204-212 N VANCE ST 90272

Certificate Information: 204-212 N VANCE ST 90272

Application / Permit
19010-20000-03688
Plan Check / Job No.
B19VN13901
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW (2) STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE (212 VANCE) AND JUNIOR ACCESSORY DWELLING UNIT (204 VANCE), BASEMENT AND ROOFTOP DECK; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT;
Permit Issued
Issued on 5/10/2022
Issuing Office
Valley
Current Status
Issued on 5/10/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/19/2019 APPLICANT
Green Plans Picked Up 8/26/2019 APPLICANT
Assigned to Plan Check Engineer 8/29/2019 SELLA BENYAMIN
Corrections Issued 9/4/2019 SELLA BENYAMIN
Quality Review Completed 9/6/2019 STEVEN KIM
Building Plans Picked Up 9/10/2019 APPLICANT
Applicant returned to address corrections 2/10/2020 SELLA BENYAMIN
Applicant returned to address corrections 4/1/2020 SELLA BENYAMIN
Applicant returned to address corrections 5/29/2020 SELLA BENYAMIN
Plan Check Approved 4/8/2022 SELLA BENYAMIN
Issued 5/10/2022 APPLICANT

Permit Application Clearance Information

Hydrant and Access approval Cleared 9/17/2019 JOHN CONNEALLY
BHO/Hillside ordinance Cleared 9/18/2019 GUILLERMO PETRA
BHO/Hillside ordinance Cleared 9/18/2019 GUILLERMO PETRA
BHO/Hillside ordinance Cleared 9/18/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 9/18/2019 GUILLERMO PETRA
Permit Cleared 9/18/2019 GUILLERMO PETRA
Sewer availability Cleared 9/18/2019 GUILLERMO PETRA
ZA Case Cleared 9/19/2019 MARITZA PRZEKOP
Green Code Cleared 2/11/2020 MICHAEL AYERS
Low Impact Development Cleared 1/28/2022 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 2/7/2022 RAYMOND MUGAMBWA
Trees in Parkway Cleared 3/17/2022 SELLA BENYAMIN
Coastal Zone Cleared 3/23/2022 LOUIS ORTEGA
Miscellaneous Cleared 3/23/2022 LOUIS ORTEGA
Address approval Cleared 4/12/2022 RAYMOND MUGAMBWA

Contact Information

Contractor Dugally Oberfeld Inc; Lic. No.: 862641-B 484 S SAN VICENTE BLVD      LOS ANGELES, CA 90048
Engineer Labib,, Youhanna T.; Lic. No.: S4549 319 MAIN STREET      EL SEGUNDO, CA 90245

