20833 W BLYTHE ST 91306

Certificate Information: 20833 W BLYTHE ST 91306

Application / Permit
19010-20000-03748
Plan Check / Job No.
B19VN14126
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW DETACHED 27' 5" X 19' 1" IRREGULAR-SHAPED POOL HOUSE. ALL WORK DONE PER WFPP.
Permit Issued
Issued on 4/22/2021
Issuing Office
Current Status
CofO Issued on 2/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/22/2019 APPLICANT
Assigned to Plan Check Engineer 8/22/2019 GURUNATH NESARAJAH
Corrections Issued 8/22/2019 GURUNATH NESARAJAH
Applicant returned to address corrections 12/22/2020 GURUNATH NESARAJAH
Plan Check Approved 3/12/2021 GURUNATH NESARAJAH
Building Plans Picked Up 3/15/2021 APPLICANT
Issued 4/22/2021 APPLICANT
CofO in Progress 2/11/2022 STEVEN BACK
Permit Finaled 2/15/2022 JOHN JANSON
CofO Issued 2/15/2022 JOHN JANSON
Permit Finaled 2/15/2022 JOHN JANSON

Permit Application Clearance Information

Construction near power lines Cleared 11/3/2019 RIDWAN HARDY
Roof/Waste drainage to street Cleared 11/16/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 11/24/2020 ADRIAN CASTRO
Miscellaneous Cleared 1/12/2021 LAUREN PADICK

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/6/2021 Corrections Issued HENRY KIM
Footing/Foundation/Slab 6/2/2021 Approved HENRY KIM
PLUMBING-Rough 6/2/2021 Partial Approval HENRY KIM
Deputy Reinf. Concrete 6/4/2021 Conditional Approval HENRY KIM
BUILDING-Rough-Frame 7/20/2021 Corrections Issued HENRY KIM
ELECTRICAL-Rough 7/20/2021 Corrections Issued HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 7/20/2021 Corrections Issued HENRY KIM
Sewer 7/20/2021 Not Ready for Inspection HENRY KIM
ELECTRICAL-Rough 11/2/2021 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 11/2/2021 Partial Approval STEVEN BACK
PLUMBING-Rough 11/2/2021 Approved STEVEN BACK
Interior/Exterior Lathing 12/7/2021 Approved JESUS PINEDA
BUILDING-Rough-Frame 12/13/2021 Approved STEVEN BACK
Green Building Rough 12/13/2021 Approved STEVEN BACK
HVAC-Rough 12/13/2021 Approved STEVEN BACK
Insulation 12/17/2021 Approved JESUS PINEDA
Drywall Nailing 12/21/2021 Approved MORRIS JACKSON
ELECTRICAL-Final 2/3/2022 Approved STEVEN BACK
Final 2/3/2022 Corrections Issued STEVEN BACK
Green Building Final 2/3/2022 Approved STEVEN BACK
HVAC-Final 2/3/2022 Approved STEVEN BACK
PLUMBING-Final 2/3/2022 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 2/3/2022 SGSOV Not Ready STEVEN BACK
Smoke Detectors 2/3/2022 Approved STEVEN BACK
Final 2/11/2022 OK to Issue CofO STEVEN BACK
SGSOV-Seismic Gas S/O Valve 2/11/2022 SGSOV Approved STEVEN BACK