18440 W BRYANT ST 91325
Certificate Information: 18440 W BRYANT ST 91325
- Application / Permit
- 19010-20000-04093
- Plan Check / Job No.
- B19VN15654
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (8) Auto Repair Garage
- Work Description
- AUTO REPAIR GARAGE ( No body & Fender work proposed)
- Permit Issued
- Issued on 11/13/2020
- Issuing Office
- Current Status
- CofO Issued on 7/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2019 | RUDOLF KINAR MELIKOFF |
| Corrections Issued | 9/30/2019 | RUDOLF KINAR MELIKOFF |
| Quality Review Completed | 10/2/2019 | STEVEN KIM |
| Building Plans Picked Up | 10/4/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 10/4/2019 | APPLICANT |
| Green Plans Picked Up | 10/4/2019 | APPLICANT |
| Applicant returned to address corrections | 8/21/2020 | ERIC WONG |
| Applicant returned to address corrections | 10/22/2020 | ERIC WONG |
| Plan Check Approved | 10/27/2020 | ERIC WONG |
| Issued | 11/13/2020 | APPLICANT |
| CofO in Progress | 7/12/2022 | JEFFREY DURAN |
| Permit Finaled | 7/13/2022 | JEFFREY DURAN |
| CofO Issued | 7/13/2022 | JEFFREY DURAN |
| Permit Finaled | 7/13/2022 | JEFFREY DURAN |
Permit Application Clearance Information
| Address approval | Cleared | 2/11/2020 | APEKSHYA BAJRACHARYA |
| Highway dedication | Cleared | 2/11/2020 | APEKSHYA BAJRACHARYA |
| Permit | Cleared | 2/11/2020 | APEKSHYA BAJRACHARYA |
| Hydrant and Access approval | Cleared | 2/20/2020 | GEORGE SUCHAND |
| "Q" conditions | Cleared | 2/28/2020 | LARUEN PADICK |
| Automotive Use | Cleared | 2/28/2020 | LARUEN PADICK |
| Automotive Use | Cleared | 3/6/2020 | VINCENT QUITORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 3/6/2020 | JOHN TRIANTAFYLLOS |
| Prkng lot landscape/Water mgmt | Cleared | 3/6/2020 | VINCENT QUITORIANO |
| Green Code | Cleared | 4/28/2020 | DAVID MATSON |
| DAS Clearance | Cleared | 5/19/2020 | RUDOLF KINAR MELIKOFF |
| Low Impact Development | Cleared | 5/29/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 6/2/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/2/2020 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 6/2/2020 | LEE GUILBEAUX |
Contact Information
| Architect | Bond,, Dwight S; Lic. No.: C33276 | 1010 SYCAMORE AVENUE # 208 SOUTH PASADENA, CA 91030 |
| Contractor | T F I Group Inc; Lic. No.: 588076-B | 4667 COCINA LANE PALMDALE, CA 93551 |
| Engineer | Chatsky,, German; Lic. No.: C84153 | 6541 ODESSA AVE UNIT 11 LAKE BALBOA, CA 91406 |
Inspector Information
| GREGORY POMISH, (818) 374-3303 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDWIN GREGORYONA, (818) 374-3303 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/11/2021 | Approved | HAMID PISHEHVAR |
| Pre-Inspection | 2/5/2021 | Partial Approval | DANNY RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 2/16/2021 | Partial Approval | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 4/22/2021 | Corrections Issued | DANNY RODRIGUEZ |
| Deputy Reinf. Masonry | 6/2/2021 | Approved | HAMID PISHEHVAR |
| Deputy Reinf. Masonry | 6/7/2021 | Approved | HAMID PISHEHVAR |
| Deputy Reinf. Masonry | 6/9/2021 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Masonry | 6/16/2021 | Conditional Approval | JEFFREY DURAN |
| Reinforced Masonry Frame | 6/21/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Green Building Rough | 6/23/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 6/23/2021 | Partial Approval | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 6/23/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Green Building Rough | 8/16/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Verify Sprinkler Sign Off | 8/16/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Wood Frame | 8/16/2021 | Partial Approval | JONATHAN QUACH |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2021 | Partial Approval | DANNY RODRIGUEZ |
| Green Building Rough | 10/13/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 10/13/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Green Building Rough | 12/9/2021 | Approved | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 12/9/2021 | Partial Inspection | DANNY RODRIGUEZ |
| Wood Frame | 12/9/2021 | Partial Inspection | DANNY RODRIGUEZ |
| Insulation | 12/10/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Insulation | 12/14/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Insulation | 12/15/2021 | Approved | DANNY RODRIGUEZ |
| Drywall Nailing | 12/22/2021 | Conditional Approval | CAMERON CHABAN |
| Drywall Nailing | 7/12/2022 | Approved | JEFFREY DURAN |
| Final | 7/12/2022 | OK to Issue CofO | JEFFREY DURAN |
| Green Building Final | 7/12/2022 | Approved | JEFFREY DURAN |
| Reinforced Masonry Frame | 7/12/2022 | Approved | JEFFREY DURAN |
| SGSOV-Seismic Gas S/O Valve | 7/12/2022 | SGSOV Approved | JEFFREY DURAN |
| Smoke Detectors | 7/12/2022 | Approved | JEFFREY DURAN |
| Structural Steel Frame | 7/12/2022 | Approved | JEFFREY DURAN |
| Verify Sprinkler Sign Off | 7/12/2022 | Approved | JEFFREY DURAN |
| Wood Frame | 7/12/2022 | Approved | JEFFREY DURAN |