4827-4829 N RIVERTON AVE 91601

Certificate Information: 4827-4829 N RIVERTON AVE 91601

Application / Permit
19010-20000-04020
Plan Check / Job No.
B19VN15339
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
50'-2"X32' 3-STORY DUPLEX WITH 2-CAR PARKING GARAGE, STUDY, AND LAUNDRY AT 1ST STORY. NFPA 13 D FIRE SPRINKLERS REQUIRED THROUGHOUT -(FRONT)
Permit Issued
Issued on 12/14/2020
Issuing Office
Current Status
CofO Issued on 6/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/10/2019 APPLICANT
Green Plans Picked Up 9/17/2019 APPLICANT
Assigned to Plan Check Engineer 9/19/2019 ALYSSA N NARCISO
Corrections Issued 9/25/2019 ALYSSA N NARCISO
Quality Review Completed 9/25/2019 CHON CHIO KUO
Building Plans Picked Up 9/26/2019 APPLICANT
Plan Check Approved 1/16/2020 ALYSSA N NARCISO
Issued 12/14/2020 APPLICANT
CofO in Progress 5/31/2023 JACK KARGODORIAN
CofO Issued 6/5/2023 MICHAEL SMITH
Permit Finaled 6/5/2023 MICHAEL SMITH

Permit Application Clearance Information

Low Impact Development Cleared 11/7/2019 JORGE MEJIA LEMUS
Address approval Cleared 12/23/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 12/23/2019 LEE GUILBEAUX
Permit Cleared 12/23/2019 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 12/23/2019 LEE GUILBEAUX
Sewer availability Cleared 12/23/2019 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 12/23/2019 LEE GUILBEAUX
Frnt yard landscape/Water mgmt Cleared 12/26/2019 HERMINIGILDO AGUSTIN
Green Code Cleared 12/26/2019 AARON COSTA
Trees in Parkway Cleared 12/26/2019 JOHN KIM
Hydrant and Access approval Cleared 1/2/2020 GEORGE SUCHAND

Contact Information

Contractor Vg&V Construction Inc; Lic. No.: 1034103-B 534 N LOUISE STREET #_B      GLENDALE, CA 91206
Engineer Hajdari,, Gentjan; Lic. No.: C88031 157 S LOS ROBLES AVE 12      PASADENA, CA 91101

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 4/12/2021 Conditional Approval THOMAS FINNILA
Deputy Steel/Welding 4/19/2021 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/30/2021 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 5/18/2021 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/9/2021 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/15/2021 Corrections Issued THOMAS FINNILA
HVAC-Rough 10/15/2021 Conditional Approval THOMAS FINNILA
PLUMBING-Rough 10/15/2021 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/29/2021 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 11/30/2021 Corrections Issued THOMAS FINNILA
HVAC-Rough 11/30/2021 Approved THOMAS FINNILA
PLUMBING-Rough 11/30/2021 Approved THOMAS FINNILA
Interior/Exterior Lathing 12/1/2021 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 12/3/2021 Approved THOMAS FINNILA
Wood Frame 12/3/2021 Approved THOMAS FINNILA
Insulation 12/10/2021 Approved JACK KARGODORIAN
Interior/Exterior Lathing 12/10/2021 Partial Approval JACK KARGODORIAN
Drywall Nailing 12/23/2021 Approved JOHN HAYES
Green Building Rough 12/23/2021 Approved JOHN HAYES
Shower Pan 3/14/2022 Approved RYAN SALAZAR
Sewer 9/15/2022 Approved THOMAS FINNILA
ELECTRICAL-Final 11/30/2022 Partial Inspection DAVID MATSON
ELECTRICAL-Final 12/6/2022 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Final 12/22/2022 Corrections Issued JACK KARGODORIAN
Gas Test 1/25/2023 Approved DAVID MATSON
Sewer 1/25/2023 Approved DAVID MATSON
Underground Mechanical 1/25/2023 Partial Approval DAVID MATSON
ELECTRICAL-Final 2/3/2023 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Final 2/8/2023 Approved JACK KARGODORIAN
HVAC-Final 2/8/2023 Not Ready for Inspection JACK KARGODORIAN
PLUMBING-Final 2/8/2023 Approved JACK KARGODORIAN
HVAC-Rough 2/27/2023 Not Ready for Inspection JACK KARGODORIAN
HVAC-Final 3/2/2023 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 5/23/2023 Approved JACK KARGODORIAN
Final 5/23/2023 Corrections Issued JACK KARGODORIAN
Footing/Foundation/Slab 5/23/2023 Approved JACK KARGODORIAN
Green Building Final 5/23/2023 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 5/23/2023 SGSOV Approved JACK KARGODORIAN
Service/Power Release 5/23/2023 Approved JACK KARGODORIAN
Smoke Detectors 5/23/2023 Approved JACK KARGODORIAN
Verify Sprinkler Sign Off 5/23/2023 Approved JACK KARGODORIAN
Final 5/30/2023 OK to Issue CofO JACK KARGODORIAN