16300 W ROSCOE BLVD 91406

Certificate Information: 16300 W ROSCOE BLVD 91406

Application / Permit
19010-20000-03969
Plan Check / Job No.
B19VN15108
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(7) Garage - Private
Work Description
NEW 2-STORY OPEN PARKING STRUCTURE WITH ROOF TOP PARKING
Permit Issued
Issued on 2/25/2020
Issuing Office
Valley
Current Status
CofO Issued on 4/7/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/6/2019 APPLICANT
Assigned to Plan Check Engineer 9/19/2019 CHON CHIO KUO
Disabled Access Plans Picked Up 9/19/2019 APPLICANT
Green Plans Picked Up 9/19/2019 APPLICANT
Corrections Issued 9/23/2019 CHON CHIO KUO
Quality Review Completed 9/24/2019 GUANG MIN TUNG
Building Plans Picked Up 9/26/2019 APPLICANT
Applicant returned to address corrections 10/4/2019 CHON CHIO KUO
Applicant returned to address corrections 11/6/2019 CHON CHIO KUO
Applicant returned to address corrections 11/19/2019 CHON CHIO KUO
Applicant returned to address corrections 12/17/2019 CHON CHIO KUO
Applicant returned to address corrections 2/6/2020 CHON CHIO KUO
Applicant returned to address corrections 2/11/2020 CHON CHIO KUO
Plan Check Approved 2/13/2020 CHON CHIO KUO
Issued 2/25/2020 LADBS
CofO in Progress 3/25/2021 JEFFREY DURAN
Permit Finaled 4/7/2021 RICKEY JACKSON
CofO Issued 4/7/2021 RICKEY JACKSON
Permit Finaled 4/7/2021 RICKEY JACKSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/22/2019 ADRIAN CASTRO
Green Code Cleared 10/22/2019 DAVID MATSON
Highway dedication Cleared 10/22/2019 ADRIAN CASTRO
Permit Cleared 10/22/2019 ADRIAN CASTRO
Sewer availability Cleared 10/22/2019 ADRIAN CASTRO
Hydrant and Access approval Cleared 10/29/2019 GEORGE SUCHAND
Prkng lot landscape/Water mgmt Cleared 10/29/2019 DAISY BENICIA
DAS Clearance Cleared 11/5/2019 CHON CHIO KUO
Low Impact Development Cleared 2/7/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 2/7/2020 THOMAS LANG
Miscellaneous Cleared 2/11/2020 CHON CHIO KUO

Contact Information

Architect Oganessian,, Armen J; Lic. No.: C13419 12601 CLASSICS DRIVE      GRANADA HILLS, CA 91344
Contractor Uncommon Builders Llc; Lic. No.: 1046026-B 9220 WINNETKA AVE      CHATSWORTH, CA 91311
Engineer Bondy,, Kenneth Dirk; Lic. No.: S3921 27575 FARGO RD      LAGUNA HILLS, CA 92653
Engineer Hill,, Edward Foster; Lic. No.: GE2126 27865 AMBERWOOD LANE      VALENCIA, CA 91354

