805 S SPRING ST 90014
Certificate Information: 805 S SPRING ST 90014
- Application / Permit
- 19010-20000-04101
- Plan Check / Job No.
- B19VN15712
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (7) Carport
- Work Description
- NEW 9'-8" x 11'-6" CARPORT FOR SOLAR PANELS IN EXISTING AUTO PARK
- Permit Issued
- Issued on 1/3/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/26/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/16/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/10/2019 | SELLA BENYAMIN |
| Disabled Access Plans Picked Up | 10/18/2019 | APPLICANT |
| Corrections Issued | 10/23/2019 | SELLA BENYAMIN |
| Quality Review Completed | 10/24/2019 | STEVEN KIM |
| Building Plans Picked Up | 11/1/2019 | APPLICANT |
| Applicant returned to address corrections | 12/20/2019 | SELLA BENYAMIN |
| Plan Check Approved | 12/31/2019 | SELLA BENYAMIN |
| Issued | 1/3/2020 | LADBS |
| CofO in Progress | 2/21/2020 | LESLIE TRUJILLO |
| Permit Finaled | 2/26/2020 | DAVID TSAU |
| CofO Issued | 2/26/2020 | DAVID TSAU |
| Permit Finaled | 2/26/2020 | DAVID TSAU |
Permit Application Clearance Information
| "D" conditions | Cleared | 11/20/2019 | SOPHIE GABEL-SCHEINBAU |
| Eng Process Fee Ord 176,300 | Cleared | 11/27/2019 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 11/27/2019 | ADRIAN CASTRO |
| Project located in CRA area | Cleared | 12/2/2019 | GRACIELA ACOSTA |
| DAS Clearance | Cleared | 12/16/2019 | NORLITO MEDRANO |
Contact Information
| Contractor | Cali Power Electric; Lic. No.: 1032379-B | 8633 BALBOA BLVD UNIT 18 NORTHRIDGE, CA 91325 |
Inspector Information
| NICK DANERI, (213) 202-5615 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/11/2020 | Approved | LESLIE TRUJILLO |
| Footing/Foundation/Slab | 2/11/2020 | Approved | LESLIE TRUJILLO |
| METHANE-Barrier | 2/11/2020 | Conditional Approval | LESLIE TRUJILLO |
| METHANE-Subgrade | 2/11/2020 | Conditional Approval | LESLIE TRUJILLO |
| Structural Steel Frame | 2/11/2020 | Partial Approval | LESLIE TRUJILLO |
| Final | 2/18/2020 | Not Ready for Inspection | LESLIE TRUJILLO |
| SGSOV-Seismic Gas S/O Valve | 2/18/2020 | SGSOV Not Required | LESLIE TRUJILLO |
| Smoke Detectors | 2/18/2020 | Approved | LESLIE TRUJILLO |
| Wood Frame | 2/18/2020 | Approved | LESLIE TRUJILLO |
| Final | 2/20/2020 | OK to Issue CofO | LESLIE TRUJILLO |