1885-1885 1/2 W 20TH ST 90007
Certificate Information: 1885-1885 1/2 W 20TH ST 90007
- Application / Permit
- 19010-20000-04062
- Plan Check / Job No.
- B19VN15555
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 19’-0" X 39’-0" 3-STORY DUPLEX PER ENGINEERING. [NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT]
- Permit Issued
- Issued on 3/2/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 9/12/2019 | APPLICANT |
Green Plans Picked Up | 9/25/2019 | APPLICANT |
Assigned to Plan Check Engineer | 9/26/2019 | JENNIFER LEE |
Corrections Issued | 10/4/2019 | JENNIFER LEE |
Quality Review Completed | 10/4/2019 | STEVEN KIM |
Building Plans Picked Up | 10/4/2019 | APPLICANT |
Plan Check Approved | 1/23/2020 | JENNIFER LEE |
Issued | 3/2/2020 | LADBS |
CofO in Progress | 5/12/2022 | STUART CHAPMAN |
CofO Issued | 6/1/2022 | DEROLD HAUFF |
Permit Finaled | 6/1/2022 | DEROLD HAUFF |
Permit Application Clearance Information
Address approval | Cleared | 10/29/2019 | THOMAS LANG |
Frnt yard landscape/Water mgmt | Cleared | 12/9/2019 | SARAHI ORTEGA |
ZI | Cleared | 12/9/2019 | SARAHI ORTEGA |
Green Code | Cleared | 12/10/2019 | DAVID MATSON |
Eng Process Fee Ord 176,300 | Cleared | 12/17/2019 | JEANIE LAM |
Hydrant and Access approval | Cleared | 12/17/2019 | GEORGE SUCHAND |
Low Impact Development | Cleared | 12/17/2019 | MARTIN FRAGOSO |
Permit | Cleared | 12/17/2019 | JEANIE LAM |
Roof/Waste drainage to street | Cleared | 12/17/2019 | JEANIE LAM |
Sewer availability | Cleared | 12/17/2019 | JEANIE LAM |
Trees in Parkway | Cleared | 12/19/2019 | ADRIAN SANCHEZ |
Mechanical Car Lift | Cleared | 1/21/2020 | JENNIFER LEE |
Contact Information
Contractor | J T K Construction Inc; Lic. No.: 1056422-B | 4055 WILSHIRE BLVD #260 LOS ANGELES, CA 90010 |
Inspector Information
WILLIAM KUEHN, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
ANTHONY RAMOS, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Excavation/Setback/Form/Re-Bar | 5/15/2020 | Approved | KATHRYN BUTTERWORTH |
Footing/Foundation/Slab | 5/15/2020 | Partial Approval | KATHRYN BUTTERWORTH |
PLUMBING-Rough | 5/15/2020 | Partial Approval | KATHRYN BUTTERWORTH |
Footing/Foundation/Slab | 5/26/2020 | Approved | KATHRYN BUTTERWORTH |
Floor/Roof Diaphrgm/Shear Wall | 6/4/2020 | Partial Approval | KATHRYN BUTTERWORTH |
Floor/Roof Diaphrgm/Shear Wall | 6/19/2020 | Partial Approval | KATHRYN BUTTERWORTH |
Floor/Roof Diaphrgm/Shear Wall | 7/2/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
Floor/Roof Diaphrgm/Shear Wall | 7/27/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
ELECTRICAL-Rough | 9/11/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
HVAC-Rough | 9/11/2020 | Partial Approval | KATHRYN BUTTERWORTH |
PLUMBING-Rough | 9/11/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
ELECTRICAL-Rough | 9/17/2020 | Approved | STUART CHAPMAN |
Gas Test | 9/17/2020 | Partial Approval | STUART CHAPMAN |
PLUMBING-Rough | 9/17/2020 | Approved | STUART CHAPMAN |
Sewer | 9/17/2020 | Not Ready for Inspection | STUART CHAPMAN |
Wood Frame | 10/13/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
BUILDING-Rough-Frame | 10/22/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
Interior/Exterior Lathing | 11/9/2020 | Partial Approval | KATHRYN BUTTERWORTH |
Insulation | 11/13/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
Insulation | 12/3/2020 | Approved | KATHRYN BUTTERWORTH |
BUILDING-Rough-Frame | 12/14/2020 | Approved | KATHRYN BUTTERWORTH |
Drywall Nailing | 12/14/2020 | Approved | KATHRYN BUTTERWORTH |
