1685 N REDESDALE AVE 90026

Certificate Information: 1685 N REDESDALE AVE 90026

Application / Permit
19010-20000-03772
Plan Check / Job No.
B19VN14217
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 47'2" X 28'4" 3-STORY SFD WITH 35' X 26'8" BASEMENT AND 22'10" X 18' ATTACHED 2-CAR GARAGE, NFPA-13D FIRE SPRINKLERS REQUIRED , ALL WORK PER ENGINEERING
Permit Issued
Issued on 1/24/2020
Issuing Office
Valley
Current Status
CofO Issued on 11/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/23/2019 APPLICANT
Assigned to Plan Check Engineer 9/5/2019 RARES BODEA
Corrections Issued 9/7/2019 RARES BODEA
Quality Review Completed 9/12/2019 GUANG MIN TUNG
Building Plans Picked Up 9/12/2019 APPLICANT
Green Plans Picked Up 9/12/2019 APPLICANT
Applicant returned to address corrections 11/13/2019 RARES BODEA
Applicant returned to address corrections 1/6/2020 RARES BODEA
Plan Check Approved 1/24/2020 RARES BODEA
Issued 1/24/2020 LADBS
CofO in Progress 11/17/2021 THOMAS LOGRASSO
Permit Finaled 11/19/2021 DEROLD HAUFF
CofO Issued 11/19/2021 DEROLD HAUFF
Permit Finaled 11/19/2021 DEROLD HAUFF

Permit Application Clearance Information

GPI Written Notices Cleared 11/13/2019 RARES BODEA
Grading Pre-Inspection Cleared 11/13/2019 RARES BODEA
Address approval Cleared 12/13/2019 EMIL KYUPELYAN
Distance to fire station Cleared 12/13/2019 JEREMY CARTER
Eng Process Fee Ord 176,300 Cleared 12/13/2019 EMIL KYUPELYAN
Hydrant and Access approval Cleared 12/13/2019 JEREMY CARTER
Permit Cleared 12/13/2019 EMIL KYUPELYAN
Sewer availability Cleared 12/13/2019 EMIL KYUPELYAN
Low Impact Development Cleared 12/18/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 12/18/2019 ERIK BEASLEY
Green Code Cleared 1/3/2020 DAVID MATSON
Trees in Parkway Cleared 1/6/2020 JOHN KIM
Work Adjacent to Public Way Cleared 1/13/2020 HOK CHI CHIU

Contact Information

Contractor Owner-Builder       ,
Engineer Robinson,, Rory Anthony; Lic. No.: C51134 4000-A SAN FERNANDO RD      GLENDALE, CA 91204
Engineer Robinson,, Rory Anthony; Lic. No.: GE2491 4000-A SAN FERNANDO RD      GLENDALE, CA 91204
Engineer Tuchscher,, James Todd; Lic. No.: C77649 5503 E 2ND ST      LONG BEACH, CA 90803
Geologist Robinson,, Rory Anthony; Lic. No.: EG1902 4000-A SAN FERNANDO RD      GLENDALE, CA 91204
Geologist Robinson,, Rory Anthony; Lic. No.: GEO5912 4000-A SAN FERNANDO RD      GLENDALE, CA 91204

