355 N MOUNT HOLYOKE AVE 90272

Certificate Information: 355 N MOUNT HOLYOKE AVE 90272

Application / Permit
19010-20000-03548
Plan Check / Job No.
B19VN13374
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SFD WITH BASEMENT AND ATTACHED GARAGE AND ATTACHED 42 SF PATIOCVER PORCH AND 726 SF OPEN TRELLIS AT THE BACK OF SECOND FLOOR.
Permit Issued
Issued on 10/21/2020
Issuing Office
Metro
Current Status
CofO Issued on 1/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/9/2019 APPLICANT
Assigned to Plan Check Engineer 9/5/2019 RODNEY SAMIIAN
Corrections Issued 9/11/2019 RODNEY SAMIIAN
Quality Review Completed 9/11/2019 ABDUL CHEGENI
Building Plans Picked Up 9/17/2019 APPLICANT
Green Plans Picked Up 9/19/2019 APPLICANT
Applicant returned to address corrections 9/15/2020 RODNEY SAMIIAN
Plan Check Approved 10/14/2020 RODNEY SAMIIAN
Issued 10/21/2020 APPLICANT
CofO in Progress 1/24/2023 BRENDAN LOONEY
Permit Finaled 1/25/2023 DANIEL ORRANTE
CofO Issued 1/25/2023 DANIEL ORRANTE
Permit Finaled 1/25/2023 DANIEL ORRANTE

Permit Application Clearance Information

Green Code Cleared 5/26/2020 MICHAEL AYERS
Hydrant and Access approval Cleared 6/25/2020 KURT CORRAL
Low Impact Development Cleared 6/30/2020 ANDRES COVARRUBIAS
BHO/Hillside ordinance Cleared 7/7/2020 DINAH GARIN
BHO/Hillside ordinance Cleared 7/7/2020 DINAH GARIN
BHO/Hillside ordinance Cleared 7/7/2020 DINAH GARIN
Permit Cleared 7/10/2020 DINAH GARIN
Roof/Waste drainage to street Cleared 7/10/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 7/14/2020 DINAH GARIN
Sewer availability Cleared 7/14/2020 DINAH GARIN
Coastal Zone Cleared 8/21/2020 DENZEL HENDERSON
ZA Case Cleared 8/21/2020 DENZEL HENDERSON
ZA Case Cleared 8/21/2020 DENZEL HENDERSON
Miscellaneous Cleared 9/25/2020 DENZEL HENDERSON
Miscellaneous Cleared 9/25/2020 DENZEL HENDERSON
Excavation more than 5-ft deep Cleared 10/1/2020 CALOSHA APPROVED

Contact Information

Contractor Blue Label Construction Inc; Lic. No.: 972011-B 1448 15TH STREET #102      SANTA MONICA, CA 90404
Engineer Walter,, Scott John; Lic. No.: GE2476 14428 HAMLIN ST STE 200      VAN NUYS, CA 91401
Engineer Warling,, Jeffrey Paul; Lic. No.: C43743 2828 COCHRAN STREET 321      SIMI VALLEY, CA 93065
Geologist Barrett,, Mark A; Lic. No.: EG2088 14428 HAMLIN ST 200      VAN NUYS, CA 91401

