3200 E OLYMPIC BLVD 1-5 90023

Certificate Information: 3200 E OLYMPIC BLVD 1-5 90023

Application / Permit
19010-20000-04112
Plan Check / Job No.
B19VN15775
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
NEW ONE STORY RETAIL BUILDING PER ENGINEERING. CONSTRUCTION TYPE VB. NFPA 13 FIRE SPRINKLERS REQUIRED THROUGHOUT OUT.
Permit Issued
Issued on 7/27/2022
Issuing Office
Valley
Current Status
CofO Issued on 7/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/17/2019 APPLICANT
Assigned to Plan Check Engineer 10/10/2019 RODNEY SAMIIAN
Disabled Access Plans Picked Up 10/16/2019 APPLICANT
Green Plans Picked Up 10/16/2019 APPLICANT
Corrections Issued 10/17/2019 RODNEY SAMIIAN
Quality Review Completed 10/21/2019 ABDUL CHEGENI
Building Plans Picked Up 1/7/2020 APPLICANT
Applicant returned to address corrections 2/3/2020 RODNEY SAMIIAN
Applicant returned to address corrections 2/24/2020 RODNEY SAMIIAN
Applicant returned to address corrections 8/19/2020 RODNEY SAMIIAN
Plan Check Approved 6/17/2022 COLIN LOREDO
Issued 7/27/2022 APPLICANT
CofO Issued 7/24/2025 ERNESTO CORRAL
Permit Finaled 7/24/2025 ERNESTO CORRAL

Permit Application Clearance Information

Green Code Cleared 1/10/2020 AARON COSTA
Address approval Cleared 2/12/2020 GUILLERMO PETRA
DAS Clearance Cleared 2/12/2020 OLLIE CARTER
Eng Process Fee Ord 176,300 Cleared 2/12/2020 GUILLERMO PETRA
Work Adjacent to Public Way Cleared 2/12/2020 GUILLERMO PETRA
Highway dedication Cleared 4/22/2020 JAMES MORALEZ
Permit Cleared 4/22/2020 JAMES MORALEZ
Hydrant and Access approval Cleared 8/6/2020 MATTHEW CRAIG
Sewer availability Cleared 8/21/2020 CELINA MORENO
Driveway location Cleared 10/14/2020 MOHAMMAD HASAN
Low Impact Development Cleared 9/29/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 2/22/2022 AMAAN MALIK
Clean Up Green Up Cleared 4/7/2022 PABLO ESTRADA
Comm Cor/Mini-Mall Cleared 4/7/2022 PABLO ESTRADA
Comm Cor/Mini-Mall Cleared 4/7/2022 PABLO ESTRADA
Prkng lot landscape/Water mgmt Cleared 4/7/2022 PABLO ESTRADA
Project located in CRA area Cleared 4/7/2022 PABLO ESTRADA
ZI Cleared 4/7/2022 PABLO ESTRADA
ZI Cleared 4/7/2022 PABLO ESTRADA
Miscellaneous Cleared 6/17/2022 RODNEY SAMIIAN

Contact Information

Architect Maly,, Farzin; Lic. No.: C33731 7136 HASKELL AVENUE # 320      VAN NUYS, CA 91406
Contractor A M C Group Inc; Lic. No.: 749575-B P O BOX 572110      TARZANA, CA 91357
Engineer Pirbadian,, Amir; Lic. No.: C72413 5435 BALBOA BLVD 214      ENCINO, CA 91342

Inspector Information

RONALD JIMENEZ, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
LARRY ARNICK, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
JOEY BUCHANAN, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
ERNESTO CORRAL, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL ESPINOZA, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/24/2022 Approved RAFAEL ESPINOZA
Deputy Reinf. Concrete 9/15/2022 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 9/19/2022 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 9/19/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 9/21/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 10/14/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 10/25/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 10/25/2022 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 10/25/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 10/28/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/2/2022 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 11/2/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 11/3/2022 Conditional Approval MICHAEL ROSENBERG
Masonry Wall/Backfill 11/4/2022 Partial Inspection RAFAEL ESPINOZA
Masonry Wall/Backfill 11/10/2022 Partial Inspection RAFAEL ESPINOZA
Deputy Reinf. Masonry 11/14/2022 Conditional Approval MICHAEL ROSENBERG
Masonry Wall/Backfill 11/14/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 11/16/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 11/16/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 11/21/2022 Conditional Approval MICHAEL ROSENBERG
Masonry Wall/Backfill 11/21/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 11/30/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 12/1/2022 Conditional Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 12/1/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 12/2/2022 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 1/24/2023 Partial Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 2/6/2023 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 3/2/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 3/7/2023 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 3/9/2023 Approved RAFAEL ESPINOZA
Deputy Reinf. Concrete 3/10/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 4/10/2023 Conditional Approval MICHAEL ROSENBERG
Green Building Rough 5/12/2023 Approved RAFAEL ESPINOZA
Verify Sprinkler Sign Off 5/12/2023 Partial Inspection RAFAEL ESPINOZA
Wood Frame 5/12/2023 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 6/15/2023 Approved RAFAEL ESPINOZA
Insulation 7/18/2023 Approved RAFAEL ESPINOZA
Drywall Nailing 7/26/2023 Approved LARRY ARNICK
Pre-Inspection 8/11/2023 Partial Inspection RAFAEL ESPINOZA
Grading Pre-Inspection 10/25/2023 Partial Inspection RAFAEL ESPINOZA
Grading Pre-Inspection 12/18/2023 Corrections Issued LARRY ARNICK
Grading Pre-Inspection 12/29/2023 Approved RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 2/16/2024 Partial Approval RAMAZANALI ALMASI
Grading Pre-Inspection 5/21/2024 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 6/17/2024 Approved RAFAEL ESPINOZA
Green Building Final 6/17/2024 Not Ready for Inspection RAFAEL ESPINOZA
Special/Order Compliance 6/27/2024 Approved RAFAEL ESPINOZA
Final 5/20/2025 Not Ready for Inspection LARRY ARNICK
Green Building Final 5/20/2025 Not Ready for Inspection LARRY ARNICK
Reinforced Masonry Frame 5/20/2025 Not Ready for Inspection LARRY ARNICK
SGSOV-Seismic Gas S/O Valve 5/20/2025 SGSOV Not Ready LARRY ARNICK
Smoke Detectors 5/20/2025 Approved LARRY ARNICK
Structural Steel Frame 5/20/2025 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 5/20/2025 Not Ready for Inspection LARRY ARNICK
Wood Frame 5/20/2025 Conditional Approval LARRY ARNICK
Final 6/24/2025 Conditional Approval LARRY ARNICK
Green Building Final 6/24/2025 Approved LARRY ARNICK
Reinforced Masonry Frame 6/24/2025 Approved LARRY ARNICK
SGSOV-Seismic Gas S/O Valve 6/24/2025 SGSOV Approved LARRY ARNICK
Structural Steel Frame 6/24/2025 Approved LARRY ARNICK
Verify Sprinkler Sign Off 6/24/2025 Approved LARRY ARNICK
Wood Frame 6/24/2025 Approved LARRY ARNICK