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

ELECTRICAL-Rough 7/14/2026    Time Frame: 8-10

Inspection Request History

Pre-Inspection 5/19/2022 Partial Inspection MICHAEL PELHAM
Piling/Pier/Caisson 8/22/2022 Partial Inspection KEVIN SARGSYAN
PLUMBING-Rough 10/3/2022 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 10/4/2022 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 10/5/2022 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 10/31/2022 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 11/23/2022 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 11/29/2022 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 12/13/2022 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 12/14/2022 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 1/11/2023 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 1/27/2023 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 2/16/2023 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 5/4/2023 Corrections Issued OGANES TARAKHCHYAN
Footing/Foundation/Slab 5/8/2023 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 5/31/2023 Partial Approval OGANES TARAKHCHYAN
Underground Mechanical 6/15/2023 Partial Approval DAVID FEILER
Footing/Foundation/Slab 6/30/2023 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 7/5/2023 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 7/26/2023 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 7/31/2023 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 8/24/2023 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 9/14/2023 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 9/15/2023 Partial Approval OGANES TARAKHCHYAN
HVAC-Rough 10/2/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Footing/Foundation/Slab 10/11/2023 Corrections Issued OGANES TARAKHCHYAN
Deputy Steel/Welding 10/30/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Steel/Welding 10/31/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Steel/Welding 11/1/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Steel/Welding 11/2/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Steel/Welding 11/3/2023 Conditional Approval MICHAEL PELHAM
HVAC-Rough 11/22/2023 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 12/19/2023 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 12/22/2023 Partial Approval EVAN COOPER
Deputy Steel/Welding 5/2/2024 Conditional Approval ARAM AVEDISIAN
Deputy Steel/Welding 5/3/2024 Conditional Approval ARAM AVEDISIAN
Pre-Inspection 5/3/2024 Partial Inspection ARAM AVEDISIAN
Pre-Inspection 6/24/2024 Partial Inspection ARAM AVEDISIAN
Footing/Foundation/Slab 8/26/2024 Not Ready for Inspection EVAN COOPER
Special/Order Compliance 8/27/2024 Corrections Issued EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 9/10/2024 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 9/17/2024 Partial Approval JESUS RODRIGUEZ
Special/Order Compliance 9/17/2024 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 10/8/2024 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 10/23/2024 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 12/4/2024 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 12/12/2024 Conditional Approval JESUS RODRIGUEZ
Insulation 12/26/2024 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Rough 3/20/2025 Corrections Issued HERBERT GIRON
PLUMBING-Rough 4/1/2025 Partial Approval HERBERT GIRON
Footing/Foundation/Slab 4/3/2025 Partial Approval HERBERT GIRON
HVAC-Rough 4/8/2025 Partial Inspection BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 4/23/2025 Corrections Issued HERBERT GIRON
Insulation 5/1/2025 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 5/20/2025 Corrections Issued HERBERT GIRON
PLUMBING-Rough 5/21/2025 Partial Approval STEPHANIE SWANSON
PLUMBING-Rough 5/22/2025 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 5/27/2025 Partial Approval HERBERT GIRON
Special/Order Compliance 5/27/2025 Corrections Issued HERBERT GIRON
PLUMBING-Rough 5/30/2025 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 6/10/2025 Partial Approval MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 6/11/2025 Not Ready for Inspection MEL KHACHATOURIAN
Footing/Foundation/Slab 6/12/2025 Partial Approval HERBERT GIRON
Insulation 6/18/2025 Partial Approval HERBERT GIRON
BUILDING-Rough-Frame 6/25/2025 Partial Approval HERBERT GIRON
ELECTRICAL-Rough 6/25/2025 Partial Approval HERBERT GIRON
Insulation 8/8/2025 Partial Approval TEMISTOCLES CAAL
ELECTRICAL-Rough 8/15/2025 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 8/18/2025 Partial Approval HERBERT GIRON
PLUMBING-Rough 9/3/2025 Partial Approval TEMISTOCLES CAAL
Gas Test 9/5/2025 Approved KENNETH NAGLE
Gas Test 9/11/2025 Approved HERBERT GIRON
Underground Mechanical 9/11/2025 Partial Approval HERBERT GIRON
Special/Order Compliance 9/12/2025 Partial Inspection TEMISTOCLES CAAL
Underground Mechanical 9/12/2025 Partial Approval HERBERT GIRON
PLUMBING-Rough 9/19/2025 Partial Approval MICHAEL ALLEN
Pre-Inspection 9/25/2025 Partial Inspection HERBERT GIRON
Gas Test 10/3/2025 Partial Approval HERBERT GIRON
Underground Mechanical 10/3/2025 Partial Approval HERBERT GIRON
PLUMBING-Rough 10/22/2025 Partial Approval STEPHANIE SWANSON
HVAC-Rough 11/5/2025 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 11/19/2025 Partial Approval HERBERT GIRON
HVAC-Rough 11/21/2025 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Rough 12/19/2025 Partial Approval HERBERT GIRON
Excavation/Setback/Form/Re-Bar 1/21/2026 Not Ready for Inspection HERBERT GIRON
Footing/Foundation/Slab 1/21/2026 Not Ready for Inspection HERBERT GIRON
HVAC-Rough 2/2/2026 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 2/4/2026 Not Ready for Inspection HERBERT GIRON
HVAC-Rough 2/5/2026 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 2/6/2026 Partial Approval RYAN SALAZAR
HVAC-Rough 2/17/2026 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 2/19/2026 Partial Approval HERBERT GIRON
Deputy Steel/Welding 2/20/2026 Conditional Approval JUAN VALENZUELA
PLUMBING-Rough 2/20/2026 No Access for Inspection HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 3/11/2026 Partial Approval HERBERT GIRON
HVAC-Rough 3/12/2026 Partial Approval HERBERT GIRON
ELECTRICAL-Rough 3/13/2026 Partial Inspection HERBERT GIRON
Special/Order Compliance 3/13/2026 Partial Inspection TEMISTOCLES CAAL
PLUMBING-Rough 3/26/2026 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 4/10/2026 Partial Approval HERBERT GIRON
Interior/Exterior Lathing 4/13/2026 Partial Approval DANIEL VERA
Shower Pan 4/14/2026 Partial Approval MICHAEL ALLEN
Underground Mechanical 4/15/2026 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 4/17/2026 Partial Approval HERBERT GIRON
Light Gage Steel Frame 4/29/2026 Partial Approval HERBERT GIRON
HVAC-Rough 5/1/2026 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 5/6/2026 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 5/7/2026 Partial Approval TEMISTOCLES CAAL
ELECTRICAL-Rough 5/8/2026 Corrections Issued HERBERT GIRON
Interior/Exterior Lathing 5/8/2026 Partial Approval HERBERT GIRON
BUILDING-Rough-Frame 5/15/2026 Partial Approval HERBERT GIRON
Drywall Nailing 5/15/2026 Partial Approval HERBERT GIRON
HVAC-Rough 5/29/2026 Partial Approval HERBERT GIRON
Light Gage Steel Frame 6/3/2026 Partial Approval HERBERT GIRON
Shower Pan 6/4/2026 Corrections Issued HERBERT GIRON
Shower Pan 6/5/2026 Partial Approval HERBERT GIRON
Shower Pan 6/9/2026 Partial Approval HERBERT GIRON
Shower Pan 6/11/2026 Approved HERBERT GIRON
Interior/Exterior Lathing 6/22/2026 Partial Approval EVAN COOPER
Interior/Exterior Lathing 7/6/2026 Partial Approval EVAN COOPER
ELECTRICAL-Rough 7/7/2026 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 7/9/2026 Corrections Issued HERBERT GIRON
Green Building Rough 7/9/2026 Partial Approval HERBERT GIRON
Verify Sprinkler Sign Off 7/9/2026 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 7/10/2026 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 7/13/2026 Partial Approval HERBERT GIRON