10189 N MAUDE AVE 91040
Certificate Information: 10189 N MAUDE AVE 91040
- Application / Permit
- 19010-20000-03720
- Plan Check / Job No.
- B19VN14009
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 2- STORY ACCESSORY DWELLING UNIT W/ ATTACHED GARAGE (38'-7"x 23'-0") per LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 4/6/2021
- Issuing Office
- Current Status
- CofO Issued on 2/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/20/2019 | APPLICANT |
| Green Plans Picked Up | 8/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2019 | ALYSSA N NARCISO |
| Corrections Issued | 9/12/2019 | ALYSSA N NARCISO |
| Quality Review Completed | 9/17/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 9/18/2019 | APPLICANT |
| Applicant returned to address corrections | 12/6/2019 | ALYSSA N NARCISO |
| Applicant returned to address corrections | 10/13/2020 | MOHAMMAD ESMAILI |
| Plan Check Approved | 3/10/2021 | MOHAMMAD ESMAILI |
| Issued | 4/6/2021 | APPLICANT |
| CofO in Progress | 1/31/2023 | DAVID ANDERSON |
| CofO Issued | 2/17/2023 | MICHAEL SMITH |
| Permit Finaled | 2/17/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Hold | Cleared | 9/11/2019 | LOURDES RAMIRO |
| Address approval | Cleared | 9/23/2019 | ADRIAN CASTRO |
| BHO/Hillside ordinance | Cleared | 12/6/2019 | JOHN LIN |
| BHO/Hillside ordinance | Cleared | 12/6/2019 | JOHN LIN |
| BHO/Hillside ordinance | Cleared | 12/6/2019 | JOHN LIN |
| Green Code | Cleared | 4/30/2020 | AARON COSTA |
| Distance to fire station | Cleared | 5/28/2020 | JOHN CONNEALLY |
| Eng Process Fee Ord 176,300 | Cleared | 5/28/2020 | JOHN LIN |
| Sewer availability | Cleared | 5/28/2020 | JOHN LIN |
| Hydrant and Access approval | Cleared | 5/29/2020 | KURT CORRAL |
| Low Impact Development | Cleared | 6/18/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 6/19/2020 | JOHN LIN |
| Specific Plan | Cleared | 8/14/2020 | PEGGY MALONE-BROWN |
| GPI Written Notices | Cleared | 3/10/2021 | ALYSSA N NARCISO |
| Grading Pre-Inspection | Cleared | 3/10/2021 | ALYSSA N NARCISO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Moradian,, Helbert; Lic. No.: C76618 | 6944 BECKETT STREET TUJUNGA, CA 91042 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/13/2021 | No Access for Inspection | BEAU COLLINS |
| Excavation/Setback/Form/Re-Bar | 7/14/2021 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 7/14/2021 | Approved | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 7/27/2021 | Approved | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2021 | Partial Approval | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 10/14/2021 | Approved | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2021 | Approved | WILLIAM KUEHN |
| Green Building Rough | 10/14/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| Rough-Elec/Plmb/HVAC | 10/14/2021 | Approved | WILLIAM KUEHN |
| Verify Sprinkler Sign Off | 10/14/2021 | Approved | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2021 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 11/22/2021 | Partial Inspection | WILLIAM KUEHN |
| Drywall Nailing | 12/21/2021 | Approved | WILLIAM KUEHN |
| Green Building Rough | 12/21/2021 | Approved | WILLIAM KUEHN |
| Service/Power Release | 2/17/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Sewer | 7/6/2022 | Approved | DAVID ANDERSON |
| Underground Mechanical | 7/6/2022 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 7/15/2022 | Approved | DAVID ANDERSON |
| Service/Power Release | 7/21/2022 | Corrections Issued | DAVID ANDERSON |
| Service/Power Release | 7/27/2022 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Final | 9/9/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 9/9/2022 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 9/9/2022 | Approved | DAVID ANDERSON |
| Green Building Final | 9/9/2022 | Approved | DAVID ANDERSON |
| HVAC-Final | 9/9/2022 | Not Ready for Inspection | DAVID ANDERSON |
| PLUMBING-Final | 9/9/2022 | Approved | DAVID ANDERSON |
| Reinforced Concrete Frame | 9/9/2022 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 9/9/2022 | SGSOV Approved | DAVID ANDERSON |
| Service/Power Release | 9/9/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 9/9/2022 | Approved | DAVID ANDERSON |
| Final | 10/17/2022 | Corrections Issued | DAVID ANDERSON |
| Service/Power Release | 10/17/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 10/25/2022 | Corrections Issued | DAVID ANDERSON |
| Service/Power Release | 10/25/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 11/7/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Service/Power Release | 11/7/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 11/15/2022 | Corrections Issued | DAVID ANDERSON |
| Service/Power Release | 11/15/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Special/Order Compliance | 12/8/2022 | Corrections Issued | DAVID ANDERSON |
| Final | 1/31/2023 | OK to Issue CofO | DAVID ANDERSON |
| Service/Power Release | 1/31/2023 | Approved | DAVID ANDERSON |