD COWAN
Footing/Foundation/Slab 8/24/2020 Partial Approval RONALD COWAN
Underground Mechanical 8/24/2020 Partial Approval RONALD COWAN
Wood Frame 10/23/2020 Partial Approval RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 11/5/2020 Approved RONALD COWAN
PLUMBING-Rough 11/5/2020 Approved RONALD COWAN
HVAC-Rough 11/19/2020 Approved RONALD COWAN
Shower Pan 11/19/2020 Approved RONALD COWAN
BUILDING-Rough-Frame 12/7/2020 Approved RONALD COWAN
ELECTRICAL-Rough 12/7/2020 Approved RONALD COWAN
Green Building Rough 12/7/2020 Approved RONALD COWAN
Interior/Exterior Lathing 12/7/2020 Partial Approval RONALD COWAN
Verify Sprinkler Sign Off 12/7/2020 Approved RONALD COWAN
Insulation 12/14/2020 Approved RONALD COWAN
Interior/Exterior Lathing 12/14/2020 Approved RONALD COWAN
Drywall Nailing 12/28/2020 Approved JOSEPH SAGEN
Gas Test 3/2/2021 Approved RONALD COWAN
HVAC-Final 4/16/2021 Approved RONALD COWAN
PLUMBING-Final 4/16/2021 Approved RONALD COWAN
ELECTRICAL-Final 4/21/2021 Approved RONALD COWAN
PLUMBING-Final 4/21/2021 Approved RONALD COWAN
SGSOV-Seismic Gas S/O Valve 4/21/2021 SGSOV Approved RONALD COWAN
Smoke Detectors 4/21/2021 Approved RONALD COWAN
Final 6/4/2021 Not Ready for Inspection RONALD COWAN
Footing/Foundation/Slab 6/4/2021 Approved RONALD COWAN
Green Building Final 6/4/2021 Approved RONALD COWAN
Service/Power Release 6/4/2021 Approved RONALD COWAN
Final 6/7/2021 Corrections Issued MICHAEL PELHAM
Final 7/23/2021 Conditional Approval RONALD COWAN