6103 W 75TH PL 90045
Certificate Information: 6103 W 75TH PL 90045
- Application / Permit
- 19010-20000-03698
- Plan Check / Job No.
- B19VN13954
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 33'11" X 16'3" ACCESSORY DWELLING UNIT WITH 11'10"X8'6" ATTACHED STORAGE & 4'0"X3'5" ATTACHED PORCH.
- Permit Issued
- Issued on 1/3/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/7/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2019 | MARVEL DELACRUZ |
| Corrections Issued | 8/31/2019 | MARVEL DELACRUZ |
| Quality Review Completed | 9/6/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 9/17/2019 | APPLICANT |
| Green Plans Picked Up | 9/17/2019 | APPLICANT |
| Applicant returned to address corrections | 12/27/2019 | MARVEL DELACRUZ |
| Plan Check Approved | 1/3/2020 | MARVEL DELACRUZ |
| Issued | 1/3/2020 | LADBS |
| CofO in Progress | 8/24/2021 | BRENDAN LOONEY |
| Permit Finaled | 9/7/2021 | RONALD MYRICK |
| CofO Issued | 9/7/2021 | RONALD MYRICK |
| Permit Finaled | 9/7/2021 | RONALD MYRICK |
Permit Application Clearance Information
| Construction near power lines | Cleared | 9/30/2019 | RIDWAN HARDY |
| Construction within easement | Cleared | 9/30/2019 | RIDWAN HARDY |
| Address approval | Cleared | 12/26/2019 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 12/26/2019 | JOHN LIN |
| Green Code | Cleared | 12/26/2019 | MICHAEL AYERS |
| Hydrant and Access approval | Cleared | 12/26/2019 | JEREMY CARTER |
| Low Impact Development | Cleared | 12/26/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 12/26/2019 | JEANIE LAM |
| Sewer availability | Cleared | 12/26/2019 | JOHN LIN |
| Specific Plan | Cleared | 12/26/2019 | MOHAMMAD HASAN |
| GPI Written Notices | Cleared | 12/27/2019 | MARVEL DELACRUZ |
| Grading Pre-Inspection | Cleared | 12/27/2019 | MARVEL DELACRUZ |
Contact Information
| Contractor | Baron Construction & Remodeling Corp; Lic. No.: 991076-B | 14510 BIG BASIN WAY UNIT B SARATOGA, CA 95070 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/17/2020 | Corrections Issued | JUAN VALENZUELA |
| Underground Mechanical | 2/10/2020 | Partial Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 2/18/2020 | Approved | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2020 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 5/1/2020 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Rough | 5/1/2020 | Corrections Issued | JUAN VALENZUELA |
| Green Building Rough | 5/1/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| PLUMBING-Rough | 5/1/2020 | Corrections Issued | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 5/1/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| ELECTRICAL-Rough | 5/14/2020 | Corrections Issued | ANTHONY MCDOWALL |
| PLUMBING-Rough | 5/14/2020 | Approved | ANTHONY MCDOWALL |
| Wood Frame | 5/14/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| ELECTRICAL-Rough | 5/19/2020 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2020 | Partial Approval | JOHNNY MIRANDA |
| Wood Frame | 5/19/2020 | Partial Approval | JOHNNY MIRANDA |
| HVAC-Rough | 5/21/2020 | Not Ready for Inspection | CRAIG DAVIS |
| HVAC-Rough | 5/26/2020 | Approved | ANTHONY MCDOWALL |
| Insulation | 6/5/2020 | Corrections Issued | JUAN VALENZUELA |
| Insulation | 6/10/2020 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 6/15/2020 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 6/15/2020 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 7/1/2020 | Partial Approval | JOHNNY MIRANDA |
| Shower Pan | 7/1/2020 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 7/8/2020 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 7/8/2020 | Partial Approval | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 7/8/2020 | Approved | JUAN VALENZUELA |
| Final | 12/23/2020 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Final | 12/23/2020 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 12/23/2020 | SGSOV Not Ready | JOHNNY MIRANDA |
| Service/Power Release | 12/23/2020 | Not Required | JOHNNY MIRANDA |
| Smoke Detectors | 12/23/2020 | Approved | JOHNNY MIRANDA |
| Final | 1/22/2021 | Corrections Issued | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 1/22/2021 | SGSOV Approved | JOHNNY MIRANDA |
| Final | 4/8/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Final | 8/23/2021 | OK to Issue CofO | BRENDAN LOONEY |