11910 N BORDEN AVE 91340

Certificate Information: 11910 N BORDEN AVE 91340

Application / Permit
19010-20000-04143
Plan Check / Job No.
B19VN15897
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 2-STORY (20'X30') ADU PER AB 494 AND SB 229.
Permit Issued
Issued on 7/1/2020
Issuing Office
Valley
Current Status
Issued on 7/1/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/18/2019 APPLICANT
Assigned to Plan Check Engineer 9/26/2019 ABDUL CHEGENI
Plans on Hold 9/30/2019 ABDUL CHEGENI
Green Plans Picked Up 10/2/2019 APPLICANT
Hold Released 10/31/2019 ABDUL CHEGENI
Corrections Issued 10/31/2019 ABDUL CHEGENI
Quality Review Completed 10/31/2019 STEVEN KIM
Building Plans Picked Up 11/4/2019 APPLICANT
Applicant returned to address corrections 1/16/2020 ABDUL CHEGENI
Plan Check Approved 1/29/2020 ABDUL CHEGENI
Issued 7/1/2020 APPLICANT

Permit Application Clearance Information

Hold Cleared 10/30/2019 LOURDES RAMIRO
Address approval Cleared 12/11/2019 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 12/11/2019 ADRIAN CASTRO
Permit Cleared 12/11/2019 ADRIAN CASTRO
Sewer availability Cleared 12/11/2019 ADRIAN CASTRO
Green Code Cleared 1/22/2020 AARON COSTA
Hydrant and Access approval Cleared 1/23/2020 GEORGE SUCHAND
Low Impact Development Cleared 1/24/2020 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 1/29/2020 GUILLERMO PETRA

Contact Information

Contractor De La Rosa Construction; Lic. No.: 855010-B 3684 E PERCY ST      LOS ANGELES, CA 90023
Engineer Carrizosa,, Richard Garcia; Lic. No.: C86224 1505 LYNDHURST AVE      HACIENDA HEIGHTS, CA 917452932

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/6/2020 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 7/14/2020 Not Ready for Inspection MICHEL ABAJAN
Footing/Foundation/Slab 7/17/2020 Corrections Issued MICHEL ABAJAN
Sewer 7/27/2020 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 8/11/2020 No Access for Inspection MICHEL ABAJAN
Footing/Foundation/Slab 9/18/2020 Approved MICHEL ABAJAN
Wood Frame 10/6/2020 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 11/2/2020 Partial Inspection MICHEL ABAJAN
ELECTRICAL-Rough 11/2/2020 Partial Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 11/2/2020 Partial Approval MICHEL ABAJAN
Green Building Rough 11/2/2020 Partial Inspection MICHEL ABAJAN
PLUMBING-Rough 11/2/2020 Partial Inspection MICHEL ABAJAN
Verify Sprinkler Sign Off 11/2/2020 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 11/9/2020 Approved MICHEL ABAJAN
ELECTRICAL-Rough 11/9/2020 Approved MICHEL ABAJAN
Green Building Rough 11/9/2020 Approved MICHEL ABAJAN
HVAC-Rough 11/9/2020 Approved MICHEL ABAJAN
PLUMBING-Rough 11/9/2020 Approved MICHEL ABAJAN
Drywall Nailing 11/20/2020 Approved MICHEL ABAJAN
Insulation 11/20/2020 Conditional Approval MICHEL ABAJAN
Interior/Exterior Lathing 1/5/2021 No Access for Inspection MICHEL ABAJAN
Interior/Exterior Lathing 1/7/2021 Approved MICHEL ABAJAN