1937 S WEST VIEW ST 90016

Certificate Information: 1937 S WEST VIEW ST 90016

Application / Permit
19010-20000-03552
Plan Check / Job No.
B19VN13392
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ACCESSORY DWELLING UNIT PER AB 494 & SB 229.
Permit Issued
Issued on 4/10/2020
Issuing Office
Valley
Current Status
CofO Issued on 2/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/12/2019 APPLICANT
Assigned to Plan Check Engineer 8/22/2019 ABDUL CHEGENI
Green Plans Picked Up 8/23/2019 APPLICANT
Corrections Issued 8/26/2019 ABDUL CHEGENI
Quality Review Completed 8/29/2019 STEVEN KIM
Building Plans Picked Up 9/3/2019 APPLICANT
Plan Check Approved 10/7/2019 ABDUL CHEGENI
Issued 4/10/2020 LADBS
CofO in Progress 2/10/2023 STUART CHAPMAN
Permit Finaled 2/15/2023 DEROLD HAUFF
CofO Issued 2/15/2023 DEROLD HAUFF
Permit Finaled 2/15/2023 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 9/17/2019 AARON COSTA
Address approval Cleared 10/2/2019 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 10/2/2019 JEANETTE VONG
Hydrant and Access approval Cleared 10/2/2019 JEREMY CARTER
Low Impact Development Cleared 10/2/2019 MARTIN FRAGOSO
Permit Cleared 10/2/2019 JEANETTE VONG
Roof/Waste drainage to street Cleared 10/2/2019 JEANETTE VONG
Sewer availability Cleared 10/2/2019 JEANETTE VONG

Contact Information

Contractor Owner-Builder       ,
Engineer Shakiban,, George; Lic. No.: C39908 23945 CALABASAS RD STE 101      CALABASAS, CA 91302

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/22/2020 Approved STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 5/1/2020 Conditional Approval STUART CHAPMAN
PLUMBING-Rough 5/1/2020 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 5/11/2020 Partial Approval STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 5/28/2020 Conditional Approval STUART CHAPMAN
Footing/Foundation/Slab 5/28/2020 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 6/17/2020 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 10/7/2020 Approved STUART CHAPMAN
HVAC-Rough 10/7/2020 Approved STUART CHAPMAN
PLUMBING-Rough 10/7/2020 Approved STUART CHAPMAN
BUILDING-Rough-Frame 11/10/2020 Approved STUART CHAPMAN
Green Building Rough 11/10/2020 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 11/10/2020 Approved STUART CHAPMAN
Insulation 2/16/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 2/16/2021 Partial Approval STUART CHAPMAN
Drywall Nailing 3/19/2021 Approved STUART CHAPMAN
Shower Pan 5/20/2021 Approved SCOTT FINNILA
Interior/Exterior Lathing 6/23/2021 Partial Approval HORACE FULTZ
Shower Pan 8/3/2021 Approved CALEB MEISTER
ELECTRICAL-Final 12/1/2021 Corrections Issued STUART CHAPMAN
Final 12/1/2021 Corrections Issued STUART CHAPMAN
Green Building Final 12/1/2021 Approved STUART CHAPMAN
HVAC-Final 12/1/2021 Corrections Issued STUART CHAPMAN
PLUMBING-Final 12/1/2021 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 12/1/2021 SGSOV Approved STUART CHAPMAN
Service/Power Release 12/1/2021 Not Ready for Inspection STUART CHAPMAN
Smoke Detectors 12/1/2021 Approved STUART CHAPMAN
Final 12/22/2021 Corrections Issued STUART CHAPMAN
Service/Power Release 12/22/2021 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Final 2/18/2022 Approved STUART CHAPMAN
Final 2/18/2022 Partial Approval STUART CHAPMAN
HVAC-Final 2/18/2022 Approved STUART CHAPMAN
Service/Power Release 2/18/2022 Approved STUART CHAPMAN
Final 2/10/2023 OK to Issue CofO STUART CHAPMAN