10612 W BLOOMFIELD ST Lot 1 91602
Certificate Information: 10612 W BLOOMFIELD ST Lot 1 91602
- Application / Permit
- 19010-20000-03584
- Plan Check / Job No.
- B19VN13607
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New (36'-9 1/2"x 19'-7 1/2") 3- story SFD with attached garage fire sprinklers NFPA-13D required through-out. per"small lot subdivision pursuant to tentative tract map no. VVT-82075-SL and Case No. ZA-2018-1870-ZV-ZAA. A certificate of occupancy (temporary or final) shall not be issued until after the final map has been recorded."
- Permit Issued
- Issued on 10/7/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/14/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/12/2019 | TROY DEGUZMAN |
| Green Plans Picked Up | 9/13/2019 | APPLICANT |
| Corrections Issued | 9/20/2019 | TROY DEGUZMAN |
| Quality Review Completed | 9/20/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 9/24/2019 | APPLICANT |
| Applicant returned to address corrections | 11/15/2019 | TROY DEGUZMAN |
| Applicant returned to address corrections | 12/12/2019 | TROY DEGUZMAN |
| Applicant returned to address corrections | 8/18/2020 | TROY DEGUZMAN |
| Plan Check Approved | 8/20/2020 | TROY DEGUZMAN |
| Issued | 10/7/2020 | APPLICANT |
| CofO in Progress | 9/9/2022 | HENRY KIM |
| Permit Finaled | 9/10/2022 | MICHAEL SMITH |
| CofO Issued | 9/10/2022 | MICHAEL SMITH |
| Permit Finaled | 9/10/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Green Code | Cleared | 10/25/2019 | MICHAEL AYERS |
| Address approval | Cleared | 12/26/2019 | HOWARD COOPER |
| Address approval | Cleared | 12/26/2019 | HOWARD COOPER |
| Hydrant and Access approval | Cleared | 1/8/2020 | ROBERT DUFF |
| Low Impact Development | Cleared | 1/10/2020 | JORGE MEJIA LEMUS |
| "Q" conditions | Cleared | 1/15/2020 | SARAH GOLDMAN |
| Frnt yard landscape/Water mgmt | Cleared | 1/15/2020 | SARAH GOLDMAN |
| Miscellaneous | Cleared | 1/15/2020 | SARAH GOLDMAN |
| Miscellaneous | Cleared | 1/15/2020 | SARAH GOLDMAN |
| Tract Map conditions | Cleared | 1/15/2020 | SARAH GOLDMAN |
| ZA Case | Cleared | 1/15/2020 | SARAH GOLDMAN |
| ZI | Cleared | 1/15/2020 | SARAH GOLDMAN |
| Trees in Parkway | Cleared | 1/22/2020 | JOHN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 3/12/2020 | JOHN TRIANTAFYLLOS |
| Highway dedication | Cleared | 3/12/2020 | JOHN TRIANTAFYLLOS |
| Miscellaneous | Cleared | 3/12/2020 | JOHN TRIANTAFYLLOS |
| Permit | Cleared | 3/12/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 3/12/2020 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 6/30/2020 | ADRIAN CASTRO |
| Miscellaneous | Cleared | 7/30/2020 | TROY DEGUZMAN |
Contact Information
| Architect | Stark,, Anthony Alan; Lic. No.: C18639 | 3630 TYNURN STREET LOS ANGELES, CA 90065 |
| Contractor | Owner-Builder | , |
| Engineer | Oruncakciel,, Sayat; Lic. No.: C77182 | 15445 VENTURA BLVD 25 SHERMAN OAKS, CA 91403 |
Inspector Information
| JOSEPH SAGEN, (818) 774-4353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/2/2020 | Partial Approval | JOSEPH SAGEN |
| Footing/Foundation/Slab | 12/2/2020 | Partial Approval | JOSEPH SAGEN |
| Underground Mechanical | 12/2/2020 | Partial Approval | JOSEPH SAGEN |
| Footing/Foundation/Slab | 12/7/2020 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 12/11/2020 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2021 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2021 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2021 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2021 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2021 | Partial Approval | JOSEPH SAGEN |
| Deputy Wood Construction | 3/4/2021 | Approved | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2021 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| ELECTRICAL-Rough | 4/15/2021 | Approved | JOSEPH SAGEN |
| HVAC-Rough | 4/16/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| HVAC-Rough | 5/11/2021 | Approved | JOSEPH SAGEN |
| PLUMBING-Rough | 5/11/2021 | Approved | JOSEPH SAGEN |
| Shower Pan | 5/18/2021 | Approved | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2021 | Partial Approval | JOSEPH SAGEN |
| Shower Pan | 6/15/2021 | Approved | JOSEPH SAGEN |
| BUILDING-Rough-Frame | 6/29/2021 | Approved | JOSEPH SAGEN |
| Green Building Rough | 6/29/2021 | Approved | JOSEPH SAGEN |
| Verify Sprinkler Sign Off | 6/29/2021 | Approved | JOSEPH SAGEN |
| Drywall Nailing | 7/26/2021 | Approved | JOSEPH SAGEN |
| Interior/Exterior Lathing | 8/5/2021 | Partial Approval | JOSEPH SAGEN |
| Interior/Exterior Lathing | 9/20/2021 | Partial Approval | JOSEPH SAGEN |
| Underground Mechanical | 11/2/2021 | Partial Approval | JOSEPH SAGEN |
| Gas Test | 2/11/2022 | Approved | HENRY KIM |
| Service/Power Release | 4/14/2022 | Approved | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 4/22/2022 | SGSOV Approved | HENRY KIM |
| ELECTRICAL-Final | 7/29/2022 | Corrections Issued | HENRY KIM |
| Final | 7/29/2022 | Corrections Issued | HENRY KIM |
| Green Building Final | 7/29/2022 | Approved | HENRY KIM |
| HVAC-Final | 7/29/2022 | Corrections Issued | HENRY KIM |
| PLUMBING-Final | 7/29/2022 | Corrections Issued | HENRY KIM |
| Smoke Detectors | 7/29/2022 | Approved | HENRY KIM |
| ELECTRICAL-Final | 9/8/2022 | Approved | HENRY KIM |
| Final | 9/8/2022 | OK to Issue CofO | HENRY KIM |
| HVAC-Final | 9/8/2022 | Approved | HENRY KIM |
| PLUMBING-Final | 9/8/2022 | Approved | HENRY KIM |