11038 N GENESTA AVE 91344

Certificate Information: 11038 N GENESTA AVE 91344

Application / Permit
19010-20000-03515
Plan Check / Job No.
B19VN13279
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW64'0" x 24'6" DETACHED ACCESSORY DWELLING UNIT PER AB 494 AND SB 229, ALL WORK PER WFPP.
Permit Issued
Issued on 10/31/2019
Issuing Office
Valley
Current Status
CofO Issued on 4/9/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/8/2019 APPLICANT
Green Plans Picked Up 8/20/2019 APPLICANT
Assigned to Plan Check Engineer 8/22/2019 JEFFREY TANGONAN
Corrections Issued 8/28/2019 JEFFREY TANGONAN
Quality Review Completed 8/29/2019 STEVEN KIM
Building Plans Picked Up 8/30/2019 APPLICANT
Plan Check Approved 10/31/2019 JEFFREY TANGONAN
Issued 10/31/2019 LADBS
CofO in Progress 3/31/2021 DAVID SCANTLIN
Permit Finaled 4/9/2021 JOHN JANSON
CofO Issued 4/9/2021 JOHN JANSON
Permit Finaled 4/9/2021 JOHN JANSON

Permit Application Clearance Information

Construction near power lines Cleared 9/12/2019 WALTER RAMIREZ
Address approval Cleared 9/30/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 9/30/2019 GUILLERMO PETRA
Hydrant and Access approval Cleared 9/30/2019 GILBERT URREA
Sewer availability Cleared 9/30/2019 GUILLERMO PETRA
Green Code Cleared 10/9/2019 DAVID MATSON
Low Impact Development Cleared 10/28/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 10/31/2019 JOHN LIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/12/2020 Corrections Issued DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 7/6/2020 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Rough 7/6/2020 Partial Approval DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 7/16/2020 Partial Approval DAVID SCANTLIN
BUILDING-Rough-Frame 9/3/2020 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 9/3/2020 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 9/3/2020 Approved DAVID SCANTLIN
PLUMBING-Rough 9/3/2020 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 9/17/2020 Partial Approval DAVID SCANTLIN
Green Building Rough 9/17/2020 Approved DAVID SCANTLIN
HVAC-Rough 9/17/2020 Approved DAVID SCANTLIN
PLUMBING-Rough 9/17/2020 Approved DAVID SCANTLIN
Drywall Nailing 10/6/2020 Approved DAVID SCANTLIN
Interior/Exterior Lathing 10/6/2020 Partial Approval DAVID SCANTLIN
Shower Pan 10/6/2020 Approved DAVID SCANTLIN
Interior/Exterior Lathing 10/14/2020 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 2/5/2021 Approved DAVID SCANTLIN
ELECTRICAL-Final 2/5/2021 Approved DAVID SCANTLIN
Final 2/5/2021 Corrections Issued DAVID SCANTLIN
Footing/Foundation/Slab 2/5/2021 Approved DAVID SCANTLIN
Green Building Final 2/5/2021 Not Ready for Inspection DAVID SCANTLIN
HVAC-Final 2/5/2021 Approved DAVID SCANTLIN
PLUMBING-Final 2/5/2021 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 2/5/2021 SGSOV Not Ready DAVID SCANTLIN
Service/Power Release 2/5/2021 Not Ready for Inspection DAVID SCANTLIN
Smoke Detectors 2/5/2021 Approved DAVID SCANTLIN
ELECTRICAL-Final 3/9/2021 Approved DAVID SCANTLIN
Final 3/9/2021 Not Ready for Inspection DAVID SCANTLIN
Gas Test 3/9/2021 Approved DAVID SCANTLIN
Green Building Final 3/9/2021 Approved DAVID SCANTLIN
HVAC-Final 3/9/2021 Approved DAVID SCANTLIN
PLUMBING-Final 3/9/2021 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 3/9/2021 SGSOV Approved DAVID SCANTLIN
Service/Power Release 3/9/2021 Not Ready for Inspection DAVID SCANTLIN
Final 3/30/2021 OK to Issue CofO DAVID SCANTLIN
Service/Power Release 3/30/2021 Approved DAVID SCANTLIN