17513 W TULSA ST 91344
Certificate Information: 17513 W TULSA ST 91344
- Application / Permit
- 19010-20000-03766
- Plan Check / Job No.
- B19VN14201
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 34' X 40' TYPE VA ONE STORY ACCESSORY DWELLING UNIT ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 9/22/2020
- Issuing Office
- Current Status
- CofO Issued on 11/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2019 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 9/27/2019 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 9/27/2019 | OMID HEDAYAT |
| Green Plans Picked Up | 10/7/2019 | APPLICANT |
| Building Plans Picked Up | 10/8/2019 | APPLICANT |
| Applicant returned to address corrections | 11/14/2019 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 11/15/2019 | SEWADA ZADOORAN MILAGARDI |
| No Progress | 11/18/2019 | SEWADA ZADOORAN MILAGARDI |
| Plan Check Approved | 11/18/2019 | SEWADA ZADOORAN MILAGARDI |
| Issued | 9/22/2020 | APPLICANT |
| CofO in Progress | 9/26/2022 | DAVID SCANTLIN |
| Permit Finaled | 11/14/2022 | JOHN JANSON |
| CofO Issued | 11/14/2022 | JOHN JANSON |
| Permit Finaled | 11/14/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 10/23/2019 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 10/23/2019 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 10/23/2019 | RINA LARA |
| Sewer availability | Cleared | 10/23/2019 | LEE GUILBEAUX |
| Green Code | Cleared | 10/28/2019 | SEWADA ZADOORAN MILAGARDI |
| Hydrant and Access approval | Cleared | 11/1/2019 | JEREMY CARTER |
| Low Impact Development | Cleared | 11/1/2019 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 11/1/2019 | THOMAS LANG |
Contact Information
| Contractor | S S S Construction Inc; Lic. No.: 743137-B | 17325 LOS ALIMOS STREET GRANADA HILLS, CA 91344 |
| Engineer | Oruncakciel,, Sayat; Lic. No.: C77182 | 15445 VENTURA BLVD 25 SHERMAN OAKS, CA 91403 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/9/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Excavation/Setback/Form/Re-Bar | 3/17/2021 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2021 | Approved | DAVID SCANTLIN |
| Rough-Elec/Plmb/HVAC | 7/20/2021 | Corrections Issued | DAVID SCANTLIN |
| Insulation | 7/30/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Interior/Exterior Lathing | 7/30/2021 | Partial Approval | DAVID SCANTLIN |
| Insulation | 8/5/2021 | Partial Approval | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 8/10/2021 | Partial Approval | STEPHANIE SWANSON |
| Green Building Rough | 8/10/2021 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 8/10/2021 | Corrections Issued | STEPHANIE SWANSON |
| Insulation | 8/10/2021 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 8/18/2021 | Partial Approval | DEANDRE HOFFMAN |
| Shower Pan | 8/18/2021 | Approved | DEANDRE HOFFMAN |
| Special/Order Compliance | 8/19/2021 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 8/24/2021 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 2/10/2022 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 2/10/2022 | Approved | DAVID SCANTLIN |
| Final | 2/10/2022 | Corrections Issued | DAVID SCANTLIN |
| Footing/Foundation/Slab | 2/10/2022 | Approved | DAVID SCANTLIN |
| Green Building Final | 2/10/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 2/10/2022 | SGSOV Not Ready | DAVID SCANTLIN |
| Service/Power Release | 2/10/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| Smoke Detectors | 2/10/2022 | Approved | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 2/10/2022 | Approved | DAVID SCANTLIN |
| Final | 9/15/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Final | 9/15/2022 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 9/15/2022 | SGSOV Approved | DAVID SCANTLIN |
| Service/Power Release | 9/15/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 9/23/2022 | OK to Issue CofO | DAVID SCANTLIN |
| Service/Power Release | 9/23/2022 | Approved | DAVID SCANTLIN |