20407 W WINDSOR LANE 91326
Certificate Information: 20407 W WINDSOR LANE 91326
- Application / Permit
- 19010-20000-03868
- Plan Check / Job No.
- B19VN14669
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- TWO STORY SFD WITH ATTACHED 3 CAR GARAGE _STANDARD PLAN #648_PLAN_4AR _ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
- Permit Issued
- Issued on 8/25/2020
- Issuing Office
- Current Status
- CofO Issued on 10/14/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/30/2019 | APPLICANT |
| Green Plans Picked Up | 9/11/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/12/2019 | DAWN MC NULTY |
| Corrections Issued | 9/16/2019 | DAWN MC NULTY |
| Quality Review Completed | 9/18/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 10/1/2019 | APPLICANT |
| Plan Check Approved | 8/18/2020 | DAWN MC NULTY |
| Issued | 8/25/2020 | APPLICANT |
| CofO in Progress | 10/13/2021 | SEAN WIRCH |
| CofO Issued | 10/14/2021 | MICHAEL SMITH |
| Permit Finaled | 10/14/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Low Impact Development | Cleared | 11/14/2019 | AMMAR ELTAWIL |
| "T" removal | Cleared | 1/27/2020 | SARAH GOLDMAN |
| CPC | Cleared | 1/27/2020 | SARAH GOLDMAN |
| Miscellaneous | Cleared | 1/27/2020 | SARAH GOLDMAN |
| Miscellaneous | Cleared | 1/27/2020 | SARAH GOLDMAN |
| Miscellaneous | Cleared | 1/27/2020 | SARAH GOLDMAN |
| Miscellaneous | Cleared | 1/27/2020 | SARAH GOLDMAN |
| Specific Plan | Cleared | 1/27/2020 | SARAH GOLDMAN |
| Tract Map conditions | Cleared | 1/27/2020 | SARAH GOLDMAN |
| Tract Map conditions | Cleared | 1/27/2020 | SARAH GOLDMAN |
| ZA Case | Cleared | 1/27/2020 | SARAH GOLDMAN |
| ZA Case | Cleared | 1/27/2020 | SARAH GOLDMAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/19/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 2/27/2020 | GUILLERMO PETRA |
| Address approval | Cleared | 5/7/2020 | GUILLERMO PETRA |
| Permit | Cleared | 5/7/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 5/7/2020 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 6/30/2020 | KURT CORRAL |
| Green Code | Cleared | 7/9/2020 | MICHAEL AYERS |
Contact Information
| Contractor | Shapell Homes Inc; Lic. No.: 1001034-B | 250 GIBRALTAR RD ATTN: GATES/LEGAL HORSHAM, PA 19044 |
| Engineer | Miller, Karen Lynn; Lic. No.: GE2257 | 5364 DORIS WY TORRANCE, CA 90505 |
| Engineer | Wong, Ramon Roman Ii; Lic. No.: S2345 | 1800 E. 16TH STREET SANTA ANA, CA 92701 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/29/2020 | Not Ready for Inspection | SEAN WIRCH |
| Underground Mechanical | 1/7/2021 | Approved | SEAN WIRCH |
| Footing/Foundation/Slab | 1/15/2021 | Approved | SEAN WIRCH |
| Deputy Reinf. Concrete | 1/22/2021 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2021 | Partial Approval | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2021 | Partial Approval | SEAN WIRCH |
| Sewer | 3/23/2021 | Approved | SEAN WIRCH |
| ELECTRICAL-Rough | 6/4/2021 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2021 | Approved | SEAN WIRCH |
| HVAC-Rough | 6/4/2021 | Approved | SEAN WIRCH |
| PLUMBING-Rough | 6/4/2021 | Not Ready for Inspection | SEAN WIRCH |
| PLUMBING-Rough | 6/10/2021 | Approved | SEAN WIRCH |
| BUILDING-Rough-Frame | 6/28/2021 | Approved | SEAN WIRCH |
| Green Building Rough | 6/28/2021 | Approved | SEAN WIRCH |
| Verify Sprinkler Sign Off | 6/28/2021 | Approved | SEAN WIRCH |
| Drywall Nailing | 7/6/2021 | Approved | SEAN WIRCH |
| Interior/Exterior Lathing | 7/6/2021 | Partial Approval | SEAN WIRCH |
| Interior/Exterior Lathing | 7/26/2021 | Corrections Issued | SEAN WIRCH |
| Gas Test | 7/28/2021 | Partial Approval | HENRY KIM |
| Interior/Exterior Lathing | 8/2/2021 | Partial Approval | JOSEPH SAGEN |
| Service/Power Release | 8/19/2021 | Approved | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 8/26/2021 | SGSOV Not Ready | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 8/31/2021 | SGSOV Approved | SEAN WIRCH |
| Underground Mechanical | 9/14/2021 | Approved | SEAN WIRCH |
| ELECTRICAL-Final | 10/1/2021 | Approved | SEAN WIRCH |
| HVAC-Final | 10/1/2021 | Approved | SEAN WIRCH |
| Final | 10/12/2021 | OK to Issue CofO | SEAN WIRCH |
| Green Building Final | 10/12/2021 | Approved | SEAN WIRCH |
| PLUMBING-Final | 10/12/2021 | Approved | SEAN WIRCH |
| Smoke Detectors | 10/12/2021 | Approved | SEAN WIRCH |