6864 N TEESDALE AVE 91605
Certificate Information: 6864 N TEESDALE AVE 91605
- Application / Permit
- 19010-20000-04050
- Plan Check / Job No.
- B19VN15467
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) IRREGULAR SHAPED 36' X 22' ACCESSORY DWELLING UNIT PER AB 494 & SB 292 ALL WORK PER WFPP
- Permit Issued
- Issued on 6/12/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/21/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/11/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2019 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 10/9/2019 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 10/11/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 10/15/2019 | APPLICANT |
| Green Plans Picked Up | 10/15/2019 | APPLICANT |
| Applicant returned to address corrections | 1/21/2020 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 1/24/2020 | SEWADA ZADOORAN MILAGARDI |
| Issued | 6/12/2020 | LADBS |
| CofO in Progress | 9/21/2021 | ARAM AVEDISIAN |
| CofO Issued | 9/21/2021 | MICHAEL SMITH |
| Permit Finaled | 9/21/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Low Impact Development | Cleared | 1/10/2020 | MARTIN FRAGOSO |
| Address approval | Cleared | 1/13/2020 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 1/13/2020 | LEE GUILBEAUX |
| Green Code | Cleared | 1/13/2020 | MICHAEL AYERS |
| Roof/Waste drainage to street | Cleared | 1/13/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/13/2020 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 1/13/2020 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 1/21/2020 | WALTER RAMIREZ |
| Hydrant and Access approval | Cleared | 1/21/2020 | GEORGE SUCHAND |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/1/2020 | No Access for Inspection | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 9/24/2020 | Corrections Issued | BRENDAN LOONEY |
| Footing/Foundation/Slab | 10/1/2020 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 10/7/2020 | Corrections Issued | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 10/8/2020 | Approved | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2020 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Rough | 10/23/2020 | Partial Approval | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 10/29/2020 | Corrections Issued | MICHAEL TEMPLE |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2020 | Partial Approval | MICHAEL TEMPLE |
| Green Building Rough | 10/29/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| Insulation | 10/29/2020 | Partial Approval | MICHAEL TEMPLE |
| PLUMBING-Rough | 12/14/2020 | Corrections Issued | MATTHEW NELSON |
| Wood Frame | 12/14/2020 | Corrections Issued | MATTHEW NELSON |
| BUILDING-Rough-Frame | 12/17/2020 | Partial Approval | BRENDAN LOONEY |
| Green Building Rough | 12/17/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 12/17/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| Verify Sprinkler Sign Off | 12/17/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| ELECTRICAL-Rough | 12/23/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| HVAC-Rough | 12/23/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 12/23/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| ELECTRICAL-Rough | 1/11/2021 | Partial Approval | DANIEL DREW |
| PLUMBING-Rough | 1/11/2021 | Partial Approval | DANIEL DREW |
| Insulation | 1/13/2021 | Corrections Issued | BRENDAN LOONEY |
| Wood Frame | 1/15/2021 | Partial Approval | BRENDAN LOONEY |
| Drywall Nailing | 1/20/2021 | Approved | JOHN HAYES |
| Green Building Rough | 1/20/2021 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 1/20/2021 | Approved | JOHN HAYES |
| Shower Pan | 1/20/2021 | Approved | JOHN HAYES |
| Sewer | 2/18/2021 | Approved | BRENDAN LOONEY |
| Underground Mechanical | 2/23/2021 | Approved | BRENDAN LOONEY |
| Gas Test | 5/11/2021 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 6/18/2021 | Approved | RICHARD DOCKUS |
| Final | 6/18/2021 | Corrections Issued | RICHARD DOCKUS |
| Footing/Foundation/Slab | 6/18/2021 | Approved | RICHARD DOCKUS |
| Green Building Final | 6/18/2021 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 6/18/2021 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 6/18/2021 | Approved | RICHARD DOCKUS |
| Verify Sprinkler Sign Off | 6/18/2021 | Approved | RICHARD DOCKUS |
| Final | 6/24/2021 | Partial Inspection | RICHARD DOCKUS |
| Final | 7/27/2021 | Corrections Issued | CHRISTOPHE COCHRAN |
| Service/Power Release | 7/27/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 9/21/2021 | OK to Issue CofO | ARAM AVEDISIAN |
| Service/Power Release | 9/21/2021 | Approved | ARAM AVEDISIAN |