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/8/2020 Approved ANDREW NAVE
Deputy Grading 12/15/2020 Approved ANDREW NAVE
Deputy Grading 12/16/2020 Approved ROBERT SHELLY
Deputy Grading 12/17/2020 Approved ROBERT SHELLY
Deputy Grading 12/18/2020 Approved ROBERT SHELLY
Deputy Reinf. Concrete 5/24/2021 Conditional Approval ANDREW NAVE
Footing/Foundation/Slab 5/24/2021 Partial Approval ANDREW NAVE
Deputy Reinf. Concrete 5/25/2021 Conditional Approval ANDREW NAVE
Deputy Shotcrete 6/9/2021 Conditional Approval AMY COLIN
Deputy Steel/Welding 6/9/2021 Conditional Approval AMY COLIN
Deputy Reinf. Concrete 6/11/2021 Conditional Approval ROBERT SHELLY
Footing/Foundation/Slab 6/11/2021 Partial Approval KENNETH NAGLE
Deputy Shotcrete 6/14/2021 Conditional Approval ROBERT SHELLY
PLUMBING-Rough 6/28/2021 Corrections Issued ANDREW NAVE
PLUMBING-Rough 7/1/2021 Partial Approval ANDREW NAVE
Deputy Reinf. Concrete 7/9/2021 Approved ANDREW NAVE
Footing/Foundation/Slab 7/12/2021 Partial Approval ANDREW NAVE
Deputy Steel/Welding 7/22/2021 Conditional Approval ANDREW NAVE
Deputy Wood Construction 8/5/2021 Approved ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 8/5/2021 Partial Approval ANDREW NAVE
Deputy Steel/Welding 8/11/2021 Conditional Approval DANIEL ORRANTE
Footing/Foundation/Slab 8/25/2021 Partial Approval ANDREW NAVE
Special/Order Compliance 8/25/2021 Approved JESUS RODRIGUEZ
Deputy Other (see comments) 8/31/2021 Conditional Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 9/8/2021 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 9/9/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 9/9/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 9/10/2021 Partial Approval ANDREW NAVE
Deputy Wood Construction 9/10/2021 Conditional Approval JESUS RODRIGUEZ
Deputy Wood Construction 9/13/2021 Conditional Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 10/22/2021 Partial Inspection ANDREW NAVE
Deputy Wood Construction 11/10/2021 Conditional Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 11/19/2021 Corrections Issued ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 12/6/2021 Approved ANDREW NAVE
Pre-Inspection 12/6/2021 Partial Inspection STEPHANIE SWANSON
ELECTRICAL-Rough 1/14/2022 Corrections Issued ANDREW NAVE
HVAC-Rough 1/18/2022 Approved ANDREW NAVE
ELECTRICAL-Rough 1/24/2022 Approved ANDREW NAVE
PLUMBING-Rough 1/24/2022 Corrections Issued ANDREW NAVE
Special/Order Compliance 1/24/2022 Corrections Issued ANDREW NAVE
BUILDING-Rough-Frame 1/28/2022 Partial Approval ANDREW NAVE
Green Building Rough 1/28/2022 Not Ready for Inspection ANDREW NAVE
Verify Sprinkler Sign Off 1/28/2022 Approved ANDREW NAVE
Deputy Wood Construction 2/9/2022 Conditional Approval ANDREW NAVE
BUILDING-Rough-Frame 2/16/2022 Corrections Issued ANDREW NAVE
Green Building Rough 2/16/2022 Not Ready for Inspection ANDREW NAVE
BUILDING-Rough-Frame 2/18/2022 Conditional Approval ANDREW NAVE
Green Building Rough 2/18/2022 Not Ready for Inspection ANDREW NAVE
PLUMBING-Rough 2/18/2022 Approved ANDREW NAVE
BUILDING-Rough-Frame 3/9/2022 Approved JUAN VALENZUELA
Green Building Rough 3/9/2022 Approved JUAN VALENZUELA
Final 3/22/2022 Corrections Issued STEPHANIE SWANSON
Insulation 3/22/2022 Approved STEPHANIE SWANSON
Drywall Nailing 3/30/2022 Partial Approval ANDREW NAVE
Drywall Nailing 4/6/2022 Approved ANDREW NAVE
Shower Pan 4/27/2022 Approved ANDREW NAVE
Interior/Exterior Lathing 5/12/2022 Partial Approval ANDREW NAVE
Gas Test 8/23/2022 Partial Approval BRENDAN LOONEY
PLUMBING-Rough 8/23/2022 Partial Approval BRENDAN LOONEY
Sewer 8/23/2022 Approved BRENDAN LOONEY
ELECTRICAL-Final 11/28/2022 Not Ready for Inspection BRENDAN LOONEY
Service/Power Release 11/28/2022 Not Ready for Inspection BRENDAN LOONEY
HVAC-Final 11/29/2022 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Final 11/30/2022 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Final 12/1/2022 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Final 12/1/2022 Corrections Issued KEVIN SARGSYAN
Service/Power Release 12/1/2022 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Final 12/5/2022 Approved BRENDAN LOONEY
HVAC-Final 12/5/2022 Approved BRENDAN LOONEY
Service/Power Release 12/5/2022 Not Ready for Inspection BRENDAN LOONEY
Gas Test 12/14/2022 Approved BRENDAN LOONEY
PLUMBING-Final 12/14/2022 Partial Approval BRENDAN LOONEY
PLUMBING-Final 1/4/2023 Approved BRENDAN LOONEY
Final 1/12/2023 Conditional Approval BRENDAN LOONEY
Footing/Foundation/Slab 1/12/2023 Approved BRENDAN LOONEY
Green Building Final 1/12/2023 Approved BRENDAN LOONEY
Reinforced Concrete Frame 1/12/2023 Approved BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 1/12/2023 SGSOV Approved BRENDAN LOONEY
Service/Power Release 1/12/2023 Approved BRENDAN LOONEY
Smoke Detectors 1/12/2023 Approved BRENDAN LOONEY
Final 1/23/2023 OK to Issue CofO BRENDAN LOONEY