4931 N MATILIJA AVE 91423

Certificate Information: 4931 N MATILIJA AVE 91423

Application / Permit
19010-20000-03878
Plan Check / Job No.
B19VN14733
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 25'x23.5' 2-Story irregularly shape Single Family Dwelling with attached 2-car Garage over 56'x38.5' Basement & attached 15'-6" x 12'-6" patio cover with trellis covering.
Permit Issued
Issued on 2/13/2020
Issuing Office
Valley
Current Status
CofO Issued on 1/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/30/2019 APPLICANT
Assigned to Plan Check Engineer 9/26/2019 SERGIO MUNIZ
Corrections Issued 10/7/2019 SERGIO MUNIZ
Quality Review Completed 10/8/2019 OMID HEDAYAT
Building Plans Picked Up 10/10/2019 APPLICANT
Green Plans Picked Up 10/10/2019 APPLICANT
Plan Check Approved 2/10/2020 SERGIO MUNIZ
Issued 2/13/2020 LADBS
CofO in Progress 1/3/2022 JACK KARGODORIAN
Permit Finaled 1/22/2022 MICHAEL SMITH
CofO Issued 1/22/2022 MICHAEL SMITH
Permit Finaled 1/22/2022 MICHAEL SMITH

Permit Application Clearance Information

Green Code Cleared 12/11/2019 AARON COSTA
Hydrant and Access approval Cleared 12/11/2019 GEORGE SUCHAND
Permit Cleared 12/13/2019 EMIL KYUPELYAN
Trees in Parkway Cleared 12/13/2019 ADRIAN SANCHEZ
ZI Cleared 12/13/2019 JASON CHAN
Eng Process Fee Ord 176,300 Cleared 1/28/2020 JUAN ASHTON
Low Impact Development Cleared 1/28/2020 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 1/28/2020 JUAN ASHTON
Sewer availability Cleared 1/28/2020 EMIL KYUPELYAN

Contact Information

Architect Azadi,, Bijan; Lic. No.: C18972 2825 PLAZA DEL AMO # 179      TORRANCE, CA 90503
Contractor J H K Contractors Inc; Lic. No.: 835178-B 3216-A SANTA MONICA BLVD      SANTA MONICA, CA 90404
Engineer Minas,, Caro Jolfaie; Lic. No.: GE601 4742 SAN FERNANDO RD      GLENDALE, CA 91204

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/7/2020 Corrections Issued BRENDAN LOONEY
Footing/Foundation/Slab 4/13/2020 Approved BRENDAN LOONEY
PLUMBING-Rough 4/15/2020 Partial Inspection MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 4/24/2020 Partial Approval MISAEL ESPARZA
ELECTRICAL-Rough 5/13/2020 Partial Approval CHARLES POWELL
Excavation/Setback/Form/Re-Bar 5/13/2020 Partial Approval CHARLES POWELL
Deputy Drilled-In Anchors 5/22/2020 Partial Approval CHARLES POWELL
Footing/Foundation/Slab 8/19/2020 Partial Approval CHARLES POWELL
PLUMBING-Rough 8/19/2020 Partial Approval CHARLES POWELL
Footing/Foundation/Slab 8/28/2020 Approved BRENDAN LOONEY
Deputy Reinf. Concrete 9/2/2020 Partial Approval CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 10/1/2020 Partial Approval CHARLES POWELL
Deputy Wood Construction 11/10/2020 Partial Approval CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 11/17/2020 Corrections Issued CHARLES POWELL
Insulation 11/17/2020 Not Ready for Inspection CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 11/23/2020 Partial Approval THOMAS FINNILA
PLUMBING-Rough 12/7/2020 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 12/29/2020 Approved BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 12/31/2020 Approved CHARLES POWELL
Interior/Exterior Lathing 1/5/2021 Approved DANIEL DREW
ELECTRICAL-Rough 1/11/2021 Partial Approval CHARLES POWELL
HVAC-Rough 1/19/2021 Corrections Issued BEAU COLLINS
Shower Pan 1/19/2021 Not Ready for Inspection BEAU COLLINS
HVAC-Rough 1/26/2021 Approved MISAEL ESPARZA
Shower Pan 1/26/2021 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 2/2/2021 Approved CHARLES POWELL
Green Building Rough 2/2/2021 Approved CHARLES POWELL
Verify Sprinkler Sign Off 2/2/2021 Approved CHARLES POWELL
Insulation 2/9/2021 Approved CHARLES POWELL
Drywall Nailing 2/17/2021 Approved BRENDAN LOONEY
Interior/Exterior Lathing 2/17/2021 Partial Approval BRENDAN LOONEY
Interior/Exterior Lathing 2/23/2021 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 2/26/2021 Approved BRENDAN LOONEY
ELECTRICAL-Rough 4/6/2021 Partial Approval CHARLES POWELL
Enclosure/Fence 8/24/2021 Corrections Issued CHARLES POWELL
Service/Power Release 9/21/2021 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Final 10/20/2021 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 10/21/2021 Corrections Issued MISAEL ESPARZA
HVAC-Final 10/21/2021 Corrections Issued MISAEL ESPARZA
Service/Power Release 10/21/2021 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Final 10/26/2021 Approved MISAEL ESPARZA
HVAC-Final 10/26/2021 Approved MISAEL ESPARZA
PLUMBING-Final 10/26/2021 Approved MISAEL ESPARZA
Final 12/28/2021 Not Ready for Inspection RICHARD DOCKUS
Green Building Final 12/28/2021 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 12/28/2021 SGSOV Approved RICHARD DOCKUS
SUSMP-Std. Urban Storm Water 12/28/2021 Not Ready for Inspection RICHARD DOCKUS
Service/Power Release 12/28/2021 Corrections Issued RICHARD DOCKUS
Smoke Detectors 12/28/2021 Approved RICHARD DOCKUS
Final 12/30/2021 Conditional Approval JACK KARGODORIAN
Service/Power Release 12/30/2021 Approved JACK KARGODORIAN
Final 1/3/2022 OK to Issue CofO JACK KARGODORIAN
SUSMP-Std. Urban Storm Water 1/3/2022 Approved JACK KARGODORIAN