6864 N TEESDALE AVE 91605

Certificate Information: 6864 N TEESDALE AVE 91605

Application / Permit
19010-20000-04050
Plan Check / Job No.
B19VN15467
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) IRREGULAR SHAPED 36' X 22' ACCESSORY DWELLING UNIT PER AB 494 & SB 292 ALL WORK PER WFPP
Permit Issued
Issued on 6/12/2020
Issuing Office
Valley
Current Status
CofO Issued on 9/21/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/11/2019 APPLICANT
Assigned to Plan Check Engineer 10/3/2019 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 10/9/2019 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 10/11/2019 OMID HEDAYAT
Building Plans Picked Up 10/15/2019 APPLICANT
Green Plans Picked Up 10/15/2019 APPLICANT
Applicant returned to address corrections 1/21/2020 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 1/24/2020 SEWADA ZADOORAN MILAGARDI
Issued 6/12/2020 LADBS
CofO in Progress 9/21/2021 ARAM AVEDISIAN
CofO Issued 9/21/2021 MICHAEL SMITH
Permit Finaled 9/21/2021 MICHAEL SMITH

Permit Application Clearance Information

Low Impact Development Cleared 1/10/2020 MARTIN FRAGOSO
Address approval Cleared 1/13/2020 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 1/13/2020 LEE GUILBEAUX
Green Code Cleared 1/13/2020 MICHAEL AYERS
Roof/Waste drainage to street Cleared 1/13/2020 LEE GUILBEAUX
Sewer availability Cleared 1/13/2020 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 1/13/2020 LEE GUILBEAUX
Construction near power lines Cleared 1/21/2020 WALTER RAMIREZ
Hydrant and Access approval Cleared 1/21/2020 GEORGE SUCHAND

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/1/2020 No Access for Inspection ARAM AVEDISIAN
Footing/Foundation/Slab 9/24/2020 Corrections Issued BRENDAN LOONEY
Footing/Foundation/Slab 10/1/2020 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 10/7/2020 Corrections Issued BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 10/8/2020 Approved KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 10/23/2020 Corrections Issued BRENDAN LOONEY
PLUMBING-Rough 10/23/2020 Partial Approval BRENDAN LOONEY
BUILDING-Rough-Frame 10/29/2020 Corrections Issued MICHAEL TEMPLE
Floor/Roof Diaphrgm/Shear Wall 10/29/2020 Partial Approval MICHAEL TEMPLE
Green Building Rough 10/29/2020 Not Ready for Inspection MICHAEL TEMPLE
Insulation 10/29/2020 Partial Approval MICHAEL TEMPLE
PLUMBING-Rough 12/14/2020 Corrections Issued MATTHEW NELSON
Wood Frame 12/14/2020 Corrections Issued MATTHEW NELSON
BUILDING-Rough-Frame 12/17/2020 Partial Approval BRENDAN LOONEY
Green Building Rough 12/17/2020 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Rough 12/17/2020 Not Ready for Inspection BRENDAN LOONEY
Verify Sprinkler Sign Off 12/17/2020 Not Ready for Inspection BRENDAN LOONEY
ELECTRICAL-Rough 12/23/2020 Not Ready for Inspection BRENDAN LOONEY
HVAC-Rough 12/23/2020 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Rough 12/23/2020 Not Ready for Inspection BRENDAN LOONEY
ELECTRICAL-Rough 1/11/2021 Partial Approval DANIEL DREW
PLUMBING-Rough 1/11/2021 Partial Approval DANIEL DREW
Insulation 1/13/2021 Corrections Issued BRENDAN LOONEY
Wood Frame 1/15/2021 Partial Approval BRENDAN LOONEY
Drywall Nailing 1/20/2021 Approved JOHN HAYES
Green Building Rough 1/20/2021 Approved JOHN HAYES
Interior/Exterior Lathing 1/20/2021 Approved JOHN HAYES
Shower Pan 1/20/2021 Approved JOHN HAYES
Sewer 2/18/2021 Approved BRENDAN LOONEY
Underground Mechanical 2/23/2021 Approved BRENDAN LOONEY
Gas Test 5/11/2021 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 6/18/2021 Approved RICHARD DOCKUS
Final 6/18/2021 Corrections Issued RICHARD DOCKUS
Footing/Foundation/Slab 6/18/2021 Approved RICHARD DOCKUS
Green Building Final 6/18/2021 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 6/18/2021 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 6/18/2021 Approved RICHARD DOCKUS
Verify Sprinkler Sign Off 6/18/2021 Approved RICHARD DOCKUS
Final 6/24/2021 Partial Inspection RICHARD DOCKUS
Final 7/27/2021 Corrections Issued CHRISTOPHE COCHRAN
Service/Power Release 7/27/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 9/21/2021 OK to Issue CofO ARAM AVEDISIAN
Service/Power Release 9/21/2021 Approved ARAM AVEDISIAN