11910 N BORDEN AVE 91340
Certificate Information: 11910 N BORDEN AVE 91340
- Application / Permit
- 19010-20000-04143
- Plan Check / Job No.
- B19VN15897
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 2-STORY (20'X30') ADU PER AB 494 AND SB 229.
- Permit Issued
- Issued on 7/1/2020
- Issuing Office
- Valley
- Current Status
- Issued on 7/1/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2019 | ABDUL CHEGENI |
| Plans on Hold | 9/30/2019 | ABDUL CHEGENI |
| Green Plans Picked Up | 10/2/2019 | APPLICANT |
| Hold Released | 10/31/2019 | ABDUL CHEGENI |
| Corrections Issued | 10/31/2019 | ABDUL CHEGENI |
| Quality Review Completed | 10/31/2019 | STEVEN KIM |
| Building Plans Picked Up | 11/4/2019 | APPLICANT |
| Applicant returned to address corrections | 1/16/2020 | ABDUL CHEGENI |
| Plan Check Approved | 1/29/2020 | ABDUL CHEGENI |
| Issued | 7/1/2020 | APPLICANT |
Permit Application Clearance Information
| Hold | Cleared | 10/30/2019 | LOURDES RAMIRO |
| Address approval | Cleared | 12/11/2019 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/11/2019 | ADRIAN CASTRO |
| Permit | Cleared | 12/11/2019 | ADRIAN CASTRO |
| Sewer availability | Cleared | 12/11/2019 | ADRIAN CASTRO |
| Green Code | Cleared | 1/22/2020 | AARON COSTA |
| Hydrant and Access approval | Cleared | 1/23/2020 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 1/24/2020 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 1/29/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | De La Rosa Construction; Lic. No.: 855010-B | 3684 E PERCY ST LOS ANGELES, CA 90023 |
| Engineer | Carrizosa,, Richard Garcia; Lic. No.: C86224 | 1505 LYNDHURST AVE HACIENDA HEIGHTS, CA 917452932 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/6/2020 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 7/14/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| Footing/Foundation/Slab | 7/17/2020 | Corrections Issued | MICHEL ABAJAN |
| Sewer | 7/27/2020 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 8/11/2020 | No Access for Inspection | MICHEL ABAJAN |
| Footing/Foundation/Slab | 9/18/2020 | Approved | MICHEL ABAJAN |
| Wood Frame | 10/6/2020 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 11/2/2020 | Partial Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 11/2/2020 | Partial Inspection | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2020 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 11/2/2020 | Partial Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 11/2/2020 | Partial Inspection | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 11/2/2020 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 11/9/2020 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 11/9/2020 | Approved | MICHEL ABAJAN |
| Green Building Rough | 11/9/2020 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 11/9/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 11/9/2020 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 11/20/2020 | Approved | MICHEL ABAJAN |
| Insulation | 11/20/2020 | Conditional Approval | MICHEL ABAJAN |
| Interior/Exterior Lathing | 1/5/2021 | No Access for Inspection | MICHEL ABAJAN |
| Interior/Exterior Lathing | 1/7/2021 | Approved | MICHEL ABAJAN |