Green Building Rough | 12/14/2020 | Approved | KATHRYN BUTTERWORTH |
MERV13>=Rough | 12/14/2020 | Approved | KATHRYN BUTTERWORTH |
Verify Sprinkler Sign Off | 12/14/2020 | Approved | KATHRYN BUTTERWORTH |
Sewer | 3/31/2021 | Approved | KATHRYN BUTTERWORTH |
Underground Mechanical | 4/9/2021 | Partial Approval | KATHRYN BUTTERWORTH |
Underground Mechanical | 7/2/2021 | Not Ready for Inspection | DAVID FEILER |
ELECTRICAL-Final | 8/19/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
ELECTRICAL-Rough | 10/5/2021 | Partial Approval | KATHRYN BUTTERWORTH |
ELECTRICAL-Final | 12/20/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
Final | 12/20/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
Gas Test | 12/20/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
Green Building Final | 12/20/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
HVAC-Final | 12/20/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
MERV13>=Final | 12/20/2021 | Approved | KATHRYN BUTTERWORTH |
PLUMBING-Final | 12/20/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
SGSOV-Seismic Gas S/O Valve | 12/20/2021 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
Service/Power Release | 12/20/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
Smoke Detectors | 12/20/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
SGSOV-Seismic Gas S/O Valve | 12/30/2021 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
Gas Test | 1/10/2022 | Corrections Issued | SCOTT FINNILA |
PLUMBING-Final | 1/10/2022 | Corrections Issued | SCOTT FINNILA |
ELECTRICAL-Final | 1/14/2022 | Corrections Issued | SCOTT FINNILA |
Final | 1/14/2022 | Corrections Issued | SCOTT FINNILA |
Gas Test | 1/14/2022 | Corrections Issued | SCOTT FINNILA |
Green Building Final | 1/14/2022 | Corrections Issued | SCOTT FINNILA |
HVAC-Final | 1/14/2022 | Corrections Issued | SCOTT FINNILA |
PLUMBING-Final | 1/14/2022 | Corrections Issued | SCOTT FINNILA |
SGSOV-Seismic Gas S/O Valve | 1/14/2022 | SGSOV Not Ready | SCOTT FINNILA |
Service/Power Release | 1/14/2022 | Not Ready for Inspection | SCOTT FINNILA |
Smoke Detectors | 1/14/2022 | Approved | SCOTT FINNILA |
ELECTRICAL-Final | 1/21/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
Final | 1/21/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
Gas Test | 1/21/2022 | Approved | KATHRYN BUTTERWORTH |
HVAC-Final | 1/21/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
PLUMBING-Final | 1/21/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
SGSOV-Seismic Gas S/O Valve | 1/21/2022 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
Service/Power Release | 1/21/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
SGSOV-Seismic Gas S/O Valve | 1/31/2022 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
ELECTRICAL-Final | 2/7/2022 | Approved | KATHRYN BUTTERWORTH |
Final | 2/7/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
Gas Test | 2/7/2022 | Approved | KATHRYN BUTTERWORTH |
Green Building Final | 2/7/2022 | Approved | KATHRYN BUTTERWORTH |
HVAC-Final | 2/7/2022 | Approved | KATHRYN BUTTERWORTH |
PLUMBING-Final | 2/7/2022 | Approved | KATHRYN BUTTERWORTH |
SGSOV-Seismic Gas S/O Valve | 2/7/2022 | SGSOV Approved | KATHRYN BUTTERWORTH |
Service/Power Release | 2/7/2022 | Approved | KATHRYN BUTTERWORTH |
Final | 2/23/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
Final | 5/5/2022 | Partial Approval | STUART CHAPMAN |
Service/Power Release | 5/5/2022 | Not Ready for Inspection | STUART CHAPMAN |
Final | 5/12/2022 | OK to Issue CofO | STUART CHAPMAN |