9421 N FARRALONE AVE 91311
Certificate Information: 9421 N FARRALONE AVE 91311
- Application / Permit
- 19010-20000-03528
- Plan Check / Job No.
- B19VN13315
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 11'-10" x 28' DETACHED ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
- Permit Issued
- Issued on 10/10/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/22/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/8/2019 | APPLICANT |
| Green Plans Picked Up | 8/21/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/22/2019 | SELLA BENYAMIN |
| Corrections Issued | 8/26/2019 | SELLA BENYAMIN |
| Quality Review Completed | 8/26/2019 | STEVEN KIM |
| Building Plans Picked Up | 8/26/2019 | APPLICANT |
| Plan Check Approved | 10/9/2019 | SELLA BENYAMIN |
| Issued | 10/10/2019 | LADBS |
| Refund in Progress-Status Void | 5/12/2020 | SELENIA GARCIA |
| Re-Activate Permit | 5/14/2020 | MARY SUM |
| Refund Withdrawn | 5/14/2020 | CHRISTINA TABIRARA |
| Reactivate - Status Void | 5/14/2020 | CHRISTINA TABIRARA |
| CofO in Progress | 12/22/2020 | HAGOP BADOSSIAN |
| Permit Finaled | 12/22/2020 | DAVID JAMES |
| CofO Issued | 12/22/2020 | DAVID JAMES |
| Permit Finaled | 12/22/2020 | DAVID JAMES |
Permit Application Clearance Information
| Address approval | Cleared | 8/28/2019 | APEKSHYA BAJRACHARYA |
| Specific Plan | Cleared | 9/5/2019 | HERMINIGILDO AGUSTIN |
| ZA Case | Cleared | 9/5/2019 | HERMINIGILDO AGUSTIN |
| ZA Case | Cleared | 9/5/2019 | HERMINIGILDO AGUSTIN |
| Hydrant and Access approval | Cleared | 9/16/2019 | GILBERT URREA |
| BHO/Hillside ordinance | Cleared | 9/20/2019 | GUILLERMO PETRA |
| BHO/Hillside ordinance | Cleared | 9/20/2019 | GUILLERMO PETRA |
| BHO/Hillside ordinance | Cleared | 9/20/2019 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 9/20/2019 | GUILLERMO PETRA |
| Green Code | Cleared | 9/20/2019 | MICHAEL AYERS |
| Sewer availability | Cleared | 9/20/2019 | GUILLERMO PETRA |
| Grading Pre-Inspection | Cleared | 9/26/2019 | BRIAN MILLER |
| Roof/Waste drainage to street | Cleared | 10/9/2019 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 7/29/2020 | Approved | HAGOP BADOSSIAN |
| Footing/Foundation/Slab | 7/29/2020 | Partial Approval | HAGOP BADOSSIAN |
| PLUMBING-Rough | 7/29/2020 | Partial Approval | HAGOP BADOSSIAN |
| PLUMBING-Rough | 7/31/2020 | Corrections Issued | MARK DOVICO |
| BUILDING-Rough-Frame | 8/4/2020 | Not Ready for Inspection | HAGOP BADOSSIAN |
| Excavation/Setback/Form/Re-Bar | 8/4/2020 | Approved | HAGOP BADOSSIAN |
| Insulation | 8/14/2020 | Approved | ROBERT SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2020 | Corrections Issued | HAGOP BADOSSIAN |
| Insulation | 8/20/2020 | Approved | HAGOP BADOSSIAN |
| Shower Pan | 8/20/2020 | Approved | HAGOP BADOSSIAN |
| Special/Order Compliance | 8/20/2020 | Approved | HAGOP BADOSSIAN |
| Excavation/Setback/Form/Re-Bar | 8/24/2020 | Approved | HAGOP BADOSSIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2020 | Approved | HAGOP BADOSSIAN |
| Drywall Nailing | 8/27/2020 | Approved | HAGOP BADOSSIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2020 | Approved | HAGOP BADOSSIAN |
| BUILDING-Rough-Frame | 11/16/2020 | Approved | HAGOP BADOSSIAN |
| Final | 11/16/2020 | Not Ready for Inspection | HAGOP BADOSSIAN |
| Green Building Final | 11/16/2020 | Approved | HAGOP BADOSSIAN |
| Green Building Rough | 11/16/2020 | Approved | HAGOP BADOSSIAN |
| SGSOV-Seismic Gas S/O Valve | 11/16/2020 | SGSOV Not Ready | HAGOP BADOSSIAN |
| Service/Power Release | 11/16/2020 | Corrections Issued | HAGOP BADOSSIAN |
| Smoke Detectors | 11/16/2020 | Approved | HAGOP BADOSSIAN |
| Verify Sprinkler Sign Off | 11/16/2020 | Approved | HAGOP BADOSSIAN |
| Final | 11/18/2020 | Not Ready for Inspection | HAGOP BADOSSIAN |
| Footing/Foundation/Slab | 11/18/2020 | Approved | HAGOP BADOSSIAN |
| SGSOV-Seismic Gas S/O Valve | 11/18/2020 | SGSOV Not Ready | HAGOP BADOSSIAN |
| Final | 11/20/2020 | Not Ready for Inspection | MARK DOVICO |
| SGSOV-Seismic Gas S/O Valve | 11/20/2020 | SGSOV Not Ready | MARK DOVICO |
| Service/Power Release | 11/20/2020 | Not Ready for Inspection | MARK DOVICO |
| Final | 11/23/2020 | Not Ready for Inspection | HAGOP BADOSSIAN |
| Gas Test | 11/23/2020 | Corrections Issued | HAGOP BADOSSIAN |
| Service/Power Release | 11/23/2020 | Not Ready for Inspection | HAGOP BADOSSIAN |
| Final | 12/14/2020 | Corrections Issued | HAGOP BADOSSIAN |
| SGSOV-Seismic Gas S/O Valve | 12/14/2020 | SGSOV Approved | HAGOP BADOSSIAN |
| Service/Power Release | 12/14/2020 | Conditional Approval | HAGOP BADOSSIAN |
| ELECTRICAL-Final | 12/21/2020 | Approved | HAGOP BADOSSIAN |
| Final | 12/21/2020 | OK to Issue CofO | HAGOP BADOSSIAN |
| HVAC-Final | 12/21/2020 | Approved | HAGOP BADOSSIAN |
| PLUMBING-Final | 12/21/2020 | Approved | HAGOP BADOSSIAN |
| Service/Power Release | 12/21/2020 | Approved | HAGOP BADOSSIAN |