2150 S WEST VIEW ST 90016

Certificate Information: 2150 S WEST VIEW ST 90016

Application / Permit
19010-20000-03994
Plan Check / Job No.
B19VN15226
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 3-STORY SFD W/ ATTACHED GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 1/21/2020
Issuing Office
South Los Angeles
Current Status
CofO Issued on 9/23/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/9/2019 APPLICANT
Assigned to Plan Check Engineer 9/19/2019 NILOOFAR MEHRAIN
Corrections Issued 9/23/2019 NILOOFAR MEHRAIN
Quality Review Completed 9/24/2019 GUANG MIN TUNG
Building Plans Picked Up 10/3/2019 APPLICANT
Green Plans Picked Up 10/3/2019 APPLICANT
Applicant returned to address corrections 12/3/2019 NILOOFAR MEHRAIN
Plan Check Approved 12/5/2019 NILOOFAR MEHRAIN
Issued 1/21/2020 LADBS
CofO in Progress 9/1/2020 STUART CHAPMAN
Permit Finaled 9/23/2020 DEROLD HAUFF
CofO Issued 9/23/2020 DEROLD HAUFF
Permit Finaled 9/23/2020 DEROLD HAUFF

Permit Application Clearance Information

Hydrant and Access approval Cleared 11/12/2019 JOHN CONNEALLY
Low Impact Development Cleared 11/12/2019 MITESH PATEL
Address approval Cleared 11/14/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 11/14/2019 GUILLERMO PETRA
Green Code Cleared 11/14/2019 MICHAEL AYERS
Permit Cleared 11/14/2019 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 11/14/2019 GUILLERMO PETRA
Sewer availability Cleared 11/14/2019 GUILLERMO PETRA

Contact Information

Contractor Arrow Construction Co; Lic. No.: 573067-B 18729 CLARK DALE AVE #C      ARTESIA, CA 90701
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 26851 GRAYSLAKE ROAD      RANCHO PALOS VERDES, CA 90275

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/24/2020 Corrections Issued CHARLENE BUSTAMANTE
Sewer 1/24/2020 Approved CHARLENE BUSTAMANTE
Underground Mechanical 1/24/2020 Partial Approval CHARLENE BUSTAMANTE
PLUMBING-Rough 1/30/2020 Partial Approval ROBERT VORHIS
Deputy Other (see comments) 2/4/2020 Approved BRAD BESCOS
Deputy Reinf. Concrete 2/4/2020 Approved BRAD BESCOS
Footing/Foundation/Slab 2/4/2020 Corrections Issued BRAD BESCOS
Footing/Foundation/Slab 2/5/2020 Approved BRAD BESCOS
Deputy Reinf. Concrete 2/6/2020 Partial Approval RUBEN SALAS
BUILDING-Rough-Frame 4/21/2020 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 4/21/2020 Not Ready for Inspection STUART CHAPMAN
Gas Test 4/21/2020 Partial Approval STUART CHAPMAN
Green Building Rough 4/21/2020 Not Ready for Inspection STUART CHAPMAN
HVAC-Rough 4/21/2020 Not Ready for Inspection STUART CHAPMAN
MERV13>=Rough 4/21/2020 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 4/21/2020 Approved STUART CHAPMAN
Underground Mechanical 4/21/2020 Not Ready for Inspection STUART CHAPMAN
Verify Sprinkler Sign Off 4/21/2020 Not Ready for Inspection STUART CHAPMAN
Insulation 4/28/2020 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 5/1/2020 Approved STUART CHAPMAN
Insulation 5/1/2020 Approved STUART CHAPMAN
Interior/Exterior Lathing 5/4/2020 Approved THOMAS LOGRASSO
Drywall Nailing 5/8/2020 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 5/14/2020 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 8/14/2020 Approved STUART CHAPMAN
ELECTRICAL-Final 8/14/2020 Corrections Issued STUART CHAPMAN
Final 8/14/2020 Corrections Issued STUART CHAPMAN
Green Building Final 8/14/2020 Corrections Issued STUART CHAPMAN
Green Building Rough 8/14/2020 Approved STUART CHAPMAN
HVAC-Final 8/14/2020 Corrections Issued STUART CHAPMAN
MERV13>=Final 8/14/2020 Corrections Issued STUART CHAPMAN
MERV13>=Rough 8/14/2020 Approved STUART CHAPMAN
PLUMBING-Final 8/14/2020 Corrections Issued STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 8/14/2020 SGSOV Not Ready STUART CHAPMAN
Service/Power Release 8/14/2020 Not Ready for Inspection STUART CHAPMAN
Smoke Detectors 8/14/2020 Not Ready for Inspection STUART CHAPMAN
Underground Mechanical 8/14/2020 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 8/14/2020 Approved STUART CHAPMAN
ELECTRICAL-Final 8/21/2020 Approved STUART CHAPMAN
Final 8/21/2020 Conditional Approval STUART CHAPMAN
Green Building Final 8/21/2020 Approved STUART CHAPMAN
HVAC-Final 8/21/2020 Approved STUART CHAPMAN
MERV13>=Final 8/21/2020 Approved STUART CHAPMAN
PLUMBING-Final 8/21/2020 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 8/21/2020 SGSOV Approved STUART CHAPMAN
Service/Power Release 8/21/2020 Approved STUART CHAPMAN
Smoke Detectors 8/21/2020 Approved STUART CHAPMAN