10612 W BLOOMFIELD ST Lot 1 91602

Certificate Information: 10612 W BLOOMFIELD ST Lot 1 91602

Application / Permit
19010-20000-03584
Plan Check / Job No.
B19VN13607
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New (36'-9 1/2"x 19'-7 1/2") 3- story SFD with attached garage fire sprinklers NFPA-13D required through-out. per"small lot subdivision pursuant to tentative tract map no. VVT-82075-SL and Case No. ZA-2018-1870-ZV-ZAA. A certificate of occupancy (temporary or final) shall not be issued until after the final map has been recorded."
Permit Issued
Issued on 10/7/2020
Issuing Office
Valley
Current Status
CofO Issued on 9/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/14/2019 APPLICANT
Assigned to Plan Check Engineer 9/12/2019 TROY DEGUZMAN
Green Plans Picked Up 9/13/2019 APPLICANT
Corrections Issued 9/20/2019 TROY DEGUZMAN
Quality Review Completed 9/20/2019 CHON CHIO KUO
Building Plans Picked Up 9/24/2019 APPLICANT
Applicant returned to address corrections 11/15/2019 TROY DEGUZMAN
Applicant returned to address corrections 12/12/2019 TROY DEGUZMAN
Applicant returned to address corrections 8/18/2020 TROY DEGUZMAN
Plan Check Approved 8/20/2020 TROY DEGUZMAN
Issued 10/7/2020 APPLICANT
CofO in Progress 9/9/2022 HENRY KIM
Permit Finaled 9/10/2022 MICHAEL SMITH
CofO Issued 9/10/2022 MICHAEL SMITH
Permit Finaled 9/10/2022 MICHAEL SMITH

Permit Application Clearance Information

Green Code Cleared 10/25/2019 MICHAEL AYERS
Address approval Cleared 12/26/2019 HOWARD COOPER
Address approval Cleared 12/26/2019 HOWARD COOPER
Hydrant and Access approval Cleared 1/8/2020 ROBERT DUFF
Low Impact Development Cleared 1/10/2020 JORGE MEJIA LEMUS
"Q" conditions Cleared 1/15/2020 SARAH GOLDMAN
Frnt yard landscape/Water mgmt Cleared 1/15/2020 SARAH GOLDMAN
Miscellaneous Cleared 1/15/2020 SARAH GOLDMAN
Miscellaneous Cleared 1/15/2020 SARAH GOLDMAN
Tract Map conditions Cleared 1/15/2020 SARAH GOLDMAN
ZA Case Cleared 1/15/2020 SARAH GOLDMAN
ZI Cleared 1/15/2020 SARAH GOLDMAN
Trees in Parkway Cleared 1/22/2020 JOHN KIM
Eng Process Fee Ord 176,300 Cleared 3/12/2020 JOHN TRIANTAFYLLOS
Highway dedication Cleared 3/12/2020 JOHN TRIANTAFYLLOS
Miscellaneous Cleared 3/12/2020 JOHN TRIANTAFYLLOS
Permit Cleared 3/12/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 3/12/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 6/30/2020 ADRIAN CASTRO
Miscellaneous Cleared 7/30/2020 TROY DEGUZMAN

Contact Information

Architect Stark,, Anthony Alan; Lic. No.: C18639 3630 TYNURN STREET      LOS ANGELES, CA 90065
Contractor Owner-Builder       ,
Engineer Oruncakciel,, Sayat; Lic. No.: C77182 15445 VENTURA BLVD 25      SHERMAN OAKS, CA 91403

Inspector Information

JOSEPH SAGEN, (818) 774-4353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/2/2020 Partial Approval JOSEPH SAGEN
Footing/Foundation/Slab 12/2/2020 Partial Approval JOSEPH SAGEN
Underground Mechanical 12/2/2020 Partial Approval JOSEPH SAGEN
Footing/Foundation/Slab 12/7/2020 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 12/11/2020 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 1/12/2021 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 1/14/2021 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 1/26/2021 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 2/1/2021 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 2/11/2021 Partial Approval JOSEPH SAGEN
Deputy Wood Construction 3/4/2021 Approved JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 3/10/2021 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 4/1/2021 Not Ready for Inspection JOSEPH SAGEN
ELECTRICAL-Rough 4/15/2021 Approved JOSEPH SAGEN
HVAC-Rough 4/16/2021 Not Ready for Inspection JOSEPH SAGEN
HVAC-Rough 5/11/2021 Approved JOSEPH SAGEN
PLUMBING-Rough 5/11/2021 Approved JOSEPH SAGEN
Shower Pan 5/18/2021 Approved JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 6/15/2021 Partial Approval JOSEPH SAGEN
Shower Pan 6/15/2021 Approved JOSEPH SAGEN
BUILDING-Rough-Frame 6/29/2021 Approved JOSEPH SAGEN
Green Building Rough 6/29/2021 Approved JOSEPH SAGEN
Verify Sprinkler Sign Off 6/29/2021 Approved JOSEPH SAGEN
Drywall Nailing 7/26/2021 Approved JOSEPH SAGEN
Interior/Exterior Lathing 8/5/2021 Partial Approval JOSEPH SAGEN
Interior/Exterior Lathing 9/20/2021 Partial Approval JOSEPH SAGEN
Underground Mechanical 11/2/2021 Partial Approval JOSEPH SAGEN
Gas Test 2/11/2022 Approved HENRY KIM
Service/Power Release 4/14/2022 Approved HENRY KIM
SGSOV-Seismic Gas S/O Valve 4/22/2022 SGSOV Approved HENRY KIM
ELECTRICAL-Final 7/29/2022 Corrections Issued HENRY KIM
Final 7/29/2022 Corrections Issued HENRY KIM
Green Building Final 7/29/2022 Approved HENRY KIM
HVAC-Final 7/29/2022 Corrections Issued HENRY KIM
PLUMBING-Final 7/29/2022 Corrections Issued HENRY KIM
Smoke Detectors 7/29/2022 Approved HENRY KIM
ELECTRICAL-Final 9/8/2022 Approved HENRY KIM
Final 9/8/2022 OK to Issue CofO HENRY KIM
HVAC-Final 9/8/2022 Approved HENRY KIM
PLUMBING-Final 9/8/2022 Approved HENRY KIM