7302 N CRANER AVE 91352
Certificate Information: 7302 N CRANER AVE 91352
- Application / Permit
- 19010-20000-03904
- Plan Check / Job No.
- B19VN14758
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT (30'-0"x40'-0") PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 5/26/2021
- Issuing Office
- Current Status
- CofO Issued on 10/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2019 | MOHAMMAD ESMAILI |
| Corrections Issued | 10/1/2019 | MOHAMMAD ESMAILI |
| Green Plans Picked Up | 10/2/2019 | APPLICANT |
| Quality Review Completed | 10/11/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 10/11/2019 | APPLICANT |
| Plan Check Approved | 5/19/2021 | MOHAMMAD ESMAILI |
| Issued | 5/26/2021 | APPLICANT |
| CofO in Progress | 8/23/2024 | ROBERTO PALACIOS-LOPEZ |
| CofO in Progress | 8/30/2024 | JUAN VALENZUELA |
| No Progress | 8/30/2024 | JUAN VALENZUELA |
| CofO in Progress | 9/22/2025 | ROBERTO PALACIOS-LOPEZ |
| CofO Issued | 10/28/2025 | RUBEN SALAS |
| Permit Finaled | 10/28/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/13/2020 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 3/16/2020 | RENZ SORIANO |
| Sewer availability | Cleared | 3/16/2020 | RENZ SORIANO |
| Green Code | Cleared | 3/17/2020 | MICHAEL AYERS |
| Low Impact Development | Cleared | 11/17/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 1/6/2021 | ABDULLAH SADOZAI |
| Hydrant and Access approval | Cleared | 1/25/2021 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/2/2021 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 8/6/2021 | Approved | DANIEL DREW |
| Gas Test | 9/8/2021 | Approved | DANIEL DREW |
| PLUMBING-Rough | 9/8/2021 | Partial Approval | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2021 | Partial Approval | DANIEL DREW |
| Insulation | 9/13/2021 | Partial Approval | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 12/16/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Verify Sprinkler Sign Off | 12/16/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 12/30/2021 | Corrections Issued | MICHEL ABAJAN |
| Green Building Rough | 12/30/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 12/30/2021 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2022 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 9/27/2022 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 10/21/2022 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 10/21/2022 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 10/21/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 10/21/2022 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 12/12/2022 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Rough | 12/12/2022 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 12/12/2022 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 12/19/2022 | Partial Approval | THOMAS FINNILA |
| HVAC-Rough | 1/4/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 2/13/2023 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 2/13/2023 | Approved | JOHN HAYES |
| Green Building Rough | 2/13/2023 | Approved | JOHN HAYES |
| HVAC-Rough | 2/13/2023 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 2/13/2023 | Corrections Issued | JOHN HAYES |
| PLUMBING-Rough | 2/13/2023 | Approved | JOHN HAYES |
| Insulation | 3/16/2023 | Approved | JOHN COLEMAN |
| Interior/Exterior Lathing | 3/23/2023 | Partial Inspection | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2023 | Corrections Issued | ROBERT GOLD |
| Interior/Exterior Lathing | 3/30/2023 | Corrections Issued | ROBERT GOLD |
| Rough-Elec/Plmb/HVAC | 3/30/2023 | Corrections Issued | ROBERT GOLD |
| Shower Pan | 5/8/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Shower Pan | 5/15/2023 | Corrections Issued | JOHN HAYES |
| Interior/Exterior Lathing | 5/23/2023 | Approved | JOHN HAYES |
| Shower Pan | 5/23/2023 | Approved | JOHN HAYES |
| Gas Test | 6/13/2023 | Corrections Issued | JOHN HAYES |
| Gas Test | 6/21/2023 | Partial Approval | JENNIFER RABUCHIN |
| Final | 12/29/2023 | Corrections Issued | CRAIG DAVIS |
| Green Building Final | 12/29/2023 | Corrections Issued | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 12/29/2023 | SGSOV Not Ready | CRAIG DAVIS |
| Service/Power Release | 12/29/2023 | Corrections Issued | CRAIG DAVIS |
| Smoke Detectors | 12/29/2023 | Approved | CRAIG DAVIS |
| Final | 3/1/2024 | Corrections Issued | JOHN HAYES |
| Green Building Final | 3/1/2024 | Partial Approval | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 3/1/2024 | SGSOV Not Ready | JOHN HAYES |
| Service/Power Release | 3/1/2024 | Not Ready for Inspection | JOHN HAYES |
| Final | 4/23/2024 | Corrections Issued | JOHN HAYES |
| Green Building Final | 4/23/2024 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 4/23/2024 | SGSOV Approved | JOHN HAYES |
| Service/Power Release | 4/23/2024 | Not Ready for Inspection | JOHN HAYES |
| Final | 6/17/2024 | Corrections Issued | JOSE AVILA |
| Final | 7/10/2024 | Corrections Issued | JOSE AVILA |
| Final | 8/6/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 8/6/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 8/6/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 8/22/2024 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 8/22/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 8/22/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 8/30/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 9/22/2025 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |