3957 S MARCASEL AVE 90066
Certificate Information: 3957 S MARCASEL AVE 90066
- Application / Permit
- 19010-20000-04065
- Plan Check / Job No.
- B19VN15563
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 89'0"X38'0" IRREGULAR SHAPED 2-STORY SFD WITH 20'0"X19'0" 2-CAR ATTACHED GARAGE. 11'0"X16'0" ROOF DECK AT FRONT & 4'0"X15'6" ROOF DECK AT REAR. 6'0"X7'0" FRONT PORCH & 11'6"X38'0" IRREGULAR SHAPED PATIO AT REAR. NFPA-13D FIRE SPRINKLERS REQ'D.
- Permit Issued
- Issued on 1/7/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/2/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/12/2019 | APPLICANT |
| Green Plans Picked Up | 9/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2019 | MARVEL DELACRUZ |
| Corrections Issued | 9/29/2019 | MARVEL DELACRUZ |
| Quality Review Completed | 9/30/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 10/1/2019 | APPLICANT |
| Applicant returned to address corrections | 12/10/2019 | MARVEL DELACRUZ |
| Plan Check Approved | 12/19/2019 | MARVEL DELACRUZ |
| Issued | 1/7/2020 | LADBS |
| CofO in Progress | 10/1/2021 | ENRIQUE MIRELES |
| Permit Finaled | 10/2/2021 | DANIEL ORRANTE |
| CofO Issued | 10/2/2021 | DANIEL ORRANTE |
| Permit Finaled | 10/2/2021 | DANIEL ORRANTE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 11/22/2019 | MITESH PATEL |
| Address approval | Cleared | 12/3/2019 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2019 | ADRIAN CASTRO |
| Permit | Cleared | 12/3/2019 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 12/3/2019 | ADRIAN CASTRO |
| Sewer availability | Cleared | 12/3/2019 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 12/4/2019 | GEORGE SUCHAND |
| Trees in Parkway | Cleared | 12/4/2019 | JOHN KIM |
| Green Code | Cleared | 12/5/2019 | AARON COSTA |
Contact Information
| Contractor | Stregan Group Ltd; Lic. No.: 962579-B | 5739 KANAN RD #255 AGOURA HILLS, CA 91301 |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
| Engineer | Miller,, Karen Lynn; Lic. No.: GE2257 | 6634 VALJEAN AVE VAN NUYS, CA 91406 |
| Engineer | Sayah,, Daniel Hoshyar; Lic. No.: C67905 | 15233 VENTURA BLVD STE 1130 SHERMAN OAKS, CA 91403 |
| Geologist | Ruberti,, Rudolph F; Lic. No.: EG1708 | 6634 VALJEAN AVE VAN NUYS, CA 91406 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/20/2020 | Partial Approval | DAVID FEILER |
| Underground Mechanical | 3/20/2020 | Partial Approval | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 4/2/2020 | Partial Approval | DAVID FEILER |
| Footing/Foundation/Slab | 4/2/2020 | Partial Approval | DAVID FEILER |
| Footing/Foundation/Slab | 5/5/2020 | Approved | JOHNNY MIRANDA |
| Wood Frame | 5/27/2020 | Partial Approval | CRAIG DAVIS |
| BUILDING-Rough-Frame | 7/15/2020 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Rough | 7/15/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Verify Sprinkler Sign Off | 7/15/2020 | Corrections Issued | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2020 | Approved | DAVID HEINE |
| PLUMBING-Rough | 8/14/2020 | Approved | DAVID HEINE |
| Rough-Elec/Plmb/HVAC | 10/2/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 10/6/2020 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 10/6/2020 | Partial Approval | ENRIQUE MIRELES |
| Drywall Nailing | 10/20/2020 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 10/20/2020 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 10/22/2020 | Corrections Issued | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 10/27/2020 | Approved | ENRIQUE MIRELES |
| Shower Pan | 10/29/2020 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 12/18/2020 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 12/22/2020 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 8/24/2021 | Approved | ENRIQUE MIRELES |
| Final | 8/24/2021 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 8/24/2021 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 8/24/2021 | SGSOV Approved | ENRIQUE MIRELES |
| Service/Power Release | 8/24/2021 | Approved | ENRIQUE MIRELES |
| Smoke Detectors | 8/24/2021 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 8/24/2021 | Approved | ENRIQUE MIRELES |
| Final | 9/14/2021 | Corrections Issued | ENRIQUE MIRELES |
| Final | 10/1/2021 | OK to Issue CofO | ENRIQUE MIRELES |