1024 N ORLANDO AVE 90069
Certificate Information: 1024 N ORLANDO AVE 90069
- Application / Permit
- 19010-20000-03858
- Plan Check / Job No.
- B19VN14667
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 80'x52' 2-STORY IRREGULAR SHAPE SINGLE FAMILY DWELLING w/ ATTACHED GARAGE. AUTOMATIC SPRINKLER SYSTEM IS REQUIRED.
- Permit Issued
- Issued on 1/16/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/6/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2019 | SEAN SHAHMIRI |
| Green Plans Picked Up | 10/4/2019 | APPLICANT |
| Corrections Issued | 10/7/2019 | SEAN SHAHMIRI |
| Quality Review Completed | 10/10/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 10/11/2019 | APPLICANT |
| Applicant returned to address corrections | 1/13/2020 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 1/16/2020 | SEAN SHAHMIRI |
| Plan Check Approved | 1/16/2020 | SEAN SHAHMIRI |
| Issued | 1/16/2020 | LADBS |
| CofO in Progress | 3/1/2021 | CHRIS CHRISTENSEN |
| Permit Finaled | 3/6/2021 | DEROLD HAUFF |
| CofO Issued | 3/6/2021 | DEROLD HAUFF |
| Permit Finaled | 3/6/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 11/21/2019 | ANDRES COVARRUBIAS |
| Trees in Parkway | Cleared | 12/16/2019 | ADRIAN SANCHEZ |
| Address approval | Cleared | 12/24/2019 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 12/24/2019 | GUILLERMO PETRA |
| Green Code | Cleared | 12/24/2019 | MICHAEL AYERS |
| Permit | Cleared | 12/24/2019 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 12/24/2019 | GUILLERMO PETRA |
| Sewer availability | Cleared | 12/24/2019 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 1/6/2020 | GEORGE SUCHAND |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/31/2020 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 2/4/2020 | Partial Approval | ARTHUR SARGSYAN |
| Deputy Steel/Welding | 2/10/2020 | Approved | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 2/10/2020 | Partial Approval | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 2/14/2020 | Partial Approval | ARTHUR SARGSYAN |
| Deputy Steel/Welding | 2/15/2020 | Approved | ARTHUR SARGSYAN |
| Deputy Wood Construction | 3/5/2020 | Approved | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2020 | Partial Approval | ARTHUR SARGSYAN |
| Deputy Wood Construction | 3/27/2020 | No Access for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2020 | Partial Approval | SCOTT FINNILA |
| Deputy Steel/Welding | 3/31/2020 | Partial Approval | SCOTT FINNILA |
| Wood Frame | 4/7/2020 | Partial Inspection | RAUL BARAJAS |
| Wood Frame | 4/14/2020 | Partial Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 4/16/2020 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 5/11/2020 | Partial Approval | CHRIS CHRISTENSEN |
| HVAC-Rough | 5/11/2020 | Approved | CHRIS CHRISTENSEN |
| Shower Pan | 5/11/2020 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 5/19/2020 | Approved | CHRIS CHRISTENSEN |
| Deputy Wood Construction | 5/20/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 5/21/2020 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Rough | 5/21/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 5/21/2020 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 6/8/2020 | Partial Approval | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 6/9/2020 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 6/9/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| HVAC-Rough | 6/9/2020 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 6/9/2020 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 6/19/2020 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 6/19/2020 | Approved | THOMAS LOGRASSO |
| Insulation | 6/23/2020 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 12/28/2020 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 12/28/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| PLUMBING-Final | 12/28/2020 | Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 12/28/2020 | Approved | CHRIS CHRISTENSEN |
| Final | 1/28/2021 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 1/28/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Final | 1/28/2021 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 1/28/2021 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 1/28/2021 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 1/28/2021 | Approved | CHRIS CHRISTENSEN |
| Structural Steel Frame | 1/28/2021 | Approved | CHRIS CHRISTENSEN |