9802 N FARRALONE AVE 91311
Certificate Information: 9802 N FARRALONE AVE 91311
- Application / Permit
- 19010-20000-03776
- Plan Check / Job No.
- B19VN14232
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- NEW (33'-0"x 62'-6") DETACHED 2ND FLOOR ACCESSORY LIVING QUARTERS ABOVE 5-CAR GARAGE , FULLY SPRINKLERED NFPA 13D THROUGHOUT. (TYPE VA CONSTRUCTION).
- Permit Issued
- Issued on 2/21/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/12/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2019 | TROY DEGUZMAN |
| Corrections Issued | 9/9/2019 | TROY DEGUZMAN |
| Quality Review Completed | 9/9/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 9/13/2019 | APPLICANT |
| Green Plans Picked Up | 9/13/2019 | APPLICANT |
| Plan Check Approved | 2/7/2020 | TROY DEGUZMAN |
| Issued | 2/21/2020 | LADBS |
| CofO in Progress | 2/5/2021 | DAVID STEPANYAN |
| Permit Finaled | 2/12/2021 | JOHN JANSON |
| CofO Issued | 2/12/2021 | JOHN JANSON |
| Permit Finaled | 2/12/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 10/21/2019 | APEKSHYA BAJRACHARYA |
| ZI | Cleared | 12/11/2019 | JOSE ROMERO-NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/27/2019 | CELINA MORENO |
| Low Impact Development | Cleared | 12/27/2019 | JORGE MEJIA LEMUS |
| Sewer availability | Cleared | 12/27/2019 | CELINA MORENO |
| Green Code | Cleared | 1/21/2020 | DAVID MATSON |
| Hydrant and Access approval | Cleared | 2/3/2020 | GEORGE SUCHAND |
| Flood clearance | Cleared | 2/5/2020 | RAYMOND LAM |
| Flood clearance | Cleared | 2/5/2020 | RAYMOND LAM |
| Roof/Waste drainage to street | Cleared | 2/5/2020 | ADRIAN CASTRO |
| GPI Written Notices | Cleared | 2/21/2020 | TROY DEGUZMAN |
| Grading Pre-Inspection | Cleared | 2/21/2020 | TROY DEGUZMAN |
Contact Information
| Architect | Blaugrund,, Charles I; Lic. No.: C25792 | 14994 MARQUETTE STREET MOORPARK, CA 93021 |
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| FLOOD-Elevation Certificate | 3/25/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Pre-Inspection | 3/25/2020 | Partial Approval | DAVID STEPANYAN |
| FLOOD-Elevation Certificate | 4/1/2020 | Partial Approval | DAVID STEPANYAN |
| Footing/Foundation/Slab | 4/1/2020 | Partial Approval | DAVID STEPANYAN |
| PLUMBING-Rough | 4/1/2020 | Partial Approval | DAVID STEPANYAN |
| FLOOD-Elevation Certificate | 4/7/2020 | Partial Approval | DAVID STEPANYAN |
| Footing/Foundation/Slab | 4/7/2020 | Partial Approval | DAVID STEPANYAN |
| Drywall Nailing | 4/21/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2020 | Partial Approval | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2020 | Partial Approval | DAVID STEPANYAN |
| ELECTRICAL-Rough | 5/11/2020 | Partial Approval | DAVID STEPANYAN |
| HVAC-Rough | 5/13/2020 | Approved | DAVID STEPANYAN |
| PLUMBING-Rough | 5/13/2020 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 5/21/2020 | Partial Approval | DAVID STEPANYAN |
| ELECTRICAL-Rough | 5/21/2020 | Approved | DAVID STEPANYAN |
| FLOOD-Proofing Certificate | 5/21/2020 | Partial Approval | DAVID STEPANYAN |
| Footing/Foundation/Slab | 5/21/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Gas Test | 5/21/2020 | Partial Approval | DAVID STEPANYAN |
| Green Building Rough | 5/21/2020 | Approved | DAVID STEPANYAN |
| Verify Sprinkler Sign Off | 5/21/2020 | Approved | DAVID STEPANYAN |
| Insulation | 5/27/2020 | Approved | DAVID STEPANYAN |
| Sewer | 5/27/2020 | Partial Approval | DAVID STEPANYAN |
| Shower Pan | 5/27/2020 | Approved | DAVID STEPANYAN |
| Gas Test | 6/3/2020 | Approved | DAVID STEPANYAN |
| Sewer | 6/3/2020 | Approved | DAVID STEPANYAN |
| Underground Mechanical | 6/3/2020 | Approved | DAVID STEPANYAN |
| Drywall Nailing | 6/4/2020 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 6/4/2020 | Partial Approval | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 6/5/2020 | Partial Approval | DAVID STEPANYAN |
| Interior/Exterior Lathing | 6/10/2020 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 6/12/2020 | Partial Approval | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 7/30/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| FLOOD-Elevation Certificate | 7/30/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| FLOOD-Proofing Certificate | 7/30/2020 | Corrections Issued | DAVID STEPANYAN |
| Final | 7/30/2020 | Corrections Issued | DAVID STEPANYAN |
| Green Building Final | 7/30/2020 | Approved | DAVID STEPANYAN |
| PLUMBING-Final | 7/30/2020 | Approved | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 7/30/2020 | SGSOV Approved | DAVID STEPANYAN |
| Service/Power Release | 7/30/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Smoke Detectors | 7/30/2020 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 1/26/2021 | Approved | DAVID STEPANYAN |
| FLOOD-Elevation Certificate | 1/26/2021 | Approved | DAVID STEPANYAN |
| FLOOD-Proofing Certificate | 1/26/2021 | Approved | DAVID STEPANYAN |
| Final | 1/26/2021 | Corrections Issued | DAVID STEPANYAN |
| Footing/Foundation/Slab | 1/26/2021 | Approved | DAVID STEPANYAN |
| Service/Power Release | 1/26/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Final | 2/4/2021 | OK to Issue CofO | DAVID STEPANYAN |