Inspector Information

GREGORY POMISH, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI
EDWIN GREGORYONA, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/6/2020 Partial Inspection ROBERT COLE
Deputy Reinf. Concrete 5/18/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Concrete 5/20/2020 Conditional Approval ROBERT COLE
Footing/Foundation/Slab 5/20/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Concrete 5/21/2020 No Access for Inspection JOE VELASQUEZ
Piling/Pier/Caisson 5/21/2020 Approved JOE VELASQUEZ
Footing/Foundation/Slab 5/28/2020 Partial Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 6/4/2020 Not Ready for Inspection ROBERT COLE
Footing/Foundation/Slab 6/4/2020 Partial Approval ROBERT COLE
Deputy Reinf. Concrete 6/8/2020 Conditional Approval ROBERT COLE
Piling/Pier/Caisson 6/8/2020 Partial Approval ROBERT COLE
Footing/Foundation/Slab 6/9/2020 Partial Approval ROBERT COLE
Deputy Reinf. Concrete 6/10/2020 Conditional Approval ROBERT COLE
Green Building Rough 6/12/2020 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 6/12/2020 Partial Approval ROBERT COLE
Green Building Rough 6/22/2020 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 6/22/2020 Partial Approval ROBERT COLE
Reinforced Masonry Frame 6/22/2020 Not Ready for Inspection ROBERT COLE
Masonry Wall/Backfill 6/23/2020 Partial Approval ROBERT COLE
Footing/Foundation/Slab 7/6/2020 Not Ready for Inspection ROBERT COLE
Excavation/Setback/Form/Re-Bar 7/8/2020 Partial Approval ROBERT COLE
Footing/Foundation/Slab 7/8/2020 Partial Approval ROBERT COLE
Green Building Rough 7/8/2020 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Concrete 7/9/2020 Conditional Approval ROBERT COLE
Deputy Reinf. Concrete 7/21/2020 Partial Approval RONALD PACHECO
Footing/Foundation/Slab 7/21/2020 Partial Approval RONALD PACHECO
Deputy Reinf. Concrete 7/22/2020 Conditional Approval DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 7/23/2020 SGSOV Not Ready DANNY RODRIGUEZ
Special/Order Compliance 7/23/2020 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 7/27/2020 Approved HAMID PISHEHVAR
Footing/Foundation/Slab 7/27/2020 Partial Approval DANNY RODRIGUEZ
Deputy Pre-Stress Concrete 7/28/2020 Conditional Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 7/29/2020 Approved HAMID PISHEHVAR
Deputy Pre-Stress Concrete 7/30/2020 Conditional Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 7/31/2020 Approved DANNY RODRIGUEZ
Footing/Foundation/Slab 7/31/2020 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 8/1/2020 Partial Approval DANNY RODRIGUEZ
Deputy Pre-Stress Concrete 8/3/2020 Conditional Approval ANDREW DORSO
Green Building Rough 8/3/2020 Not Ready for Inspection ANDREW DORSO
Reinforced Concrete Frame 8/3/2020 Not Ready for Inspection ANDREW DORSO
Deputy Pre-Stress Concrete 8/4/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Concrete 8/4/2020 Approved HAMID PISHEHVAR
Deputy Pre-Stress Concrete 8/5/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Pre-Stress Concrete 8/6/2020 Approved DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 8/6/2020 Partial Approval DANNY RODRIGUEZ
Deputy Pre-Stress Concrete 8/7/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Pre-Stress Concrete 8/10/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Pre-Stress Concrete 8/11/2020 Approved HAMID PISHEHVAR
Deputy Pre-Stress Concrete 8/12/2020 Approved HAMID PISHEHVAR
Footing/Foundation/Slab 8/12/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Concrete 8/13/2020 Approved HAMID PISHEHVAR
Deputy Pre-Stress Concrete 8/17/2020 Approved HAMID PISHEHVAR
Green Building Rough 8/17/2020 Partial Approval HAMID PISHEHVAR
Reinforced Concrete Frame 8/17/2020 Partial Approval HAMID PISHEHVAR
Deputy Pre-Stress Concrete 8/27/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 8/27/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Pre-Stress Concrete 8/28/2020 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 8/28/2020 Approved DANNY RODRIGUEZ
Green Building Rough 8/28/2020 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 8/28/2020 Corrections Issued DANNY RODRIGUEZ
Deputy Pre-Stress Concrete 8/31/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Concrete 8/31/2020 Approved HAMID PISHEHVAR
Deputy Pre-Stress Concrete 9/1/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Concrete 9/1/2020 Approved HAMID PISHEHVAR
Deputy Pre-Stress Concrete 9/2/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Concrete 9/2/2020 Approved HAMID PISHEHVAR
Deputy Steel/Welding 9/2/2020 Approved HAMID PISHEHVAR
Green Building Rough 9/3/2020 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 9/3/2020 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 9/4/2020 Conditional Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 9/8/2020 Approved HAMID PISHEHVAR
Deputy Pre-Stress Concrete 9/9/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Pre-Stress Concrete 9/10/2020 Approved DANNY RODRIGUEZ
Green Building Rough 9/10/2020 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 9/10/2020 Partial Approval DANNY RODRIGUEZ
Deputy Pre-Stress Concrete 9/11/2020 Approved DANNY RODRIGUEZ
Deputy Pre-Stress Concrete 9/14/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Pre-Stress Concrete 9/15/2020 Conditional Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 9/16/2020 Approved HAMID PISHEHVAR
Reinforced Concrete Frame 9/17/2020 Partial Approval HAMID PISHEHVAR
Deputy Pre-Stress Concrete 9/18/2020 Conditional Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 9/21/2020 Conditional Approval SORIN CIRSTOIU
Green Building Rough 9/21/2020 Partial Inspection SORIN CIRSTOIU
Reinforced Masonry Frame 9/21/2020 Partial Inspection SORIN CIRSTOIU
Deputy Pre-Stress Concrete 9/22/2020 Conditional Approval DANNY RODRIGUEZ
Green Building Rough 9/30/2020 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 9/30/2020 Partial Approval DANNY RODRIGUEZ
Reinforced Masonry Frame 9/30/2020 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 10/13/2020 Approved HAMID PISHEHVAR
Deputy Reinf. Concrete 10/30/2020 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 11/5/2020 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 11/6/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/10/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 11/12/2020 Approved HAMID PISHEHVAR
Green Building Rough 11/12/2020 Not Ready for Inspection HAMID PISHEHVAR
Reinforced Masonry Frame 11/12/2020 Not Ready for Inspection HAMID PISHEHVAR
Deputy Steel/Welding 11/16/2020 Approved HAMID PISHEHVAR
Deputy Steel/Welding 11/17/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Drilled-In Anchors 11/23/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Drilled-In Anchors 11/25/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Drilled-In Anchors 11/30/2020 Conditional Approval DANNY RODRIGUEZ
Deputy Drilled-In Anchors 12/3/2020 Approved HAMID PISHEHVAR
Drywall Nailing 12/14/2020 Not Ready for Inspection DANNY RODRIGUEZ
Final 12/14/2020 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Final 12/14/2020 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 12/14/2020 Approved DANNY RODRIGUEZ
Reinforced Concrete Frame 12/14/2020 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 12/14/2020 Not Ready for Inspection DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 12/14/2020 SGSOV No Gas DANNY RODRIGUEZ
Smoke Detectors 12/14/2020 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 2/4/2021 Not Ready for Inspection DANNY RODRIGUEZ
Final 2/4/2021 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Final 2/4/2021 Approved DANNY RODRIGUEZ
Reinforced Concrete Frame 2/4/2021 Approved DANNY RODRIGUEZ
Reinforced Masonry Frame 2/4/2021 Approved DANNY RODRIGUEZ
Smoke Detectors 2/4/2021 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 2/26/2021 Approved HAMID PISHEHVAR
Final 2/26/2021 Partial Approval HAMID PISHEHVAR
Smoke Detectors 2/26/2021 Approved HAMID PISHEHVAR