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 5/21/2020 Corrections Issued KATHRYN BUTTERWORTH
Piling/Pier/Caisson 5/26/2020 Partial Approval KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 5/28/2020 Partial Approval KATHRYN BUTTERWORTH
Footing/Foundation/Slab 5/28/2020 Partial Approval KATHRYN BUTTERWORTH
Piling/Pier/Caisson 5/28/2020 Approved KATHRYN BUTTERWORTH
Footing/Foundation/Slab 6/10/2020 Corrections Issued RUBEN SALAS
Piling/Pier/Caisson 6/15/2020 Partial Approval RUBEN SALAS
Piling/Pier/Caisson 7/23/2020 Partial Approval ENRIQUE MIRELES
Piling/Pier/Caisson 7/24/2020 Partial Approval DAVID CHAN
Footing/Foundation/Slab 8/19/2020 Partial Approval HAMIK HARTOUNIAN
Piling/Pier/Caisson 8/19/2020 Partial Approval HAMIK HARTOUNIAN
Piling/Pier/Caisson 8/24/2020 Partial Approval STUART CHAPMAN
Footing/Foundation/Slab 8/27/2020 Partial Approval KATHRYN BUTTERWORTH
Underground Mechanical 9/3/2020 Approved ARTHUR SARGSYAN
Footing/Foundation/Slab 9/15/2020 Conditional Approval HAMIK HARTOUNIAN
Piling/Pier/Caisson 9/30/2020 Partial Approval DONALD CRICHLOW
Underground Mechanical 9/30/2020 Partial Approval DONALD CRICHLOW
Footing/Foundation/Slab 10/1/2020 Approved ARTHUR SARGSYAN
Deputy Reinf. Concrete 10/2/2020 No Access for Inspection ELMER BLAND
Piling/Pier/Caisson 10/8/2020 Partial Approval STUART CHAPMAN
Deputy Drilled-In Anchors 10/14/2020 No Access for Inspection ELMER BLAND
Footing/Foundation/Slab 10/15/2020 Order to Comply Issued DAVID CHAN
Deputy Drilled-In Anchors 10/16/2020 No Access for Inspection ELMER BLAND
Wood Frame 12/8/2020 Partial Approval STUART CHAPMAN
Wood Frame 12/17/2020 Partial Approval KATHRYN BUTTERWORTH
HVAC-Rough 2/18/2021 Not Ready for Inspection ROBERT VORHIS
Insulation 2/18/2021 Partial Approval ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 2/22/2021 Partial Approval HAMIK HARTOUNIAN
PLUMBING-Rough 2/22/2021 Conditional Approval HAMIK HARTOUNIAN
HVAC-Rough 2/26/2021 Corrections Issued HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 3/1/2021 Approved ROBERT VORHIS
HVAC-Rough 3/2/2021 Approved STUART CHAPMAN
ELECTRICAL-Rough 3/3/2021 Approved ROBERT VORHIS
BUILDING-Rough-Frame 3/10/2021 Corrections Issued SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/10/2021 Partial Approval SCOTT FINNILA
Green Building Rough 3/10/2021 Corrections Issued SCOTT FINNILA
PLUMBING-Rough 3/10/2021 Approved SCOTT FINNILA
Verify Sprinkler Sign Off 3/10/2021 Approved SCOTT FINNILA
Interior/Exterior Lathing 3/16/2021 Partial Approval HAMIK HARTOUNIAN
Wood Frame 3/16/2021 Approved HAMIK HARTOUNIAN
Insulation 3/22/2021 Approved RUBEN SALAS
BUILDING-Rough-Frame 4/12/2021 Approved ROBERT VORHIS
Drywall Nailing 4/12/2021 Approved ROBERT VORHIS
Green Building Rough 4/12/2021 Approved ROBERT VORHIS
Sewer 4/29/2021 Approved ROBERT VORHIS
Interior/Exterior Lathing 5/19/2021 Approved CHRISTOPHER DELLEFIELD
Shower Pan 5/19/2021 Partial Approval CHRISTOPHER DELLEFIELD
Gas Test 7/13/2021 Approved SCOTT FINNILA
HVAC-Final 7/21/2021 Corrections Issued SCOTT FINNILA
PLUMBING-Final 7/21/2021 Approved SCOTT FINNILA
ELECTRICAL-Final 11/10/2021 Corrections Issued THOMAS LOGRASSO
Final 11/10/2021 Corrections Issued THOMAS LOGRASSO
Footing/Foundation/Slab 11/10/2021 Approved THOMAS LOGRASSO
Green Building Final 11/10/2021 Not Ready for Inspection THOMAS LOGRASSO
HVAC-Final 11/10/2021 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 11/10/2021 SGSOV Approved THOMAS LOGRASSO
Service/Power Release 11/10/2021 Not Ready for Inspection THOMAS LOGRASSO
Smoke Detectors 11/10/2021 Approved THOMAS LOGRASSO
ELECTRICAL-Final 11/16/2021 Approved THOMAS LOGRASSO
Final 11/16/2021 OK to Issue CofO THOMAS LOGRASSO
Green Building Final 11/16/2021 Approved THOMAS LOGRASSO
Service/Power Release 11/16/2021 Approved THOMAS LOGRASSO