1741 W 81ST ST 90047
Certificate Information: 1741 W 81ST ST 90047
- Application / Permit
- 19010-20000-03780
- Plan Check / Job No.
- B19VN14243
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 24'2" X 14'6" TWO STORY ACCESSORY DWELLING UNIT WITH 3'8" X 6' ATTACHED PORCH PER AB 494 AND SB 229 , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 1/17/2020
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 10/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2019 | RARES BODEA |
| Corrections Issued | 9/26/2019 | RARES BODEA |
| Quality Review Completed | 9/26/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 10/1/2019 | APPLICANT |
| Green Plans Picked Up | 10/1/2019 | APPLICANT |
| Plan Check Approved | 12/2/2019 | RARES BODEA |
| Issued | 1/17/2020 | LADBS |
| CofO in Progress | 9/29/2022 | ENRIQUE MIRELES |
| CofO Issued | 10/12/2022 | DEROLD HAUFF |
| Permit Finaled | 10/12/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/15/2019 | JULIUS GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 10/15/2019 | JULIUS GARCIA |
| Sewer availability | Cleared | 10/15/2019 | JULIUS GARCIA |
| Green Code | Cleared | 10/23/2019 | MICHAEL AYERS |
| Roof/Waste drainage to street | Cleared | 11/21/2019 | ADRIAN CASTRO |
| Construction near power lines | Cleared | 12/2/2019 | OSCAR CASTRO |
| Construction within easement | Cleared | 12/2/2019 | OSCAR CASTRO |
Contact Information
| Architect | Salcedo,, Glen Charles; Lic. No.: C33143 | P O BOX 14202 VAN NUYS, CA 91409 |
| Contractor | Diversfied Construction & Engineering Group Inc; Lic. No.: 768516-B | 621 WEST COVINA BOULEVARD SAN DIMAS, CA 91773 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/31/2020 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Rough | 3/31/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 1/6/2021 | Partial Approval | ROBERT VORHIS |
| Underground Mechanical | 1/6/2021 | Corrections Issued | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 1/7/2021 | Conditional Approval | FREDDIE RIVERA |
| Underground Mechanical | 1/7/2021 | Approved | FREDDIE RIVERA |
| Deputy Drilled-In Anchors | 2/3/2021 | No Access for Inspection | ELMER BLAND |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2021 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 4/8/2021 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 4/8/2021 | Approved | FREDDIE RIVERA |
| Green Building Rough | 4/8/2021 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 4/8/2021 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 4/8/2021 | Approved | FREDDIE RIVERA |
| Pre-Inspection | 4/8/2021 | Corrections Issued | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 4/8/2021 | Approved | FREDDIE RIVERA |
| Insulation | 4/28/2021 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 4/28/2021 | Not Ready for Inspection | SABAS ALONSO |
| Insulation | 5/7/2021 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 5/7/2021 | Partial Approval | FREDDIE RIVERA |
| Pre-Inspection | 5/7/2021 | Corrections Issued | FREDDIE RIVERA |
| Drywall Nailing | 5/26/2021 | No Access for Inspection | FREDDIE RIVERA |
| Drywall Nailing | 6/2/2021 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 7/15/2021 | Approved | JESUS RODRIGUEZ |
| Gas Test | 9/1/2021 | Approved | FREDDIE RIVERA |
| Sewer | 9/1/2021 | Approved | FREDDIE RIVERA |
| Underground Mechanical | 9/1/2021 | Partial Inspection | FREDDIE RIVERA |
| Final | 10/6/2021 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 10/6/2021 | Approved | FREDDIE RIVERA |
| Green Building Final | 10/6/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 10/6/2021 | SGSOV Not Ready | FREDDIE RIVERA |
| Service/Power Release | 10/6/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Smoke Detectors | 10/6/2021 | Approved | FREDDIE RIVERA |
| Final | 11/9/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Green Building Final | 11/9/2021 | No Access for Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 11/9/2021 | SGSOV Not Ready | FREDDIE RIVERA |
| Service/Power Release | 11/9/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Final | 1/13/2022 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 1/13/2022 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 1/13/2022 | SGSOV Not Ready | FREDDIE RIVERA |
| Service/Power Release | 1/13/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| Final | 3/7/2022 | Conditional Approval | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 3/7/2022 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 3/7/2022 | Approved | FREDDIE RIVERA |
| Final | 9/7/2022 | OK to Issue CofO | ENRIQUE MIRELES |